KYTC contract 26-1511 bid tabulation
SLIDE REPAIR KY 7. Let by Kentucky Transportation Cabinet on May 21, 2026. 3 bids received; low bid $3,936,305 by Frederick & May Construction Co, -14% against the engineer's estimate of $4,602,061.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 MAY 2026
- Pay items
- 78
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Frederick & May Construction Co | $3,936,305 | Low | -14% |
| 2 | Walker Construction & Materials LLC | $3,974,000 | +1.0% | -14% |
| 3 | Hinkle Construction Services LLC | $5,428,137 | +38% | +18% |
Engineer's estimate: $4,602,061.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Frederick & May Construction Co | 2. Walker Construction & Materials LLC | 3. Hinkle Construction Services LLC |
|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 1,875 | $56.76 | $56.75 | $61.00 |
| 0020 | Asphalt seal aggregate | TON A A | 11 | $354.50 | $354.50 | $381.00 |
| 0030 | Asphalt seal coat | TON A A | 1.30 | $1,950.00 | $1,950.00 | $2,100.00 |
| 0040 | Leveling & wedging PG64-22 | TON A A | 120 | $218.10 | $218.10 | $234.50 |
| 0050 | CL3 asph base 1.00D PG64-22 | TON A A | 1,650 | $196.15 | $196.15 | $211.00 |
| 0060 | CL3 asph surf 0.38B PG64-22 | TON A A | 475 | $229.80 | $229.80 | $247.00 |
| 0070 | Joint adhesive | LF A A | 3,600 | $2.25 | $2.25 | $2.40 |
| 0080 | Asphalt material for tack non-tracking | TON A A | 6 | $985.00 | $985.00 | $1,060.00 |
| 0090 | Crushed aggregate size no 2 | TON A A | 3 | $200.00 | $385.00 | $585.00 |
| 0100 | Delineator for G/R BI directional white | EACH A A | 38 | $13.83 | $12.00 | $32.80 |
| 0110 | Delineator for barrier wall-B/W | EACH A A | 14 | $15.07 | $12.00 | $24.00 |
| 0120 | Barricade-type III | EACH A A | 4 | $100.00 | $180.00 | $280.00 |
| 0130 | Temp ditch | LF A A | 1,021 | $1.00 | $0.50 | $1.00 |
| 0140 | Clean temp ditch | LF A A | 511 | $0.10 | $0.20 | $1.00 |
| 0150 | Roadway excavation | CUYD A A | 87,566 | $15.00 | $18.80 | $34.25 |
| 0160 | Water | MGAL A A | 19 | $1.00 | $1.00 | $0.01 |
| 0170 | G/R-W beam-S face TL-3 | LF A A | 1,875 | $31.69 | $26.95 | $30.00 |
| 0180 | G/R end treatment type 1 | EACH A A | 2 | $448.06 | $3,295.00 | $3,500.00 |
| 0190 | Right-of-way monument type 1 | EACH A A | 16 | $177.25 | $300.00 | $169.00 |
| 0200 | Witness post | EACH A A | 3 | $144.14 | $300.00 | $49.00 |
| 0210 | Channel lining class IV | CUYD A A | 2,987 | $10.00 | $19.00 | $17.50 |
| 0220 | Clearing and grubbing | LS A A | 1 | $75,000 | $125,000 | $169,000 |
| 0230 | Concrete-class B | CUYD A A | 25 | $700.00 | $875.00 | $453.00 |
| 0240 | Temporary signs | SQFT A A | 168.50 | $13.00 | $15.00 | $13.50 |
| 0250 | Edge key | LF A A | 71 | $75.25 | $75.25 | $81.00 |
| 0260 | Fabric-geotextile class 1 | SQYD A A | 2,000 | $2.50 | $2.50 | $2.40 |
| 0270 | Fabric-geotextile class 4A | SQYD A A | 20,000 | $4.60 | $4.50 | $5.00 |
| 0280 | Maintain & control traffic | LS A A | 1 | $100,000 | $50,000 | $21,000 |
| 0290 | Portable changeable message sign | EACH A A | 3 | $8,910.00 | $8,000.00 | $11,000 |
| 0300 | Safeloading | CUYD A A | 7.60 | $700.00 | $500.00 | $975.00 |
| 0310 | Edgeline rumble strips | LF A A | 6,930 | $0.55 | $0.75 | $0.60 |
| 0320 | Temp silt fence | LF A A | 1,021 | $2.00 | $3.00 | $7.00 |
| 0330 | Silt trap type A | EACH A A | 12 | $100.00 | $50.00 | $325.00 |
| 0340 | Silt trap type B | EACH A A | 12 | $100.00 | $50.00 | $400.00 |
| 0350 | Silt trap type C | EACH A A | 12 | $100.00 | $50.00 | $485.00 |
| 0360 | Clean silt trap type A | EACH A A | 12 | $10.00 | $5.00 | $46.00 |
| 0370 | Clean silt trap type B | EACH A A | 12 | $10.00 | $5.00 | $46.00 |
| 0380 | Clean silt trap type C | EACH A A | 12 | $10.00 | $5.00 | $46.00 |
| 0390 | Staking | LS A A | 1 | $20,000 | $15,000 | $44,200 |
| 0400 | Conc barrier wall type 9T | LF A A | 1,400 | $60.00 | $75.00 | $50.00 |
| 0410 | Temp signal 2 phase | EACH A A | 1 | $30,000 | $15,000 | $42,900 |
| 0420 | Erosion control blanket | SQYD A A | 17,900 | $2.29 | $2.45 | $2.65 |
| 0430 | Temp mulch | SQYD A A | 38,268 | $0.37 | $0.26 | $0.28 |
| 0440 | Temp seeding and protection | SQYD A A | 28,702 | $0.39 | $0.28 | $0.30 |
| 0450 | Initial fertilizer | TON A A | 2.20 | $1,659.00 | $1,800.00 | $1,900.00 |
| 0460 | Maintenance fertilizer | TON A A | 1.30 | $1,659.00 | $1,800.00 | $1,900.00 |
| 0470 | Seeding and protection | SQYD A A | 22,200 | $0.68 | $0.54 | $0.58 |
| 0480 | Agricultural limestone | TON A A | 13.80 | $76.21 | $185.00 | $200.00 |
| 0490 | Pave striping-temp paint-4 in | LF A A | 3,000 | $0.20 | $0.50 | $0.22 |
| 0500 | Pave striping-perm paint-4 in | LF A A | 10,100 | $0.30 | $0.40 | $0.32 |
| 0510 | Pave striping-temp rem tape-W | LF A A | 500 | $2.55 | $5.00 | $2.75 |
| 0520 | Crash cushion TY 6 class T TL2 | EACH A A | 2 | $5,183.57 | $5,555.00 | $4,560.00 |
| 0530 | Fuel adjustment | DOLL A A | 15,145 | $1.00 | $1.00 | $1.00 |
| 0540 | Asphalt adjustment | DOLL A A | 8,777 | $1.00 | $1.00 | $1.00 |
| 0550 | Object marker TY 3 | EACH A A | 2 | $23.35 | $60.00 | $65.00 |
| 0560 | Remove-store and reinstall sign | EACH A A | 4 | $329.67 | $375.00 | $320.00 |
| 0570 | Longitudinal edge key | LF A A | 698 | $12.75 | $12.75 | $14.00 |
| 0580 | Remove sign | EACH A A | 5 | $20.89 | $85.00 | $200.00 |
| 0590 | Gabion step ditch | CUYD A A | 1,446 | $500.00 | $265.00 | $250.00 |
| 0600 | Temporary earth pad | CUYD A A | 1,800 | $16.00 | $12.00 | $20.00 |
| 0610 | Electronic delivery MGMT system - agg | LS A A | 1 | $2,000.00 | $1,750.00 | $1,890.00 |
| 0620 | Culvert pipe-18 in | LF A A | 144 | $110.00 | $225.00 | $230.00 |
| 0630 | Culvert pipe-24 in | LF A A | 73 | $135.00 | $200.00 | $290.00 |
| 0640 | Pipe culvert headwall-18 in | EACH A A | 3 | $1,600.00 | $2,000.00 | $1,900.00 |
| 0650 | Pipe culvert headwall-24 in | EACH A A | 1 | $1,700.00 | $2,600.00 | $2,000.00 |
| 0660 | S & F box inlet-outlet-18 in | EACH A A | 1 | $2,500.00 | $4,000.00 | $3,050.00 |
| 0670 | Drop box inlet type 1 | EACH A A | 1 | $5,000.00 | $4,800.00 | $7,700.00 |
| 0680 | Fabric-geotextile class 2 for pipe | SQYD A A | 253 | $2.00 | $2.00 | $2.00 |
| 0690 | Pipeline inspection | LF A A | 217 | $11.25 | $12.00 | $12.00 |
| 0700 | Sloped and mitered headwall-18 in | EACH A A | 2 | $2,500.00 | $6,400.00 | $3,500.00 |
| 0710 | W pipe PVC 06 inch | LF A A | 1,010 | $82.00 | $78.00 | $51.25 |
| 0720 | W pipe PVC 10 inch | LF A A | 1,260 | $150.00 | $118.00 | $86.00 |
| 0730 | W tie-in 06 inch | EACH A A | 2 | $4,900.00 | $6,800.00 | $3,200.00 |
| 0740 | W tie-in 10 inch | EACH A A | 2 | $10,350 | $16,500 | $4,830.00 |
| 0750 | W valve 10 inch | EACH A A | 1 | $5,200.00 | $8,500.00 | $5,590.00 |
| 0760 | W line marker | EACH A A | 4 | $100.00 | $100.00 | $59.00 |
| 0770 | Mobilization | LS A A | 1 | $162,973 | $175,000 | $250,300 |
| 0780 | Demobilization | LS A A | 1 | $57,596 | $64,935 | $81,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of May 21, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.