KYTC contract 26-2233 bid tabulation

CULVERT REPLACEMENT CULVERT REPLACMENTS ON KY 40 IN MARTIN COUNTY. Let by Kentucky Transportation Cabinet on August 20, 2026. 5 bids received; low bid $342,911 by Frederick & May Construction Co, -39% against the engineer's estimate of $559,637.

Owner
Kentucky Transportation Cabinet
Letting
20 AUG 2026
Pay items
26
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Frederick & May Construction Co$342,911Low-39%
2Mountain Enterprises Inc$496,450+45%-11%
3Walker Construction & Materials LLC$518,815+51%-7.0%
4Boca Enterprises Inc$526,470+54%-6.0%
5Hinkle Construction Services LLC$588,987+72%+5.0%
KYTC contract 26-2233: bids by rank

Engineer's estimate: $559,637.

Bid tabulation

LinePay itemUnitQuantity1. Frederick & May Construction Co2. Mountain Enterprises Inc3. Walker Construction & Materials LLC4. Boca Enterprises Inc5. Hinkle Construction Services LLC
0010Dga baseTON A A100$50.00$76.50$135.00$75.00$80.00
0020Barricade-type IIIEACH A A8$100.00$185.00$160.00$150.00$130.00
0030JPC pavement-8 inSQYD A A250$150.00$187.50$250.00$360.00$440.00
0040Temporary signsSQFT A A375$10.00$9.25$8.50$15.00$10.00
0050Maintain & control trafficLS A A1$2,500.00$7,500.00$3,500.00$9,000.00$8,840.00
0060Maintain & control trafficLS A A1$2,500.00$7,500.00$3,500.00$9,000.00$10,790
0070Portable changeable message signEACH A A4$2,500.00$1,775.00$500.00$1,200.00$1,090.00
0080Pave striping-perm paint-6 inLF A A980$0.75$0.75$1.50$3.00$0.80
0090Drop box inlet-specialEACH A A1$13,000$14,500$15,000$45,000$32,020
0100Remove drop box inletEACH A A1$1,500.00$3,925.00$1,000.00$10,000$2,570.00
0110Site preparationEACH A A1$9,895.00$24,750$40,000$20,000$63,370
0120Site preparationEACH A A1$6,500.00$42,500$40,000$20,000$73,310
0130Channel lining class IIITON A A225$60.00$79.75$90.00$78.00$80.00
0140Fabric-geotextile class 2SQYD A A80$4.00$3.10$10.00$5.00$4.25
0150StakingLS A A1$4,500.00$3,500.00$4,500.00$10,000$3,730.00
0160StakingLS A A1$4,500.00$3,500.00$4,500.00$10,000$4,660.00
0170Foundation preparationLS A A1$30,000$22,900$13,000$15,000$10,770
0180Foundation preparationLS A A1$29,000$28,900$15,000$15,000$13,130
0190Aluminum structural plate box culvertLF A A85$1,806.00$2,660.00$2,900.00$2,450.00$2,325.00
0200Erosion controlLS A A1$1,500.00$5,000.00$5,749.00$2,500.00$3,860.00
0210Erosion controlLS A A1$1,500.00$5,000.00$5,749.00$2,500.00$3,900.00
0220Delineator for G/R BI directional whiteEACH A A6$15.00$13.00$15.00$25.00$10.00
0230G/R-W beam-S face TL-3LF A A132.50$39.00$55.00$39.00$70.00$33.00
0240G/R terminal section no 1EACH A A2$100.00$95.00$100.00$140.00$90.00
0250Remove G/RLF A A125$3.00$3.75$3.00$20.00$5.00
0260DemobilizationLS A A1$5,068.00$7,350.00$9,997.00$8,000.00$8,900.00
KYTC contract 26-2233: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of August 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy