KYTC contract 26-1513 bid tabulation
GRADE & DRAIN WITH BRIDGE JCPS ACCESS ROAD. Let by Kentucky Transportation Cabinet on May 21, 2026. 4 bids received; low bid $6,362,726 by Frederick & May Construction Co, -8.7% against the engineer's estimate of $6,971,484.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 MAY 2026
- Pay items
- 146
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Frederick & May Construction Co | $6,362,726 | Low | -9.0% |
| 2 | Walker Construction & Materials LLC | $6,965,000 | +9.0% | 0.0% |
| 3 | Bush & Burchett Inc | $7,731,086 | +22% | +11% |
| 4 | Haydon Bridge Company Inc | $8,872,687 | +39% | +27% |
Engineer's estimate: $6,971,484.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Frederick & May Construction Co | 2. Walker Construction & Materials LLC | 3. Bush & Burchett Inc | 4. Haydon Bridge Company Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 58 | $55.00 | $75.00 | $70.00 | $100.00 |
| 0020 | Crushed stone base | TON A A | 2,742 | $55.30 | $55.30 | $55.30 | $58.00 |
| 0030 | Traffic bound base | TON A A | 81 | $50.00 | $65.00 | $70.00 | $100.00 |
| 0040 | Crushed aggregate size no 2 | TON A A | 3,746 | $50.00 | $47.00 | $70.00 | $70.00 |
| 0050 | Asphalt seal aggregate | TON A A | 20 | $286.75 | $286.75 | $286.75 | $300.00 |
| 0060 | Asphalt seal coat | TON A A | 2 | $1,600.00 | $1,600.00 | $1,600.00 | $1,600.00 |
| 0070 | CL2 asph base 1.00D PG64-22 | TON A A | 1,145 | $161.70 | $161.70 | $161.70 | $168.00 |
| 0080 | CL3 asph base 1.00D PG64-22 | TON A A | 1,921 | $161.70 | $161.70 | $161.70 | $168.00 |
| 0090 | CL2 asph surf 0.38D PG64-22 | TON A A | 261 | $186.75 | $186.75 | $186.75 | $194.00 |
| 0100 | CL3 asph surf 0.38B PG64-22 | TON A A | 1,567 | $186.75 | $186.75 | $186.75 | $194.00 |
| 0110 | Fabric-geotextile class 1 | SQYD A A | 6,316 | $2.10 | $2.10 | $2.10 | $2.20 |
| 0120 | Fabric-geotextile class 4A | SQYD A A | 6,316 | $4.60 | $4.50 | $4.00 | $4.25 |
| 0130 | Asphalt pave milling & texturing | TON A A | 1,158 | $45.50 | $45.50 | $45.50 | $48.00 |
| 0140 | Joint adhesive | LF A A | 8,691 | $0.95 | $0.95 | $0.95 | $1.00 |
| 0150 | Sawcut pavement | LF A A | 3,713 | $5.00 | $2.50 | $2.25 | $3.50 |
| 0160 | Longitudinal edge key | LF A A | 3,713 | $9.10 | $9.10 | $9.10 | $9.45 |
| 0170 | Asphalt material for tack non-tracking | TON A A | 9 | $850.00 | $850.00 | $850.00 | $850.00 |
| 0180 | Electronic delivery MGMT system - agg | LS A A | 1 | $1,500.00 | $1,500.00 | $1,500.00 | $2,000.00 |
| 0190 | Flume inlet type 2 | EACH A A | 2 | $6,000.00 | $11,000 | $7,400.00 | $7,000.00 |
| 0200 | Lip curb and gutter | LF A A | 100 | $70.00 | $90.00 | $48.00 | $75.00 |
| 0210 | Standard header curb | LF A A | 346 | $80.00 | $69.00 | $52.00 | $55.00 |
| 0220 | Mountable median type 6A | SQYD A A | 258 | $160.00 | $127.00 | $220.00 | $185.00 |
| 0230 | Delineator for G/R BI directional white | EACH A A | 14 | $13.00 | $13.00 | $13.00 | $15.00 |
| 0240 | Barricade-type III | EACH A A | 11 | $100.00 | $160.00 | $200.00 | $225.00 |
| 0250 | Remove pavement | SQYD A A | 781 | $5.00 | $10.00 | $8.00 | $8.50 |
| 0260 | Temp ditch | LF A A | 1,570 | $1.00 | $0.50 | $1.70 | $1.95 |
| 0270 | Clean temp ditch | LF A A | 785 | $0.10 | $0.20 | $2.25 | $2.25 |
| 0280 | Embankment in place | CUYD A A | 13,948 | $25.00 | $32.00 | $16.00 | $17.25 |
| 0290 | Water | MGAL A A | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0300 | G/R-W beam-S face TL-3 | LF A A | 1,052 | $26.95 | $26.95 | $26.95 | $28.00 |
| 0310 | G/R end treatment type 1 | EACH A A | 2 | $3,400.00 | $3,400.00 | $3,400.00 | $3,750.00 |
| 0320 | G/R end treatment type 2M | EACH A A | 1 | $2,200.00 | $2,200.00 | $2,200.00 | $2,500.00 |
| 0330 | Remove G/R | LF A A | 787.50 | $4.00 | $4.00 | $4.00 | $4.50 |
| 0340 | Right-of-way monument type 1 | EACH A A | 5 | $250.00 | $300.00 | $300.00 | $300.00 |
| 0350 | Witness post | EACH A A | 3 | $250.00 | $300.00 | $200.00 | $300.00 |
| 0360 | Channel lining class III | TON A A | 755 | $60.00 | $62.00 | $70.00 | $75.00 |
| 0370 | Clearing and grubbing | LS A A | 1 | $15,000 | $100,000 | $100,000 | $275,000 |
| 0380 | Temporary signs | SQFT A A | 328 | $13.00 | $15.00 | $18.00 | $17.00 |
| 0390 | Fabric-geotextile class 1 | SQYD A A | 833 | $2.50 | $4.00 | $4.00 | $4.25 |
| 0400 | Fabric-geotextile class 2 for pipe | SQYD A A | 270 | $2.00 | $2.00 | $2.00 | $2.00 |
| 0410 | Maintain & control traffic | LS A A | 1 | $100,000 | $100,000 | $100,000 | $195,000 |
| 0420 | Lane closure | EACH A A | 8 | $1,500.00 | $1.00 | $2,000.00 | $4,250.00 |
| 0430 | Portable changeable message sign | EACH A A | 2 | $10,000 | $7,500.00 | $10,000 | $11,500 |
| 0440 | Mobilization for mill & text | LS A A | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,500.00 |
| 0450 | Shoulder rumble strips | LF A A | 3,032 | $1.00 | $2.20 | $1.05 | $2.25 |
| 0460 | Temp silt fence | LF A A | 1,570 | $2.50 | $4.00 | $6.00 | $6.50 |
| 0470 | Silt trap type A | EACH A A | 14 | $100.00 | $50.00 | $250.00 | $260.00 |
| 0480 | Silt trap type B | EACH A A | 14 | $100.00 | $50.00 | $250.00 | $260.00 |
| 0490 | Silt trap type C | EACH A A | 14 | $100.00 | $50.00 | $250.00 | $260.00 |
| 0500 | Clean silt trap type A | EACH A A | 14 | $25.00 | $5.00 | $250.00 | $260.00 |
| 0510 | Clean silt trap type B | EACH A A | 14 | $25.00 | $5.00 | $240.00 | $260.00 |
| 0520 | Clean silt trap type C | EACH A A | 14 | $25.00 | $5.00 | $240.00 | $260.00 |
| 0530 | Staking | LS A A | 1 | $21,000 | $20,000 | $45,000 | $75,000 |
| 0540 | Arrow panel | EACH A A | 2 | $4,200.00 | $2,000.00 | $1,820.00 | $5,000.00 |
| 0550 | Temp signal 2 phase | EACH A A | 2 | $11,500 | $2,000.00 | $3,500.00 | $15,000 |
| 0560 | Erosion control blanket | SQYD A A | 4,591 | $2.45 | $2.45 | $2.45 | $2.65 |
| 0570 | Temp mulch | SQYD A A | 45,173 | $0.25 | $0.25 | $0.25 | $0.25 |
| 0580 | Temp seeding and protection | SQYD A A | 33,880 | $0.27 | $0.27 | $0.27 | $0.27 |
| 0590 | Initial fertilizer | TON A A | 4 | $1,600.00 | $1,600.00 | $1,600.00 | $1,600.00 |
| 0600 | Maintenance fertilizer | TON A A | 2 | $1,600.00 | $1,600.00 | $1,600.00 | $1,600.00 |
| 0610 | Seeding and protection | SQYD A A | 36,300 | $0.55 | $0.55 | $0.55 | $0.60 |
| 0620 | Agricultural limestone | TON A A | 26 | $145.00 | $145.00 | $145.00 | $150.00 |
| 0630 | SBM alum sheet signs .080 in | SQFT A A | 5 | $40.00 | $40.00 | $40.00 | $50.00 |
| 0640 | SBM alum sheet signs .125 in | SQFT A A | 14 | $45.00 | $45.00 | $45.00 | $55.00 |
| 0650 | Steel post type 1 | LF A A | 39 | $30.00 | $30.00 | $30.00 | $35.00 |
| 0660 | Pave striping-temp paint-6 in | LF A A | 7,658 | $0.18 | $0.25 | $0.18 | $0.20 |
| 0670 | Pave striping-perm paint-4 in | LF A A | 2,731 | $0.20 | $0.50 | $0.20 | $0.22 |
| 0680 | Pave striping-perm paint-6 in | LF A A | 9,678 | $0.24 | $0.50 | $0.24 | $0.26 |
| 0690 | Pave striping-perm paint-8 in | LF A A | 171 | $0.30 | $0.50 | $0.30 | $0.33 |
| 0700 | Pave striping-perm paint-12 in | LF A A | 1,771 | $0.45 | $0.50 | $0.45 | $0.49 |
| 0710 | Pave striping-thermo-4 in W | LF A A | 183 | $3.50 | $3.75 | $3.50 | $3.75 |
| 0720 | Pave striping-thermo-12 in W | LF A A | 134 | $6.50 | $7.50 | $6.50 | $7.25 |
| 0730 | Pave marking-thermo stop bar-24IN | LF A A | 54 | $10.00 | $12.50 | $10.00 | $11.00 |
| 0740 | Pave marking-thermo cross-hatch | SQFT A A | 559 | $6.50 | $7.00 | $6.50 | $7.25 |
| 0750 | Pave marking-thermo curv arrow | EACH A A | 18 | $125.00 | $125.00 | $125.00 | $150.00 |
| 0760 | Inlaid pavement marker-MW | EACH A A | 82 | $45.00 | $34.00 | $45.00 | $37.50 |
| 0770 | Inlaid pavement marker-MY | EACH A A | 15 | $45.00 | $34.00 | $45.00 | $37.50 |
| 0780 | Inlaid pavement marker-by | EACH A A | 42 | $45.00 | $34.00 | $45.00 | $37.50 |
| 0790 | Inlaid pavement marker-B W/R | EACH A A | 11 | $45.00 | $34.00 | $45.00 | $37.50 |
| 0800 | Fuel adjustment | DOLL A A | 5,010 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0810 | Asphalt adjustment | DOLL A A | 19,821 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0820 | Object marker TY 3 | EACH A A | 2 | $65.00 | $65.00 | $65.00 | $70.00 |
| 0830 | Pave marking-thermo yield bar-36 in | LF A A | 20 | $45.00 | $45.00 | $45.00 | $50.00 |
| 0840 | Pave mark thermo-lane reduction arrow | EACH A A | 2 | $250.00 | $250.00 | $250.00 | $275.00 |
| 0850 | Barcode sign inventory | EACH A A | 3 | $30.00 | $30.00 | $30.00 | $35.00 |
| 0860 | Pipeline inspection | LF A A | 81 | $30.86 | $32.00 | $8.00 | $8.25 |
| 0870 | Thrie beam G/R transition TL-2 | EACH A A | 2 | $3,450.00 | $4,500.00 | $2,200.00 | $2,750.00 |
| 0880 | Corps of engineers coordination | LS A A | 1 | $5,000.00 | $15,000 | $40,000 | $75,000 |
| 0890 | Crushed aggregate size no 2 | TON A A | 1 | $400.00 | $250.00 | $69.00 | $100.00 |
| 0900 | Culvert pipe-18 in | LF A A | 81 | $120.00 | $125.00 | $170.00 | $180.00 |
| 0910 | Perforated pipe-4 in | LF A A | 52 | $40.00 | $40.00 | $8.00 | $8.50 |
| 0920 | Non-perforated pipe-4 in | LF A A | 10 | $40.00 | $80.00 | $8.00 | $8.50 |
| 0930 | Perf pipe headwall TY 3-4 in | EACH A A | 1 | $1,200.00 | $1,500.00 | $1,420.00 | $1,500.00 |
| 0940 | Pipe culvert headwall-18 in | EACH A A | 1 | $1,500.00 | $2,600.00 | $1,820.00 | $1,850.00 |
| 0950 | Channel lining class II | TON A A | 15 | $100.00 | $125.00 | $70.00 | $75.00 |
| 0960 | Concrete-class A | CUYD A A | 1.07 | $3,000.00 | $1,500.00 | $680.00 | $750.00 |
| 0970 | Junction box-24 in | EACH A A | 3 | $4,000.00 | $3,000.00 | $1,000.00 | $1,500.00 |
| 0980 | Structure granular backfill | CUYD A A | 604 | $65.00 | $85.00 | $100.00 | $95.00 |
| 0990 | Armored edge for concrete | LF A A | 81.60 | $150.00 | $135.00 | $125.00 | $125.00 |
| 1000 | Foundation preparation | LS A A | 1 | $60,000 | $150,000 | $550,000 | $325,000 |
| 1010 | Cyclopean stone rip rap | TON A A | 3,473 | $55.00 | $55.00 | $60.00 | $75.00 |
| 1020 | Test piles | LF A A | 126 | $155.00 | $165.00 | $300.00 | $350.00 |
| 1030 | Piles-steel HP14X89 | LF A A | 1,066 | $145.00 | $165.00 | $125.00 | $150.00 |
| 1040 | Pile points-14 in | EACH A A | 20 | $350.00 | $165.00 | $200.00 | $325.00 |
| 1050 | Concrete-class A | CUYD A A | 289.80 | $950.00 | $1,250.00 | $1,350.00 | $1,425.00 |
| 1060 | Concrete-class AA | CUYD A A | 477 | $975.00 | $1,250.00 | $1,750.00 | $1,595.00 |
| 1070 | Steel reinforcement | LB A A | 41,936 | $2.00 | $1.75 | $2.50 | $2.40 |
| 1080 | Steel reinforcement-epoxy coated | LB A A | 132,568 | $1.90 | $2.05 | $2.50 | $2.30 |
| 1090 | Precast PC I beam type 8 | LF A A | 1,057.30 | $753.00 | $770.00 | $900.00 | $1,150.00 |
| 1100 | Electrical junction box type A | EACH A A | 2 | $1,520.66 | $1,520.66 | $1,520.66 | $2,500.00 |
| 1110 | Rock soundings | LF A A | 197.60 | $42.60 | $37.00 | $75.00 | $62.00 |
