KYTC contract 25-2988 bid tabulation
BRIDGE REPLACEMENT STATE HWY 3630 (KY 3630). Let by Kentucky Transportation Cabinet on August 21, 2025. 7 bids received; low bid $648,801 by Irvine Contracting Limited Liability Company, -30% against the engineer's estimate of $928,448.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 AUG 2025
- Pay items
- 33
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Irvine Contracting Limited Liability Company | $648,801 | Low | -30% |
| 2 | Bush & Burchett Inc | $716,291 | +10% | -23% |
| 3 | M & M Services Co Inc | $756,657 | +17% | -19% |
| 4 | Jave LLC | $761,127 | +17% | -18% |
| 5 | Hinkle Construction Services LLC | $790,402 | +22% | -15% |
| 6 | Todd Johnson Contracting Inc | $793,516 | +22% | -15% |
| 7 | Frederick & May Construction Co | $823,896 | +27% | -11% |
Engineer's estimate: $928,448.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Irvine Contracting Limited Liability Company | 2. Bush & Burchett Inc | 3. M & M Services Co Inc | 4. Jave LLC | 5. Hinkle Construction Services LLC | 6. Todd Johnson Contracting Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Traffic bound base | TON A A | 14 | $118.00 | $50.00 | $65.00 | $107.38 | $80.00 | $85.00 |
| 0020 | Edge key | LF A A | 77 | $50.00 | $50.00 | $15.00 | $51.00 | $52.65 | $57.50 |
| 0030 | Bridge overlay approach pavement | SQYD A A | 455 | $88.00 | $88.00 | $125.00 | $89.76 | $93.00 | $101.20 |
| 0040 | Sawcut pavement | LF A A | 267 | $1.75 | $10.00 | $15.00 | $11.80 | $7.30 | $7.00 |
| 0050 | Delineator for guardrail BI directional white | EACH A A | 6 | $14.80 | $13.00 | $15.00 | $13.26 | $79.00 | $16.25 |
| 0060 | Roadway excavation | CUYD A A | 60 | $144.00 | $100.00 | $85.00 | $212.40 | $72.00 | $500.00 |
| 0070 | Granular embankment | CUYD A A | 103 | $97.00 | $60.00 | $65.00 | $143.96 | $118.00 | $480.00 |
| 0080 | Guardrail-steel W beam-S face | LF A A | 162.50 | $56.73 | $27.00 | $59.00 | $27.54 | $79.00 | $31.05 |
| 0090 | Guardrail-steel W beam-S face A | LF A A | 100 | $67.78 | $55.00 | $70.00 | $35.70 | $79.00 | $63.25 |
| 0100 | Guardrail terminal section no 1 | EACH A A | 2 | $80.72 | $110.00 | $85.00 | $112.20 | $79.00 | $126.50 |
| 0110 | Temporary signs | SQFT A A | 180 | $12.00 | $15.00 | $12.00 | $7.14 | $13.30 | $15.90 |
| 0120 | Maintain & control traffic | LS A A | 1 | $24,000 | $20,000 | $18,000 | $21,420 | $81,300 | $35,989 |
| 0130 | Staking | LS A A | 1 | $3,000.00 | $10,000 | $12,000 | $7,670.00 | $4,515.00 | $3,500.00 |
| 0135 | Pave striping-perm paint-6 in | LF A A | 980 | $4.50 | $2.00 | $1.25 | $4.69 | $2.10 | $2.30 |
| 0140 | Remove superstructure | LS A A | 1 | $24,845 | $75,000 | $48,000 | $25,342 | $26,540 | $40,000 |
| 0150 | Erosion control | LS A A | 1 | $7,000.00 | $5,000.00 | $15,000 | $16,390 | $14,870 | $16,540 |
| 0160 | Structure granular backfill | CUYD A A | 112 | $88.00 | $85.00 | $72.00 | $129.80 | $153.00 | $478.00 |
| 0170 | Armored edge for concrete | LF A A | 48 | $89.00 | $100.00 | $92.00 | $145.14 | $77.00 | $96.46 |
| 0180 | Structure excav-solid rock | CUYD A A | 31 | $181.00 | $100.00 | $350.00 | $215.94 | $154.00 | $175.00 |
| 0190 | Foundation preparation | LS A A | 1 | $32,000 | $50,000 | $28,000 | $39,978 | $35,050 | $37,850 |
| 0200 | Cyclopean stone rip rap | TON A A | 264 | $58.00 | $40.00 | $69.00 | $75.52 | $108.00 | $80.00 |
| 0210 | Test piles | LF A A | 26 | $116.00 | $200.00 | $350.00 | $171.10 | $196.00 | $200.00 |
| 0220 | Pre-drilling for piles | LF A A | 126 | $510.00 | $275.00 | $285.00 | $587.86 | $375.00 | $450.78 |
| 0230 | Piles-steel HP14X89 | LF A A | 133 | $103.00 | $150.00 | $225.00 | $171.10 | $200.00 | $173.74 |
| 0240 | Concrete-class A | CUYD A A | 73.90 | $1,100.00 | $1,000.00 | $1,250.00 | $1,192.98 | $1,265.00 | $980.76 |
| 0250 | Concrete-class AA | CUYD A A | 43.80 | $1,300.00 | $1,500.00 | $1,450.00 | $1,459.66 | $1,700.00 | $1,258.09 |
| 0260 | Steel reinforcement | LB A A | 3,458 | $2.05 | $2.00 | $2.25 | $2.24 | $2.00 | $1.72 |
| 0270 | Steel reinforcement-epoxy coated | LB A A | 6,908 | $2.20 | $2.00 | $2.05 | $2.48 | $2.15 | $2.00 |
| 0280 | Precast PC box beam CB27-48 | LF A A | 471 | $315.13 | $375.00 | $375.00 | $341.02 | $336.00 | $258.26 |
| 0290 | Concrete sealing | SQFT A A | 3,124 | $1.50 | $2.00 | $3.00 | $2.70 | $1.95 | $3.98 |
| 0300 | Deep beam bridge guardrail | LF A A | 146 | $203.90 | $270.00 | $315.00 | $318.60 | $245.00 | $310.50 |
| 0310 | Mobilization for concrete surf treatment | LS A A | 1 | $1,000.00 | $1,000.00 | $2,500.00 | $5,900.00 | $1,500.00 | $1,500.00 |
| 0320 | Demobilization | LS A A | 1 | $10,075 | $10,600 | $11,890 | $11,248 | $12,000 | $11,757 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of August 21, 2025. Compiled by Mirage Metrics.