KYTC contract 25-5399 bid tabulation
BRIDGE REPLACEMENT KY 292. Let by Kentucky Transportation Cabinet on December 11, 2025. 5 bids received; low bid $3,173,879 by Walker Construction & Materials LLC, -15% against the engineer's estimate of $3,737,981.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 11 DEC 2025
- Pay items
- 57
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Walker Construction & Materials LLC | $3,173,879 | Low | -15% |
| 2 | Bush & Burchett Inc | $3,275,326 | +3.0% | -12% |
| 3 | Orders Construction Company Inc | $3,571,156 | +13% | -4.0% |
| 4 | Frederick & May Construction Co | $3,677,505 | +16% | -2.0% |
| 5 | Hinkle Construction Services LLC | $3,780,331 | +19% | +1.0% |
Engineer's estimate: $3,737,981.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Walker Construction & Materials LLC | 2. Bush & Burchett Inc | 3. Orders Construction Company Inc | 4. Frederick & May Construction Co | 5. Hinkle Construction Services LLC |
|---|---|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 609 | $68.25 | $68.25 | $74.00 | $68.25 | $60.00 |
| 0020 | Crushed aggregate size no 2 | TON A A | 100 | $65.00 | $50.00 | $66.00 | $66.00 | $58.00 |
| 0030 | Asphalt seal aggregate | TON A A | 6.30 | $775.00 | $775.00 | $840.00 | $775.00 | $815.00 |
| 0040 | Asphalt seal coat | TON A A | 0.76 | $3,880.00 | $3,880.00 | $4,200.00 | $3,880.00 | $4,080.00 |
| 0050 | Leveling & wedging PG64-22 | TON A A | 83 | $261.85 | $261.85 | $280.00 | $261.85 | $275.00 |
| 0060 | CL2 asph base 0.75D PG64-22 | TON A A | 215 | $249.85 | $249.85 | $270.00 | $249.85 | $260.00 |
| 0070 | CL2 asph surf 0.38D PG64-22 | TON A A | 82 | $261.85 | $261.85 | $280.00 | $261.85 | $275.00 |
| 0080 | Asphalt material for tack | TON A A | 0.60 | $925.00 | $925.00 | $1,000.00 | $925.00 | $975.00 |
| 0090 | Dga base | TON A A | 640 | $68.25 | $68.25 | $69.00 | $68.25 | $60.00 |
| 0100 | CL2 asph base 0.75D PG64-22 | TON A A | 168 | $249.85 | $249.85 | $270.00 | $249.85 | $260.00 |
| 0110 | Delineator for guardrail BI directional white | EACH A A | 14 | $13.00 | $13.00 | $14.00 | $13.00 | $11.50 |
| 0120 | Barricade-type III | EACH A A | 4 | $175.00 | $200.00 | $380.00 | $150.00 | $160.00 |
| 0130 | Roadway excavation | CUYD A A | 7,350 | $29.95 | $21.66 | $27.00 | $20.00 | $35.00 |
| 0140 | Guardrail-steel W beam-S face | LF A A | 275 | $26.00 | $26.00 | $28.00 | $26.00 | $46.00 |
| 0150 | Guardrail terminal section no 1 | EACH A A | 1 | $110.00 | $110.00 | $120.00 | $110.00 | $105.00 |
| 0160 | Guardrail end treatment type 1 | EACH A A | 2 | $3,800.00 | $3,800.00 | $4,100.00 | $3,800.00 | $4,475.00 |
| 0170 | Guardrail end treatment type 7 | EACH A A | 1 | $2,100.00 | $2,100.00 | $2,300.00 | $2,100.00 | $2,050.00 |
| 0180 | Remove guardrail | LF A A | 137.50 | $5.00 | $5.00 | $41.00 | $5.00 | $14.75 |
| 0190 | Right-of-way monument type 1 | EACH A A | 5 | $275.00 | $200.00 | $96.00 | $275.00 | $155.00 |
| 0200 | Witness post | EACH A A | 3 | $275.00 | $200.00 | $160.00 | $275.00 | $135.00 |
| 0210 | Clearing and grubbing | LS A A | 1 | $50,000 | $10,000 | $86,000 | $101,406 | $15,400 |
| 0220 | Temporary signs | SQFT A A | 85.25 | $25.00 | $40.00 | $81.00 | $24.50 | $24.00 |
| 0230 | Object marker type 2 | EACH A A | 2 | $400.00 | $400.00 | $430.00 | $400.00 | $420.00 |
| 0240 | Edge key | LF A A | 60 | $56.75 | $56.75 | $62.00 | $56.75 | $60.00 |
