KYTC letting results, April 23, 2026
17 contracts let by Kentucky Transportation Cabinet on April 23, 2026, $24,797,287 in low bids, a median of 3 bidders per contract. On the 17 with an engineer's estimate, the low bid came in under it 14 times; median low bid -13% against the estimate.
- Owner
- Kentucky Transportation Cabinet
- Contracts
- 17
- Low bids, total
- $24,797,287
- Data through
- 22 OCT 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 26-1510 | WIDENING THREE SPRINGS RD (KY 884) | 2 | Scotty'S Contracting & Stone LLC | $14,589,689 | $18,330,000 | +26% | -11% | KYTC | |
| 26-4505 | GRADE & DRAIN WITH ASPHALT SURFACE US HIGHWAY 60 (US 60) | 1 | Jim Smith Contracting Company LLC | $2,092,361 | -9.0% | KYTC | |||
| 26-4401 | ASPHALT RESURFACING EAST BROADWAY (US 150) | 5 | Hall Contracting of Kentucky Inc | $1,746,000 | $1,858,000 | +6.0% | -15% | KYTC | |
| 26-4111 | WIDENING KY HIGHWAY 90 (KY 90) | 1 | Rame Contracting LLC | $1,258,397 | +3.0% | KYTC | |||
| 26-4206 | PAVEMENT (WITH ALTERNATES) VARIOUS ROUTES IN DISTRICT 7 | 2 | Strawser Construction Inc | $870,164 | $888,289 | +2.0% | -10% | KYTC | |
| 26-5411 | BRIDGE REPLACEMENT CR 1464 | 8 | Frederick & May Construction Co | $685,508 | $737,037 | +8.0% | -36% | KYTC | |
| 26-5413 | BRIDGE REPLACEMENT KY 1102 | 8 | Landmark Construction LLC | $622,765 | $691,687 | +11% | -31% | KYTC | |
| 26-5410 | BRIDGE REPLACEMENT CR 1401 | 6 | Galusha Contracting LLC | $547,195 | $635,871 | +16% | -18% | KYTC | |
| 26-5412 | BRIDGE REPAIRS KY 56 | 5 | Intech Contracting LLC | $505,868 | $548,268 | +8.0% | +1.0% | KYTC | |
| 26-4509 | GUARDRAIL KY HIGHWAY 81 (KY 81) | 3 | N W K Construction Inc | $405,415 | $442,684 | +9.0% | -8.0% | KYTC | |
| 26-4114 | TRAFFIC SIGNAL SYSTEMS WINCHESTER ROAD (US 60) | 1 | Davis H Elliot Construction Company Inc | $362,220 | +11% | KYTC | |||
| 26-4113 | PAVEMENT (WITH ALTERNATES) IRVINE ROAD (KY 82) | 3 | Walker Construction & Materials LLC | $317,296 | $324,231 | +2.0% | -21% | KYTC | |
| 26-4410 | SIGNS VARIOUS ROUTES IN DISTRICT 5 | 5 | George B Stone Co LLC | $249,725 | $315,750 | +26% | -40% | KYTC | |
| 26-4200 | ASPHALT SURFACE WITH GRADE & DRAIN OLD FRANKFORT PIKE (KY 1681) | 2 | L-M Asphalt Partners LTD D/B/A Ats Construction | $176,163 | $399,998 | +127% | -13% | KYTC | |
| 26-4507 | GUARDRAIL KY HIGHWAY 416 (KY 416) | 4 | George B Stone Co LLC | $154,270 | $164,545 | +7.0% | -12% | KYTC | |
| 26-4508 | GUARDRAIL KY HIGHWAY 81 (KY 81) | 4 | N W K Construction Inc | $139,000 | $145,223 | +4.0% | -18% | KYTC | |
| 26-4506 | PAINTED PAVEMENT STRIPING VARIOUS ROUTES IN DISTRICT 2 | 2 | Reynolds-Central Seal A Joint Venture | $75,250 | $92,958 | +24% | -71% | KYTC |
Gap is the second bid over the low bid. Where a contract shows fewer bids than KYTC received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.