KYTC contract 26-5411 bid tabulation
BRIDGE REPLACEMENT CR 1464. Let by Kentucky Transportation Cabinet on April 23, 2026. 8 bids received; low bid $685,508 by Frederick & May Construction Co, -36% against the engineer's estimate of $1,065,621.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 APR 2026
- Pay items
- 37
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Frederick & May Construction Co | $685,508 | Low | -36% |
| 2 | Walker Construction & Materials LLC | $737,037 | +8.0% | -31% |
| 3 | Hinkle Construction Services LLC | $799,517 | +17% | -25% |
| 4 | M & M Services Co Inc | $843,292 | +23% | -21% |
| 5 | Bush & Burchett Inc | $856,252 | +25% | -20% |
| 6 | Jave LLC | $921,248 | +34% | -14% |
| 7 | Adams Contracting LLC | $926,248 | +35% | -13% |
| 8 | Haydon Bridge Company Inc | $1,290,543 | +88% | +21% |
Engineer's estimate: $1,065,621.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Frederick & May Construction Co | 2. Walker Construction & Materials LLC | 3. Hinkle Construction Services LLC | 4. M & M Services Co Inc | 5. Bush & Burchett Inc | 6. Jave LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 306 | $86.50 | $55.00 | $91.00 | $65.00 | $86.50 | $89.10 |
| 0020 | CL2 asph base 1.00D PG64-22 | TON A A | 142 | $347.50 | $222.00 | $366.00 | $150.00 | $347.50 | $357.93 |
| 0030 | CL2 asph surf 0.38D PG64-22 | TON A A | 23 | $363.25 | $444.00 | $382.00 | $205.00 | $363.25 | $374.15 |
| 0040 | Asphalt material for tack | TON A A | 1 | $648.00 | $1,111.00 | $682.00 | $1,500.00 | $648.00 | $667.44 |
| 0050 | Culvert pipe-15 in | LF A A | 12 | $100.00 | $333.00 | $125.00 | $188.00 | $200.00 | $177.12 |
| 0060 | Drop box inlet type 15 | EACH A A | 1 | $4,000.00 | $5,555.00 | $4,040.00 | $9,800.00 | $5,000.00 | $7,977.78 |
| 0070 | Delineator for G/R BI directional white | EACH A A | 10 | $15.11 | $16.00 | $11.00 | $25.00 | $15.11 | $18.59 |
| 0080 | Barricade-type III | EACH A A | 8 | $75.00 | $159.00 | $140.00 | $300.00 | $175.00 | $123.00 |
| 0090 | Roadway excavation | CUYD A A | 228 | $25.00 | $75.00 | $55.00 | $85.00 | $35.00 | $79.95 |
| 0100 | G/R terminal section no 1 | EACH A A | 1 | $72.64 | $75.20 | $84.00 | $150.00 | $72.64 | $74.82 |
| 0110 | G/R end treatment type 7 | EACH A A | 3 | $2,053.08 | $2,055.00 | $2,129.00 | $2,800.00 | $2,053.08 | $2,114.67 |
| 0120 | Right-of-way monument type 1 | EACH A A | 8 | $155.40 | $156.00 | $175.00 | $250.00 | $155.40 | $160.06 |
| 0130 | Witness post | EACH A A | 8 | $120.46 | $121.00 | $33.00 | $250.00 | $120.46 | $124.10 |
| 0140 | Channel lining class II | TON A A | 136 | $38.00 | $66.00 | $51.00 | $105.00 | $50.00 | $79.95 |
| 0150 | Clearing and grubbing | LS A A | 1 | $33,787 | $34,000 | $13,000 | $15,000 | $40,000 | $33,395 |
| 0160 | Temporary signs | SQFT A A | 216 | $16.00 | $15.00 | $16.00 | $18.00 | $15.00 | $8.61 |
| 0170 | Edge key | LF A A | 25 | $75.25 | $99.00 | $79.00 | $20.00 | $75.25 | $77.51 |
| 0180 | Fabric-geotextile class 1 | SQYD A A | 281 | $3.00 | $2.00 | $3.00 | $3.00 | $3.00 | $3.69 |
| 0190 | Maintain & control traffic | LS A A | 1 | $2,500.00 | $10,000 | $35,000 | $19,500 | $5,000.00 | $3,690.00 |
| 0200 | Safeloading | CUYD A A | 2 | $500.00 | $777.00 | $1,015.00 | $4,500.00 | $500.00 | $615.00 |
| 0210 | Staking | LS A A | 1 | $6,000.00 | $7,000.00 | $6,000.00 | $9,000.00 | $7,000.00 | $11,685 |
| 0220 | Erosion control | LS A A | 1 | $5,000.00 | $5,000.00 | $5,600.00 | $11,500 | $7,000.00 | $9,840.00 |
| 0230 | G/R steel W beam-S face (7 FT post) | LF A A | 187.50 | $39.53 | $40.00 | $46.00 | $85.00 | $39.53 | $40.72 |
| 0240 | Remove structure | LS A A | 1 | $15,000 | $21,380 | $22,840 | $29,000 | $50,000 | $24,600 |
| 0250 | Armored edge for concrete | LF A A | 57 | $150.00 | $120.00 | $99.00 | $65.00 | $150.00 | $170.97 |
| 0260 | Structure excav-solid rock | CUYD A A | 180 | $100.00 | $155.00 | $111.00 | $105.00 | $75.00 | $215.25 |
| 0270 | Foundation preparation | LS A A | 1 | $21,000 | $33,333 | $48,360 | $68,000 | $65,000 | $50,123 |
| 0280 | Cyclopean stone rip rap | TON A A | 475 | $45.00 | $60.00 | $62.00 | $105.00 | $56.00 | $95.17 |
| 0290 | Concrete-class A | CUYD A A | 226 | $850.00 | $777.00 | $922.00 | $1,050.00 | $1,000.00 | $1,253.37 |
| 0300 | Concrete-class AA | CUYD A A | 28 | $2,000.00 | $2,900.00 | $2,950.00 | $1,580.00 | $2,500.00 | $1,950.78 |
| 0310 | Steel reinforcement | LB A A | 22,157 | $2.00 | $2.00 | $2.00 | $2.05 | $2.25 | $2.30 |
| 0320 | Steel reinforcement-epoxy coated | LB A A | 1,988 | $3.00 | $2.60 | $2.10 | $2.35 | $3.25 | $4.94 |
| 0330 | Precast PC box beam CB17-48 | LF A A | 230 | $425.00 | $444.00 | $420.00 | $450.00 | $500.00 | $439.11 |
| 0340 | Concrete sealing | SQFT A A | 3,092 | $2.50 | $2.00 | $2.20 | $3.00 | $2.00 | $2.80 |
| 0350 | Rail system side mounted MGS | LF A A | 75 | $207.21 | $210.00 | $227.00 | $285.00 | $207.21 | $213.43 |
| 0360 | Mobilization for concrete surf treatment | LS A A | 1 | $100.00 | $1,111.00 | $1,330.00 | $1,900.00 | $500.00 | $6,150.00 |
| 0370 | Demobilization | LS A A | 1 | $10,131 | $11,111 | $11,830 | $12,638 | $12,700 | $13,615 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of April 23, 2026. Compiled by Mirage Metrics.