| 0250 | Fabric-geotextile class 2 | SQYD A A | 72 | $8.00 | $4.00 | $2.00 | $5.00 | $2.75 |
| 0260 | Maintain & control traffic | LS A A | 1 | $25,000 | $32,000 | $31,000 | $95,000 | $170,000 |
| 0270 | Diversions (by-pass detours) | LS A A | 1 | $263,000 | $400,000 | $380,000 | $300,000 | $640,000 |
| 0280 | Portable changeable message sign | EACH A A | 4 | $6,000.00 | $3,000.00 | $3,800.00 | $5,200.00 | $3,500.00 |
| 0290 | Staking | LS A A | 1 | $13,000 | $15,000 | $90,000 | $20,000 | $13,200 |
| 0300 | SBM alum sheet signs .080 in | SQFT A A | 12.50 | $48.00 | $48.00 | $52.00 | $48.00 | $50.00 |
| 0310 | Steel post type 1 | LF A A | 10 | $40.00 | $40.00 | $43.00 | $40.00 | $42.00 |
| 0320 | Pave striping-perm paint-4 in | LF A A | 1,460 | $2.00 | $1.50 | $2.30 | $1.50 | $1.60 |
| 0330 | Object marker TY 3 | EACH A A | 2 | $75.00 | $75.00 | $81.00 | $75.00 | $79.00 |
| 0340 | Erosion control | LS A A | 1 | $12,000 | $8,000.00 | $35,000 | $20,000 | $5,800.00 |
| 0350 | Pave mark temp paint stop bar-24 in | LF A A | 6 | $125.00 | $25.00 | $39.00 | $25.00 | $26.00 |
| 0360 | Barcode sign inventory | EACH A A | 2 | $50.00 | $50.00 | $54.00 | $50.00 | $53.00 |
| 0370 | Remove and reinstall | LS A A | 1 | $3,500.00 | $10,000 | $5,300.00 | $5,000.00 | $2,400.00 |
| 0380 | Electronic delivery MGMT system - agg | LS A A | 1 | $1,000.00 | $1,000.00 | $5,600.00 | $1,500.00 | $1,000.00 |
| 0390 | Structure granular backfill | CUYD A A | 2,708 | $82.00 | $100.00 | $110.00 | $100.00 | $125.00 |
| 0400 | Channel lining class IA | TON A A | 328 | $65.00 | $60.00 | $110.00 | $350.00 | $210.00 |
| 0410 | Remove structure | LS A A | 1 | $33,000 | $20,000 | $47,000 | $15,000 | $51,000 |
| 0420 | Armored edge for concrete | LF A A | 52.30 | $150.00 | $100.00 | $150.00 | $150.00 | $95.00 |
| 0430 | Foundation preparation | LS A A | 1 | $125,000 | $250,000 | $200,000 | $225,000 | $73,600 |
| 0440 | Cyclopean stone rip rap | TON A A | 2,260 | $60.00 | $65.00 | $77.00 | $75.00 | $75.00 |
| 0450 | Test piles | LF A A | 280 | $110.00 | $85.00 | $41.00 | $135.00 | $68.00 |
| 0460 | Piles-steel HP12X53 | LF A A | 3,441 | $110.00 | $85.00 | $75.00 | $125.00 | $75.00 |
| 0470 | Pile points-12 in | EACH A A | 88 | $155.00 | $150.00 | $170.00 | $225.00 | $180.00 |
| 0480 | Concrete-class A | CUYD A A | 550.70 | $775.00 | $850.00 | $830.00 | $825.00 | $820.00 |
| 0490 | Concrete-class AA | CUYD A A | 122.70 | $1,775.00 | $1,300.00 | $1,600.00 | $1,650.00 | $1,640.00 |
| 0500 | Steel reinforcement | LB A A | 45,459 | $1.80 | $2.00 | $1.70 | $2.20 | $1.85 |
| 0510 | Steel reinforcement-epoxy coated | LB A A | 38,038 | $2.00 | $2.00 | $1.90 | $2.80 | $1.95 |
| 0520 | Concrete sealing | SQFT A A | 7,788 | $2.00 | $2.00 | $4.80 | $3.00 | $1.40 |
| 0530 | PPC I-beam HN 48-49 | LF A A | 304.50 | $890.00 | $875.00 | $890.00 | $900.00 | $990.00 |
| 0540 | Rail system type T631 | LF A A | 206 | $194.50 | $194.50 | $200.00 | $194.50 | $160.00 |
| 0550 | Mobilization for concrete surf treatment | LS A A | 1 | $1,500.00 | $100.00 | $11,000 | $1,000.00 | $1,800.00 |
| 0560 | Mobilization | LS A A | 1 | $145,000 | $150,000 | $165,000 | $150,000 | $177,400 |
| 0570 | Demobilization | LS A A | 1 | $47,250 | $50,000 | $51,000 | $54,348 | $53,520 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of December 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.