KYTC contract 26-5404 bid tabulation
BRIDGE REPLACEMENT KY 32. Let by Kentucky Transportation Cabinet on February 19, 2026. 7 bids received; low bid $2,049,227 by Frederick & May Construction Co, -18% against the engineer's estimate of $2,487,516.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 19 FEB 2026
- Pay items
- 62
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Frederick & May Construction Co | $2,049,227 | Low | -18% |
| 2 | Walker Construction & Materials LLC | $2,133,000 | +4.0% | -14% |
| 3 | Hinkle Construction Services LLC | $2,562,557 | +25% | +3.0% |
| 4 | Orders Construction Company Inc | $2,649,173 | +29% | +6.0% |
| 5 | Bush & Burchett Inc | $2,793,402 | +36% | +12% |
| 6 | Hall Contracting of Kentucky Inc | $3,175,000 | +55% | +28% |
| 7 | Haydon Bridge Company Inc | $3,496,930 | +71% | +41% |
Engineer's estimate: $2,487,516.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Frederick & May Construction Co | 2. Walker Construction & Materials LLC | 3. Hinkle Construction Services LLC | 4. Orders Construction Company Inc | 5. Bush & Burchett Inc | 6. Hall Contracting of Kentucky Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 2,613 | $51.00 | $45.00 | $40.00 | $48.00 | $43.00 | $50.00 |
| 0020 | Traffic bound base | TON A A | 202 | $44.00 | $37.00 | $43.00 | $84.00 | $76.00 | $80.00 |
| 0030 | Asphalt seal aggregate | TON A A | 23 | $255.00 | $255.00 | $268.00 | $360.00 | $325.00 | $331.00 |
| 0040 | Asphalt seal coat | TON A A | 3 | $1.00 | $1.00 | $1.00 | $1,300.00 | $1,175.00 | $1,180.00 |
| 0050 | Leveling & wedging PG64-22 | TON A A | 138 | $115.00 | $115.00 | $121.00 | $180.00 | $164.00 | $169.00 |
| 0060 | CL2 asph base 1.00D PG64-22 | TON A A | 1,250 | $101.00 | $101.00 | $106.00 | $110.00 | $93.25 | $93.25 |
| 0070 | CL2 asph surf 0.38D PG64-22 | TON A A | 254 | $115.00 | $115.00 | $120.00 | $130.00 | $120.00 | $120.00 |
| 0080 | Asphalt material for tack | TON A A | 6 | $1.00 | $1.00 | $1.00 | $1.10 | $1.00 | $1.00 |
| 0090 | Asphalt pave milling & texturing | TON A A | 128 | $40.00 | $40.00 | $42.00 | $72.00 | $65.00 | $65.00 |
| 0100 | Entrance pipe-12 in | LF A A | 34 | $65.00 | $99.00 | $130.00 | $200.00 | $70.00 | $100.00 |
| 0110 | Flume inlet type 2 | EACH A A | 1 | $6,000.00 | $9,000.00 | $7,225.00 | $12,000 | $1,800.00 | $7,000.00 |
| 0120 | Delineator for guardrail BI directional white | EACH A A | 8 | $16.89 | $12.00 | $12.60 | $13.00 | $12.00 | $12.00 |
| 0130 | Delineator for barrier wall-B/W | EACH A A | 4 | $17.79 | $20.00 | $21.00 | $22.00 | $20.00 | $20.00 |
| 0140 | Barricade-type III | EACH A A | 2 | $100.00 | $160.00 | $150.00 | $160.00 | $200.00 | $200.00 |
| 0150 | Remove pavement | SQYD A A | 441 | $12.00 | $10.00 | $13.00 | $11.00 | $22.00 | $16.00 |
| 0160 | Roadway excavation | CUYD A A | 4,004 | $20.00 | $24.00 | $55.00 | $26.00 | $22.00 | $85.00 |
| 0170 | Guardrail-steel W beam-S face | LF A A | 125 | $37.38 | $38.00 | $40.00 | $41.00 | $38.00 | $38.00 |
| 0180 | Guardrail terminal section no 1 | EACH A A | 2 | $89.67 | $80.00 | $84.00 | $87.00 | $80.00 | $80.00 |
| 0190 | Guardrail end treatment type 1 | EACH A A | 1 | $3,864.00 | $4,000.00 | $4,210.00 | $4,300.00 | $4,000.00 | $4,000.00 |
| 0200 | Guardrail end treatment type 2M | EACH A A | 1 | $2,080.65 | $1,500.00 | $1,575.00 | $1,600.00 | $1,500.00 | $1,500.00 |
| 0210 | Right-of-way monument type 1 | EACH A A | 14 | $250.00 | $150.00 | $155.00 | $160.00 | $300.00 | $150.00 |
| 0220 | Witness post | EACH A A | 4 | $250.00 | $150.00 | $125.00 | $160.00 | $150.00 | $150.00 |
| 0230 | Channel lining class II | TON A A | 112 | $50.00 | $45.00 | $55.00 | $78.00 | $68.00 | $60.00 |
| 0240 | Channel lining class III | TON A A | 211 | $60.00 | $50.00 | $70.00 | $92.00 | $67.00 | $70.00 |
| 0250 | Clearing and grubbing | LS A A | 1 | $7,500.00 | $25,000 | $18,100 | $53,000 | $50,000 | $100,000 |
| 0260 | Temporary signs | SQFT A A | 160 | $14.50 | $12.72 | $13.40 | $13.00 | $15.00 | $10.00 |
| 0270 | Edge key | LF A A | 69 | $22.00 | $22.00 | $23.00 | $17.00 | $15.00 | $15.00 |
| 0280 | Fabric-geotextile class 1 | SQYD A A | 323 | $3.00 | $2.50 | $2.15 | $4.30 | $4.00 | $3.50 |
| 0290 | Maintain & control traffic | LS A A | 1 | $15,000 | $20,000 | $42,140 | $32,000 | $90,000 | $250,000 |
| 0300 | Mobilization for mill & text | LS A A | 1 | $2,800.00 | $2,800.00 | $2,950.00 | $5,600.00 | $4,275.00 | $4,275.00 |
| 0310 | Staking | LS A A | 1 | $20,000 | $12,500 | $22,400 | $77,000 | $25,000 | $100,000 |
| 0320 | Erosion control blanket | SQYD A A | 2,197 | $3.32 | $2.50 | $1.75 | $2.70 | $2.50 | $2.50 |
| 0330 | SBM alum sheet signs .080 in | SQFT A A | 29.25 | $51.12 | $40.00 | $42.00 | $43.00 | $40.00 | $40.00 |
| 0340 | Steel post type 1 | LF A A | 35 | $33.56 | $30.00 | $32.00 | $33.00 | $30.00 | $30.00 |
| 0350 | Pave striping-perm paint-4 in | LF A A | 5,580 | $0.35 | $0.50 | $0.45 | $0.51 | $0.35 | $0.40 |
| 0360 | Asphalt adjustment | DOLL A A | 5,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0370 | Object marker TY 3 | EACH A A | 1 | $32.20 | $100.00 | $105.00 | $110.00 | $100.00 | $100.00 |
| 0380 | Longitudinal edge key | LF A A | 645 | $4.25 | $4.25 | $4.50 | $4.40 | $4.00 | $4.00 |
| 0390 | Erosion control | LS A A | 1 | $10,000 | $10,000 | $30,000 | $24,000 | $20,000 | $50,000 |
| 0400 | Barcode sign inventory | EACH A A | 3 | $51.81 | $25.00 | $26.00 | $27.00 | $25.00 | $25.00 |
| 0410 | Thrie beam guardrail transition TL-3 | EACH A A | 4 | $4,129.00 | $5,300.00 | $3,685.00 | $3,800.00 | $3,500.00 | $5,200.00 |
| 0420 | Mobilization for concrete surf treatment | LS A A | 1 | $1,000.00 | $1,700.00 | $1,375.00 | $11,000 | $1,000.00 | $1.00 |
| 0430 | Structure granular backfill | CUYD A A | 119 | $70.00 | $78.00 | $145.00 | $150.00 | $100.00 | $110.00 |
| 0440 | Fabric-geotextile class 2 | SQYD A A | 983 | $3.00 | $2.00 | $1.50 | $5.30 | $3.00 | $2.50 |
| 0450 | Remove structure | LS A A | 1 | $50,000 | $90,000 | $78,280 | $130,000 | $100,000 | $125,000 |
| 0460 | Armored edge for concrete | LF A A | 65 | $150.00 | $134.50 | $95.00 | $170.00 | $150.00 | $80.00 |
| 0470 | Structure excav-solid rock | CUYD A A | 42 | $125.00 | $260.00 | $190.00 | $350.00 | $250.00 | $525.00 |
| 0480 | Foundation preparation | LS A A | 1 | $90,000 | $85,000 | $124,170 | $110,000 | $300,000 | $150,000 |
| 0490 | Cyclopean stone rip rap | TON A A | 1,315 | $62.00 | $50.00 | $80.00 | $73.00 | $60.00 | $75.00 |
| 0500 | Test piles | LF A A | 43 | $195.00 | $130.00 | $205.00 | $230.00 | $300.00 | $250.00 |
| 0510 | Pre-drilling for piles | LF A A | 174 | $340.00 | $385.00 | $365.00 | $360.00 | $600.00 | $540.00 |
| 0520 | Piles-steel HP12X53 | LF A A | 165 | $185.00 | $130.00 | $230.00 | $230.00 | $150.00 | $250.00 |
| 0530 | Pile points-12 in | EACH A A | 12 | $200.00 | $130.00 | $140.00 | $380.00 | $150.00 | $200.00 |
| 0540 | Concrete-class A | CUYD A A | 190.10 | $1,315.00 | $1,400.00 | $2,010.00 | $1,300.00 | $1,425.00 | $1,600.00 |
| 0550 | Concrete-class AA | CUYD A A | 187.10 | $1,050.00 | $1,400.00 | $1,465.00 | $1,800.00 | $1,800.00 | $1,610.00 |
| 0560 | Steel reinforcement | LB A A | 24,270 | $2.00 | $1.95 | $2.00 | $2.20 | $2.50 | $1.50 |
| 0570 | Steel reinforcement-epoxy coated | LB A A | 58,041 | $2.10 | $1.95 | $2.05 | $2.40 | $2.50 | $1.60 |
| 0580 | Precast PC box beam SB27 | LF A A | 830 | $395.00 | $380.00 | $410.00 | $340.00 | $475.00 | $400.00 |
| 0590 | Concrete sealing | SQFT A A | 11,930 | $2.50 | $1.50 | $1.40 | $6.20 | $2.00 | $1.10 |
| 0600 | Rail system single slope - 40 in | LF A A | 339 | $150.00 | $165.00 | $150.00 | $250.00 | $150.00 | $175.00 |
| 0610 | Mobilization | LS A A | 1 | $95,287 | $90,000 | $110,000 | $120,000 | $130,000 | $148,752 |
| 0620 | Demobilization | LS A A | 1 | $30,285 | $32,003 | $38,000 | $40,000 | $40,000 | $45,689 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of February 19, 2026. Compiled by Mirage Metrics.