KYTC contract 26-1513 bid tabulation

GRADE & DRAIN WITH BRIDGE JCPS ACCESS ROAD. Let by Kentucky Transportation Cabinet on May 21, 2026. 4 bids received; low bid $6,362,726 by Frederick & May Construction Co, -8.7% against the engineer's estimate of $6,971,484.

Owner
Kentucky Transportation Cabinet
Letting
21 MAY 2026
Pay items
146
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Frederick & May Construction Co$6,362,726Low-9.0%
2Walker Construction & Materials LLC$6,965,000+9.0%0.0%
3Bush & Burchett Inc$7,731,086+22%+11%
4Haydon Bridge Company Inc$8,872,687+39%+27%
KYTC contract 26-1513: bids by rank

Engineer's estimate: $6,971,484.

Bid tabulation

LinePay itemUnitQuantity1. Frederick & May Construction Co2. Walker Construction & Materials LLC3. Bush & Burchett Inc4. Haydon Bridge Company Inc
0010Dga baseTON A A58$55.00$75.00$70.00$100.00
0020Crushed stone baseTON A A2,742$55.30$55.30$55.30$58.00
0030Traffic bound baseTON A A81$50.00$65.00$70.00$100.00
0040Crushed aggregate size no 2TON A A3,746$50.00$47.00$70.00$70.00
0050Asphalt seal aggregateTON A A20$286.75$286.75$286.75$300.00
0060Asphalt seal coatTON A A2$1,600.00$1,600.00$1,600.00$1,600.00
0070CL2 asph base 1.00D PG64-22TON A A1,145$161.70$161.70$161.70$168.00
0080CL3 asph base 1.00D PG64-22TON A A1,921$161.70$161.70$161.70$168.00
0090CL2 asph surf 0.38D PG64-22TON A A261$186.75$186.75$186.75$194.00
0100CL3 asph surf 0.38B PG64-22TON A A1,567$186.75$186.75$186.75$194.00
0110Fabric-geotextile class 1SQYD A A6,316$2.10$2.10$2.10$2.20
0120Fabric-geotextile class 4ASQYD A A6,316$4.60$4.50$4.00$4.25
0130Asphalt pave milling & texturingTON A A1,158$45.50$45.50$45.50$48.00
0140Joint adhesiveLF A A8,691$0.95$0.95$0.95$1.00
0150Sawcut pavementLF A A3,713$5.00$2.50$2.25$3.50
0160Longitudinal edge keyLF A A3,713$9.10$9.10$9.10$9.45
0170Asphalt material for tack non-trackingTON A A9$850.00$850.00$850.00$850.00
0180Electronic delivery MGMT system - aggLS A A1$1,500.00$1,500.00$1,500.00$2,000.00
0190Flume inlet type 2EACH A A2$6,000.00$11,000$7,400.00$7,000.00
0200Lip curb and gutterLF A A100$70.00$90.00$48.00$75.00
0210Standard header curbLF A A346$80.00$69.00$52.00$55.00
0220Mountable median type 6ASQYD A A258$160.00$127.00$220.00$185.00
0230Delineator for G/R BI directional whiteEACH A A14$13.00$13.00$13.00$15.00
0240Barricade-type IIIEACH A A11$100.00$160.00$200.00$225.00
0250Remove pavementSQYD A A781$5.00$10.00$8.00$8.50
0260Temp ditchLF A A1,570$1.00$0.50$1.70$1.95
0270Clean temp ditchLF A A785$0.10$0.20$2.25$2.25
0280Embankment in placeCUYD A A13,948$25.00$32.00$16.00$17.25
0290WaterMGAL A A100$1.00$1.00$1.00$1.00
0300G/R-W beam-S face TL-3LF A A1,052$26.95$26.95$26.95$28.00
0310G/R end treatment type 1EACH A A2$3,400.00$3,400.00$3,400.00$3,750.00
0320G/R end treatment type 2MEACH A A1$2,200.00$2,200.00$2,200.00$2,500.00
0330Remove G/RLF A A787.50$4.00$4.00$4.00$4.50
0340Right-of-way monument type 1EACH A A5$250.00$300.00$300.00$300.00
0350Witness postEACH A A3$250.00$300.00$200.00$300.00
0360Channel lining class IIITON A A755$60.00$62.00$70.00$75.00
0370Clearing and grubbingLS A A1$15,000$100,000$100,000$275,000
0380Temporary signsSQFT A A328$13.00$15.00$18.00$17.00
0390Fabric-geotextile class 1SQYD A A833$2.50$4.00$4.00$4.25
0400Fabric-geotextile class 2 for pipeSQYD A A270$2.00$2.00$2.00$2.00
0410Maintain & control trafficLS A A1$100,000$100,000$100,000$195,000
0420Lane closureEACH A A8$1,500.00$1.00$2,000.00$4,250.00
0430Portable changeable message signEACH A A2$10,000$7,500.00$10,000$11,500
0440Mobilization for mill & textLS A A1$5,000.00$5,000.00$5,000.00$5,500.00
0450Shoulder rumble stripsLF A A3,032$1.00$2.20$1.05$2.25
0460Temp silt fenceLF A A1,570$2.50$4.00$6.00$6.50
0470Silt trap type AEACH A A14$100.00$50.00$250.00$260.00
0480Silt trap type BEACH A A14$100.00$50.00$250.00$260.00
0490Silt trap type CEACH A A14$100.00$50.00$250.00$260.00
0500Clean silt trap type AEACH A A14$25.00$5.00$250.00$260.00
0510Clean silt trap type BEACH A A14$25.00$5.00$240.00$260.00
0520Clean silt trap type CEACH A A14$25.00$5.00$240.00$260.00
0530StakingLS A A1$21,000$20,000$45,000$75,000
0540Arrow panelEACH A A2$4,200.00$2,000.00$1,820.00$5,000.00
0550Temp signal 2 phaseEACH A A2$11,500$2,000.00$3,500.00$15,000
0560Erosion control blanketSQYD A A4,591$2.45$2.45$2.45$2.65
0570Temp mulchSQYD A A45,173$0.25$0.25$0.25$0.25
0580Temp seeding and protectionSQYD A A33,880$0.27$0.27$0.27$0.27
0590Initial fertilizerTON A A4$1,600.00$1,600.00$1,600.00$1,600.00
0600Maintenance fertilizerTON A A2$1,600.00$1,600.00$1,600.00$1,600.00
0610Seeding and protectionSQYD A A36,300$0.55$0.55$0.55$0.60
0620Agricultural limestoneTON A A26$145.00$145.00$145.00$150.00
0630SBM alum sheet signs .080 inSQFT A A5$40.00$40.00$40.00$50.00
0640SBM alum sheet signs .125 inSQFT A A14$45.00$45.00$45.00$55.00
0650Steel post type 1LF A A39$30.00$30.00$30.00$35.00
0660Pave striping-temp paint-6 inLF A A7,658$0.18$0.25$0.18$0.20
0670Pave striping-perm paint-4 inLF A A2,731$0.20$0.50$0.20$0.22
0680Pave striping-perm paint-6 inLF A A9,678$0.24$0.50$0.24$0.26
0690Pave striping-perm paint-8 inLF A A171$0.30$0.50$0.30$0.33
0700Pave striping-perm paint-12 inLF A A1,771$0.45$0.50$0.45$0.49
0710Pave striping-thermo-4 in WLF A A183$3.50$3.75$3.50$3.75
0720Pave striping-thermo-12 in WLF A A134$6.50$7.50$6.50$7.25
0730Pave marking-thermo stop bar-24INLF A A54$10.00$12.50$10.00$11.00
0740Pave marking-thermo cross-hatchSQFT A A559$6.50$7.00$6.50$7.25
0750Pave marking-thermo curv arrowEACH A A18$125.00$125.00$125.00$150.00
0760Inlaid pavement marker-MWEACH A A82$45.00$34.00$45.00$37.50
0770Inlaid pavement marker-MYEACH A A15$45.00$34.00$45.00$37.50
0780Inlaid pavement marker-byEACH A A42$45.00$34.00$45.00$37.50
0790Inlaid pavement marker-B W/REACH A A11$45.00$34.00$45.00$37.50
0800Fuel adjustmentDOLL A A5,010$1.00$1.00$1.00$1.00
0810Asphalt adjustmentDOLL A A19,821$1.00$1.00$1.00$1.00
0820Object marker TY 3EACH A A2$65.00$65.00$65.00$70.00
0830Pave marking-thermo yield bar-36 inLF A A20$45.00$45.00$45.00$50.00
0840Pave mark thermo-lane reduction arrowEACH A A2$250.00$250.00$250.00$275.00
0850Barcode sign inventoryEACH A A3$30.00$30.00$30.00$35.00
0860Pipeline inspectionLF A A81$30.86$32.00$8.00$8.25
0870Thrie beam G/R transition TL-2EACH A A2$3,450.00$4,500.00$2,200.00$2,750.00
0880Corps of engineers coordinationLS A A1$5,000.00$15,000$40,000$75,000
0890Crushed aggregate size no 2TON A A1$400.00$250.00$69.00$100.00
0900Culvert pipe-18 inLF A A81$120.00$125.00$170.00$180.00
0910Perforated pipe-4 inLF A A52$40.00$40.00$8.00$8.50
0920Non-perforated pipe-4 inLF A A10$40.00$80.00$8.00$8.50
0930Perf pipe headwall TY 3-4 inEACH A A1$1,200.00$1,500.00$1,420.00$1,500.00
0940Pipe culvert headwall-18 inEACH A A1$1,500.00$2,600.00$1,820.00$1,850.00
0950Channel lining class IITON A A15$100.00$125.00$70.00$75.00
0960Concrete-class ACUYD A A1.07$3,000.00$1,500.00$680.00$750.00
0970Junction box-24 inEACH A A3$4,000.00$3,000.00$1,000.00$1,500.00
0980Structure granular backfillCUYD A A604$65.00$85.00$100.00$95.00
0990Armored edge for concreteLF A A81.60$150.00$135.00$125.00$125.00
1000Foundation preparationLS A A1$60,000$150,000$550,000$325,000
1010Cyclopean stone rip rapTON A A3,473$55.00$55.00$60.00$75.00
1020Test pilesLF A A126$155.00$165.00$300.00$350.00
1030Piles-steel HP14X89LF A A1,066$145.00$165.00$125.00$150.00
1040Pile points-14 inEACH A A20$350.00$165.00$200.00$325.00
1050Concrete-class ACUYD A A289.80$950.00$1,250.00$1,350.00$1,425.00
1060Concrete-class AACUYD A A477$975.00$1,250.00$1,750.00$1,595.00
1070Steel reinforcementLB A A41,936$2.00$1.75$2.50$2.40
1080Steel reinforcement-epoxy coatedLB A A132,568$1.90$2.05$2.50$2.30
1090Precast PC I beam type 8LF A A1,057.30$753.00$770.00$900.00$1,150.00
1100Electrical junction box type AEACH A A2$1,520.66$1,520.66$1,520.66$2,500.00
1110Rock soundingsLF A A197.60$42.60$37.00$75.00$62.00
1120Rock coringsLF A A120$76.50$70.00$100.00$105.00
1130CSL testing (6 tubes)EACH A A4$8,717.00$7,500.00$6,000.00$1,500.00
1140Drilled shaft-72 in-rockLF A A48$5,744.00$5,400.00$6,000.00$5,100.00
1150Concrete sealingSQFT A A25,924$2.50$1.35$2.00$2.50
1160Deck drainEACH A A10$1,000.00$825.00$1,500.00$1,250.00
1170Drilled shaft-78 in commonLF A A192$1,929.00$2,100.00$1,500.00$4,150.00
1180PVC conduit-3 in-schedule 80LF A A298.30$12.85$12.85$12.85$16.00
1190Rail system single slope - 40 inLF A A537$150.00$175.00$150.00$160.00
1200Mobilization for concrete surf treatmentLS A A1$500.00$1,500.00$500.00$1,500.00
1210W cap existing mainEACH A A2$1,905.00$1,774.00$1,905.00$2,250.00
1220W pipe PVC 08 inchLF A A310$53.25$74.46$53.25$60.00
1230W tie-in 08 inchEACH A A2$2,725.00$5,469.00$2,725.00$3,500.00
1240W valve 08 inchEACH A A2$3,850.00$3,737.00$3,850.00$4,500.00
1250W encasement steel open cut range 4 instLF A A240$160.00$297.00$160.00$185.00
1260S force main PE/plastic 04 inchLF A A307$37.15$110.35$37.15$42.50
1270S manholeEACH A A2$3,680.00$7,579.50$3,680.00$4,250.00
1280S manhole tap existingEACH A A3$1,300.00$2,000.00$1,300.00$2,000.00
1290S pipe PVC 08 inchLF A A110$146.80$85.03$146.80$185.00
1300S pump stationEACH A A1$242,690$246,277$242,690$305,000
1310S cap existing mainEACH A A5$915.00$700.00$915.00$1,000.00
1320G encasement steel open cut range 1LF A A150$310.00$177.12$260.00$180.00
1330G pipe polyethylene/plastic 02 inchLF A A256$48.00$21.96$58.00$23.00
1340G valve steel 02 inchEACH A A2$850.00$1,406.00$2,610.00$1,500.00
1350G cap existing mainEACH A A2$1,200.00$510.00$860.00$650.00
1360Pole baseEACH A A2$4,101.77$4,102.00$1,520.66$4,500.00
1370Lighting control equipmentEACH A A1$38,001$38,001$38,001$50,000
1380Trenching and backfillingLF A A605$12.40$12.40$12.40$14.00
1390Wire-no. 12LF A A400$2.20$2.20$2.20$2.50
1400Electrical junction box type AEACH A A4$1,520.66$1,521.00$1,520.66$2,500.00
1410Bore and jack conduitLF A A63$126.51$127.00$126.51$140.00
1420Install luminaire poleEACH A A4$1,626.97$1,627.00$1,626.96$2,100.00
1430Wire-no. 10LF A A2,100$2.57$2.57$2.57$2.75
1440PVC conduit-2 in-schedule 80LF A A668$8.34$8.50$8.34$9.00
1450MobilizationLS A A1$272,988$314,991$350,000$415,000
1460DemobilizationLS A A1$94,031$105,000$115,000$124,650
KYTC contract 26-1513: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of May 21, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy