KYTC contract 25-5389 bid tabulation
BRIDGE REPLACEMENT CR 1110. Let by Kentucky Transportation Cabinet on September 25, 2025. 6 bids received; low bid $660,669 by Todd Johnson Contracting Inc, -21% against the engineer's estimate of $840,314.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 25 SEP 2025
- Pay items
- 40
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Todd Johnson Contracting Inc | $660,669 | Low | -21% |
| 2 | Hinkle Construction Services LLC | $708,499 | +7.0% | -16% |
| 3 | Walker Construction & Materials LLC | $737,737 | +12% | -12% |
| 4 | Frederick & May Construction Co | $754,450 | +14% | -10% |
| 5 | Jave LLC | $769,304 | +16% | -8.0% |
| 6 | M & M Services Co Inc | $926,013 | +40% | +10% |
Engineer's estimate: $840,314.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Todd Johnson Contracting Inc | 2. Hinkle Construction Services LLC | 3. Walker Construction & Materials LLC | 4. Frederick & May Construction Co | 5. Jave LLC | 6. M & M Services Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 417 | $48.00 | $49.00 | $60.00 | $115.00 | $80.30 | $65.00 |
| 0020 | Asphalt seal aggregate | TON A A | 5 | $575.00 | $526.00 | $480.00 | $2,500.00 | $1,616.00 | $1,250.00 |
| 0030 | Asphalt seal coat | TON A A | 1 | $2,875.00 | $2,630.00 | $1,250.00 | $2,000.00 | $2,222.00 | $2,500.00 |
| 0040 | CL2 asph base 1.00D PG64-22 | TON A A | 228 | $184.00 | $168.00 | $155.00 | $200.00 | $145.44 | $155.00 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A A | 36 | $391.00 | $358.00 | $300.00 | $360.00 | $252.50 | $155.00 |
| 0060 | Asphalt material for tack | TON A A | 1 | $1.15 | $1.05 | $500.00 | $1,000.00 | $1.01 | $1,500.00 |
| 0070 | Entrance pipe-18 in | LF A A | 36 | $97.47 | $95.00 | $90.00 | $75.00 | $119.90 | $125.00 |
| 0080 | Barricade-type III | EACH A A | 8 | $175.00 | $148.00 | $160.00 | $100.00 | $101.00 | $250.00 |
| 0090 | Roadway excavation | CUYD A A | 463 | $50.00 | $52.00 | $55.00 | $60.00 | $62.70 | $185.00 |
| 0100 | Granular embankment | CUYD A A | 75 | $52.00 | $132.00 | $85.00 | $70.00 | $127.60 | $70.00 |
| 0110 | Right-of-way monument type 1 | EACH A A | 11 | $294.91 | $150.00 | $257.00 | $256.44 | $259.00 | $280.00 |
| 0120 | Witness post | EACH A A | 11 | $268.25 | $122.00 | $234.00 | $233.26 | $235.59 | $240.00 |
| 0130 | Channel lining class II | TON A A | 345 | $58.00 | $53.00 | $65.00 | $50.00 | $99.00 | $72.00 |
| 0140 | Clearing and grubbing | LS A A | 1 | $8,000.00 | $18,500 | $15,000 | $30,000 | $11,022 | $15,000 |
| 0150 | Temporary signs | SQFT A A | 216 | $14.63 | $14.20 | $13.00 | $14.00 | $8.08 | $15.00 |
| 0160 | Edge key | LF A A | 24 | $28.75 | $26.00 | $75.00 | $55.00 | $121.20 | $20.00 |
| 0170 | Fabric-geotextile class 1 | SQYD A A | 550 | $4.00 | $3.10 | $3.00 | $3.00 | $7.58 | $4.00 |
| 0180 | Maintain & control traffic | LS A A | 1 | $15,000 | $10,000 | $15,000 | $5,000.00 | $17,685 | $38,000 |
| 0190 | Portable changeable message sign | EACH A A | 2 | $1,694.00 | $2,500.00 | $2,300.00 | $3,000.00 | $2,248.26 | $3,600.00 |
| 0200 | Staking | LS A A | 1 | $8,000.00 | $5,350.00 | $10,000 | $7,500.00 | $4,950.00 | $12,500 |
| 0210 | Remove structure | LS A A | 1 | $40,000 | $19,165 | $23,500 | $10,000 | $19,800 | $45,000 |
| 0215 | Structure excav-solid rock | CUYD A A | 200 | $105.00 | $60.00 | $10.00 | $100.00 | $174.90 | $425.00 |
| 0220 | SBM alum sheet signs .080 in | SQFT A A | 12 | $92.08 | $115.00 | $81.00 | $80.07 | $80.87 | $85.00 |
| 0230 | Steel post type 1 | LF A A | 40 | $39.11 | $47.00 | $33.80 | $31.44 | $31.75 | $35.00 |
| 0240 | Erosion control | LS A A | 1 | $10,000 | $4,770.00 | $10,000 | $5,000.00 | $7,975.00 | $15,000 |
| 0250 | Barcode sign inventory | EACH A A | 4 | $74.15 | $57.00 | $65.00 | $64.48 | $65.12 | $70.00 |
| 0260 | Electronic delivery MGMT system - agg | LS A A | 1 | $5,000.00 | $105.00 | $500.00 | $500.00 | $2,750.00 | $15,000 |
| 0270 | Structure granular backfill | CUYD A A | 364 | $56.00 | $125.00 | $85.00 | $70.00 | $108.90 | $65.00 |
| 0280 | Armored edge for concrete | LF A A | 46 | $85.00 | $80.00 | $105.00 | $160.00 | $108.90 | $85.00 |
| 0290 | Foundation preparation | LS A A | 1 | $25,000 | $25,950 | $58,000 | $35,000 | $46,794 | $38,000 |
| 0300 | Cyclopean stone rip rap | TON A A | 525 | $75.00 | $100.00 | $88.00 | $65.00 | $99.00 | $90.00 |
| 0310 | Concrete-class A | CUYD A A | 174 | $1,040.00 | $980.00 | $900.00 | $900.00 | $969.10 | $1,150.00 |
| 0320 | Concrete-class AA | CUYD A A | 16 | $1,400.00 | $3,675.00 | $4,900.00 | $4,500.00 | $2,075.70 | $1,650.00 |
| 0330 | Steel reinforcement | LB A A | 14,586 | $1.97 | $1.92 | $2.00 | $3.00 | $2.42 | $2.05 |
| 0340 | Steel reinforcement-epoxy coated | LB A A | 1,275 | $2.28 | $2.02 | $2.00 | $4.00 | $1.27 | $2.32 |
| 0350 | Precast PC box beam CB12-48 | LF A A | 128 | $354.12 | $390.00 | $400.00 | $350.00 | $369.60 | $465.00 |
| 0360 | Concrete sealing | SQFT A A | 1,991 | $2.00 | $2.60 | $2.00 | $5.00 | $3.04 | $3.00 |
| 0370 | Mobilization for concrete surf treatment | LS A A | 1 | $3,000.00 | $1,325.00 | $750.00 | $2,500.00 | $2,750.00 | $1,800.00 |
| 0380 | Mobilization | LS A A | 1 | $15,430 | $32,030 | $33,675 | $32,970 | $35,842 | $25,000 |
| 0390 | Demobilization | LS A A | 1 | $9,896.00 | $12,000 | $12,500 | $11,150 | $10,839 | $13,981 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of September 25, 2025. Compiled by Mirage Metrics.