KYTC contract 25-5391 bid tabulation

BRIDGE REPLACEMENT CR 1117. Let by Kentucky Transportation Cabinet on September 25, 2025. 4 bids received; low bid $494,439 by M & M Services Co Inc, -46% against the engineer's estimate of $912,431.

Owner
Kentucky Transportation Cabinet
Letting
25 SEP 2025
Pay items
35
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1M & M Services Co Inc$494,439Low-46%
2Jave LLC$610,338+23%-33%
3Bush & Burchett Inc$612,309+24%-33%
4Todd Johnson Contracting Inc$644,285+30%-29%
KYTC contract 25-5391: bids by rank

Engineer's estimate: $912,431.

Bid tabulation

LinePay itemUnitQuantity1. M & M Services Co Inc2. Jave LLC3. Bush & Burchett Inc4. Todd Johnson Contracting Inc
0010Dga baseTON A A127$55.00$87.50$65.00$48.00
0020Asphalt seal aggregateTON A A0.60$1,500.00$1,575.00$1,000.00$1,725.00
0030Asphalt seal coatTON A A0.10$2,000.00$1,575.00$1,000.00$1,725.00
0040CL2 asph base 1.00D PG64-22TON A A115$155.00$288.75$275.00$316.25
0050CL2 asph surf 0.38D PG64-22TON A A6$155.00$1,050.00$1,000.00$1,150.00
0060Asphalt material for tackTON A A0.10$2,000.00$10.50$10.00$11.50
0070Granular embankmentCUYD A A13$65.00$265.00$100.00$60.00
0080Delineator for guardrail BI directional whiteEACH A A6$15.00$21.00$20.00$22.34
0090Barricade-type IIIEACH A A4$250.00$105.00$200.00$318.00
0100Guardrail terminal section no 1EACH A A4$150.00$183.75$175.00$116.02
0110Temp guardrailLF A A487.50$35.00$26.25$25.00$31.12
0120Clearing and grubbingLS A A1$15,000$49,550$60,000$8,000.00
0130Temporary signsSQFT A A144$15.00$10.50$15.00$14.63
0140Object marker type 2EACH A A4$185.00$157.50$150.00$412.70
0150Edge keyLF A A25$15.00$100.80$96.00$110.40
0160Maintain & control trafficLS A A1$15,000$1,575.00$1,000.00$29,000
0170Diversions (by-pass detours)LS A A1$68,000$85,575$80,000$120,000
0180Portable changeable message signEACH A A2$3,600.00$2,337.30$750.00$1,694.00
0190StakingLS A A1$11,500$6,250.00$5,000.00$8,000.00
0200Remove structureLS A A1$28,000$18,150$50,000$42,000
0210Foundation preparationLS A A1$19,000$30,875$40,000$28,000
0220Erosion controlLS A A1$9,200.00$12,313$10,000$6,000.00
0230Structure granular backfillCUYD A A100$58.00$118.13$1.00$59.00
0240Armored edge for concreteLF A A32$80.00$146.25$130.00$110.00
0250Cyclopean stone rip rapTON A A40$85.00$111.25$65.00$75.00
0260Test pilesLF A A44$350.00$149.38$200.00$185.00
0270Pre-drilling for pilesLF A A130$200.00$462.00$300.00$483.00
0280Piles-steel HP12X53LF A A170$205.00$149.38$100.00$102.00
0290Concrete-class ACUYD A A65$1,200.00$1,227.50$1,500.00$1,172.00
0300Concrete-class AACUYD A A18$1,650.00$2,803.75$2,500.00$1,600.00
0310Steel reinforcement-epoxy coatedLB A A6,400$2.35$2.55$2.00$2.28
0320Precast PC box beam CB12-48LF A A128$340.00$396.25$450.00$393.18
0330Concrete sealingSQFT A A1,650$5.00$2.81$2.00$2.03
0340Mobilization for concrete surf treatmentLS A A1$1,800.00$3,547.50$1,000.00$3,640.00
0350DemobilizationLS A A1$7,306.99$9,019.78$9,100.00$47,406
KYTC contract 25-5391: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of September 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy