Todd Johnson Contracting Inc: KYTC bid record
Todd Johnson Contracting Inc submitted 12 bids on Kentucky Transportation Cabinet contracts in the data, from 21 FEB 2020 to 25 SEP 2025, and was the low bidder on 4 of them (33%). When it was not low, its total sat a median +10% above the low bid.
- Owner
- Kentucky Transportation Cabinet
- Low bid volume
- $2,210,358
- Latest bid
- 25 SEP 2025
- Data through
- 22 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 3 | 1 | 33% |
| 2024 | 6 | 2 | 33% |
| 2025 | 3 | 1 | 33% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 5 | 2 | 0 | 0% |
| District 7 | 2 | 2 | 100% |
| District 4 | 2 | 1 | 50% |
| District 6 | 2 | 0 | 0% |
| District 3 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Concrete-class AA | CY | 6 | 4 (67%) | $1,015.00 | $1,716.02 | |
| Cyclopean stone rip rap | TON | 6 | 3 (50%) | $51.71 | $60.00 | |
| Armored edge for concrete | LF | 6 | 2 (33%) | $77.83 | $120.00 | |
| Granular embankment | CY | 5 | 2 (40%) | $48.30 | $85.00 | |
| Concrete sealing | SF | 7 | 1 (14%) | $2.33 | $3.00 | |
| Rail system side mounted MGS | LF | 6 | 1 (17%) | $268.57 | $231.46 | |
| Guardrail-steel W beam-S face | LF | 5 | 1 (20%) | $38.40 | $38.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| M & M Services Co Inc | 10 | 5 of 10 |
| Hinkle Construction Services LLC | 9 | 2 of 9 |
| Jave LLC | 9 | 3 of 9 |
| Galusha Contracting LLC | 7 | 3 of 7 |
| Scott and Murphy Inc | 4 | 3 of 4 |
| Cambry Contracting Inc | 4 | 1 of 4 |
| Frederick & May Construction Co | 4 | 0 of 4 |
| R G F Inc | 3 | 0 of 3 |
| Walker Construction & Materials LLC | 3 | 1 of 3 |
| Bush & Burchett Inc | 3 | 2 of 3 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 25 SEP 2025 | 25-5391 | BRIDGE REPLACEMENT CR 1117 | 4 of 4 | $644,285 | +30% | |
| 25 SEP 2025 | 25-5389 | BRIDGE REPLACEMENT CR 1110 | 1 of 6 | $660,669 | Low, 7.0% under the second | |
| 21 AUG 2025 | 25-2988 | BRIDGE REPLACEMENT STATE HWY 3630 (KY 3630) | 6 of 7 | $793,516 | +22% | |
| 14 NOV 2024 | 24-2943 | District 7 | BRIDGE REPLACEMENT BIRDIE ROAD (KY 395) | 1 of 9 | $710,383 | Low, 4.0% under the second |
| 14 NOV 2024 | 24-2906 | District 4 | BRIDGE WITH GRADE & DRAIN SHORT LINE PIKE (KY 1195) | 1 of 7 | $432,884 | Low, 27% under the second |
| 26 SEP 2024 | 24-2995 | District 3 | BRIDGE WITH GRADE, DRAIN & SURFACE STRINGTOWN FLIPPIN ROAD (KY 678) | 3 of 4 | $839,515 | +4.0% |
| 22 AUG 2024 | 24-2952 | District 6 | BRIDGE REPLACEMENT ELLISTON-MT. ZION ROAD (KY 1942) | 3 of 7 | $984,627 | +9.0% |
| 18 JUL 2024 | 24-5358 | District 6 | BRIDGE REPLACEMENT KY 491 | 3 of 8 | $791,168 | +9.0% |
| 18 JUL 2024 | 24-5356 | District 5 | BRIDGE REPLACEMENT CR 1004 | 5 of 6 | $933,264 | +10% |
| 20 NOV 2020 | 20-5188 | District 4 | BRIDGE SUPERSTRUCTURE REPLACEMENT WATSON SCHOOL ROAD | 9 of 10 | $259,138 | +46% |
| 23 OCT 2020 | 20-5175 | District 7 | BRIDGE REPLACEMENT KY 1984 OVER TATES CREEK | 1 of 11 | $406,422 | Low, 18% under the second |
| 21 FEB 2020 | 20-5168 | District 5 | BRIDGE REPAIRS CR 1128 | 3 of 9 | $498,278 | +9.0% |
How this record was read
KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; KYTC's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.