Walker Construction & Materials LLC: KYTC bid record
Walker Construction & Materials LLC submitted 170 bids on Kentucky Transportation Cabinet contracts in the data, from 22 NOV 2019 to 24 SEP 2026, and was the low bidder on 87 of them (51%). When it was not low, its total sat a median +11% above the low bid.
- Owner
- Kentucky Transportation Cabinet
- Low bid volume
- $196,523,280
- Latest bid
- 24 SEP 2026
- Data through
- 22 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2019 | 5 | 4 | 80% |
| 2020 | 19 | 6 | 32% |
| 2021 | 25 | 16 | 64% |
| 2022 | 29 | 20 | 69% |
| 2023 | 32 | 12 | 38% |
| 2024 | 20 | 11 | 55% |
| 2025 | 22 | 10 | 45% |
| 2026 | 18 | 8 | 44% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 10 | 67 | 36 | 54% |
| District 9 | 36 | 15 | 42% |
| District 7 | 19 | 17 | 89% |
| District 12 | 10 | 3 | 30% |
| District 6 | 4 | 1 | 25% |
| District 5 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Asphalt material for tack | TON | 49 | 39 (80%) | $11.00 | $10.00 | |
| Asphalt pave milling & texturing | TON | 46 | 33 (72%) | $75.00 | $36.50 | |
| Delineator for guardrail BI directional white | EACH | 46 | 33 (72%) | $15.00 | $14.19 | |
| CL2 asph surf 0.38D PG64-22 | TON | 66 | 32 (48%) | $157.43 | $102.95 | |
| Asphalt seal aggregate | TON | 45 | 29 (64%) | $450.00 | $261.98 | |
| Temp seeding and protection | SY | 44 | 29 (66%) | $0.30 | $0.30 | |
| Temporary signs | SF | 49 | 26 (53%) | $13.00 | $6.50 | |
| Temp mulch | SY | 44 | 26 (59%) | $0.29 | $0.28 | |
| Leveling & wedging PG64-22 | TON | 42 | 26 (62%) | $113.00 | $94.00 | |
| Fuel adjustment | DOL | 26 | 26 (100%) | $1.00 | $1.00 | |
| Asphalt seal coat | TON | 42 | 25 (60%) | $1,700.00 | $1,370.39 | |
| Pave striping-perm paint-4 in | LF | 55 | 24 (44%) | $0.35 | $0.29 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Frederick & May Construction Co | 61 | 37 of 61 |
| Hinkle Construction Services LLC | 37 | 10 of 37 |
| Bush & Burchett Inc | 34 | 10 of 34 |
| Hinkle Contracting Company LLC | 28 | 15 of 28 |
| M & M Services Co Inc | 26 | 8 of 26 |
| Jave LLC | 20 | 3 of 20 |
| Mountain Enterprises Inc | 13 | 9 of 13 |
| Haydon Bridge Company Inc | 10 | 2 of 10 |
| Bti Contracting Inc DBA Blacktop Industries | 8 | 1 of 8 |
| American Pavements Inc | 7 | 2 of 7 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 24 SEP 2026 | 26-3039 | ASPHALT RESURFACING VARIOUS ROADS IN MENIFEE CO | 1 of 2 | $316,649 | Low, 16% under the second | |
| 03 SEP 2026 | 26-3034 | ASPHALT RESURFACING SNOW CREEK RD (KY 1028) | 1 of 2 | $208,444 | Low, 23% under the second | |
| 20 AUG 2026 | 26-2948 | CULVERT REPLACEMENT KY 0002 | 2 of 3 | $1,272,740 | +10% | |
| 20 AUG 2026 | 26-2235 | ASPHALT RESURFACING TARR RIDGE ROAD (KY 77) | 1 of 1 | $886,505 | Low | |
| 20 AUG 2026 | 26-2233 | CULVERT REPLACEMENT CULVERT REPLACMENTS ON KY 40 IN MARTIN COUNTY | 3 of 5 | $518,815 | +51% | |
| 20 AUG 2026 | 26-2172 | ASPHALT RESURFACING US 460 IN MONTGOMERY COUNTY | 1 of 1 | $838,280 | Low | |
| 21 MAY 2026 | 26-1511 | SLIDE REPAIR KY 7 | 2 of 3 | $3,974,000 | +1.0% | |
| 21 MAY 2026 | 26-1122 | GRADE & DRAIN WITH ASPHALT SURFACE KY 32 | 1 of 2 | $43,834,383 | Low, 15% under the second | |
| 21 MAY 2026 | 26-1513 | GRADE & DRAIN WITH BRIDGE JCPS ACCESS ROAD | 2 of 4 | $6,965,000 | +9.0% | |
| 23 APR 2026 | 26-5411 | BRIDGE REPLACEMENT CR 1464 | 2 of 8 | $737,037 | +8.0% | |
| 23 APR 2026 | 26-4113 | PAVEMENT (WITH ALTERNATES) IRVINE ROAD (KY 82) | 1 of 3 | $317,296 | Low, 2.0% under the second | |
| 26 MAR 2026 | 26-1508 | GRADE & DRAIN WITH ASPHALT SURFACE BROWN RIDGE RD. (KY 32) | 3 of 4 | $12,944,000 | +35% | |
| 26 MAR 2026 | 26-1112 | ASPHALT REHAB WITH BRIDGE (S) I-64 | 1 of 1 | $6,064,000 | Low | |
| 26 MAR 2026 | 26-2093 | ASPHALT RESURFACING OLD WINCHESTER ROAD (KY 15) | 2 of 2 | $193,700 | +7.0% | |
| 19 FEB 2026 | 26-5405 | BRIDGE REPLACEMENT CR 1380 | 2 of 5 | $929,000 | +33% | |
| 19 FEB 2026 | 26-5404 | BRIDGE REPLACEMENT KY 32 | 2 of 7 | $2,133,000 | +4.0% | |
| 19 FEB 2026 | 26-2092 | ASPHALT RESURFACING HARDWICKS CREEK ROAD (KY 1057) | 1 of 2 | $312,170 | Low, 6.0% under the second | |
| 29 JAN 2026 | 26-1001 | Fd04 035 0011 010-011 | 2 of 3 | $1,423,000 | +9.0% | |
| 11 DEC 2025 | 25-5399 | BRIDGE REPLACEMENT KY 292 | 1 of 5 | $3,173,879 | Low, 3.0% under the second | |
| 11 DEC 2025 | 25-2415 | PAVEMENT (WITH ALTERNATES) MCCAUSEY RIDGE ROAD (KY 3338) | 1 of 1 | $149,606 | Low | |
| 20 NOV 2025 | 25-3133 | ASPHALT RESURFACING BUNKER HILL/VAN THOMPSON RD (KY 537) | 1 of 1 | $524,500 | Low | |
| 23 OCT 2025 | 25-1025 | GRADE & DRAIN WITH ASPHALT SURFACE KY-7 | 3 of 3 | $6,430,000 | +27% | |
| 23 OCT 2025 | 25-3125 | ASPHALT RESURFACING MOORES FERRY (KY 211) | 1 of 2 | $439,868 | Low, 5.0% under the second | |
| 23 OCT 2025 | 25-2931 | BRIDGE WITH GRADE & DRAIN STURGEON CREEK BRIDGE (KY 1334) | 2 of 4 | $869,420 | +11% | |
| 25 SEP 2025 | 25-5389 | BRIDGE REPLACEMENT CR 1110 | 3 of 6 | $737,737 | +12% |
How this record was read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; KYTC's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.