| 1120 | Rock corings | LF A A | 120 | $76.50 | $70.00 | $100.00 | $105.00 |
| 1130 | CSL testing (6 tubes) | EACH A A | 4 | $8,717.00 | $7,500.00 | $6,000.00 | $1,500.00 |
| 1140 | Drilled shaft-72 in-rock | LF A A | 48 | $5,744.00 | $5,400.00 | $6,000.00 | $5,100.00 |
| 1150 | Concrete sealing | SQFT A A | 25,924 | $2.50 | $1.35 | $2.00 | $2.50 |
| 1160 | Deck drain | EACH A A | 10 | $1,000.00 | $825.00 | $1,500.00 | $1,250.00 |
| 1170 | Drilled shaft-78 in common | LF A A | 192 | $1,929.00 | $2,100.00 | $1,500.00 | $4,150.00 |
| 1180 | PVC conduit-3 in-schedule 80 | LF A A | 298.30 | $12.85 | $12.85 | $12.85 | $16.00 |
| 1190 | Rail system single slope - 40 in | LF A A | 537 | $150.00 | $175.00 | $150.00 | $160.00 |
| 1200 | Mobilization for concrete surf treatment | LS A A | 1 | $500.00 | $1,500.00 | $500.00 | $1,500.00 |
| 1210 | W cap existing main | EACH A A | 2 | $1,905.00 | $1,774.00 | $1,905.00 | $2,250.00 |
| 1220 | W pipe PVC 08 inch | LF A A | 310 | $53.25 | $74.46 | $53.25 | $60.00 |
| 1230 | W tie-in 08 inch | EACH A A | 2 | $2,725.00 | $5,469.00 | $2,725.00 | $3,500.00 |
| 1240 | W valve 08 inch | EACH A A | 2 | $3,850.00 | $3,737.00 | $3,850.00 | $4,500.00 |
| 1250 | W encasement steel open cut range 4 inst | LF A A | 240 | $160.00 | $297.00 | $160.00 | $185.00 |
| 1260 | S force main PE/plastic 04 inch | LF A A | 307 | $37.15 | $110.35 | $37.15 | $42.50 |
| 1270 | S manhole | EACH A A | 2 | $3,680.00 | $7,579.50 | $3,680.00 | $4,250.00 |
| 1280 | S manhole tap existing | EACH A A | 3 | $1,300.00 | $2,000.00 | $1,300.00 | $2,000.00 |
| 1290 | S pipe PVC 08 inch | LF A A | 110 | $146.80 | $85.03 | $146.80 | $185.00 |
| 1300 | S pump station | EACH A A | 1 | $242,690 | $246,277 | $242,690 | $305,000 |
| 1310 | S cap existing main | EACH A A | 5 | $915.00 | $700.00 | $915.00 | $1,000.00 |
| 1320 | G encasement steel open cut range 1 | LF A A | 150 | $310.00 | $177.12 | $260.00 | $180.00 |
| 1330 | G pipe polyethylene/plastic 02 inch | LF A A | 256 | $48.00 | $21.96 | $58.00 | $23.00 |
| 1340 | G valve steel 02 inch | EACH A A | 2 | $850.00 | $1,406.00 | $2,610.00 | $1,500.00 |
| 1350 | G cap existing main | EACH A A | 2 | $1,200.00 | $510.00 | $860.00 | $650.00 |
| 1360 | Pole base | EACH A A | 2 | $4,101.77 | $4,102.00 | $1,520.66 | $4,500.00 |
| 1370 | Lighting control equipment | EACH A A | 1 | $38,001 | $38,001 | $38,001 | $50,000 |
| 1380 | Trenching and backfilling | LF A A | 605 | $12.40 | $12.40 | $12.40 | $14.00 |
| 1390 | Wire-no. 12 | LF A A | 400 | $2.20 | $2.20 | $2.20 | $2.50 |
| 1400 | Electrical junction box type A | EACH A A | 4 | $1,520.66 | $1,521.00 | $1,520.66 | $2,500.00 |
| 1410 | Bore and jack conduit | LF A A | 63 | $126.51 | $127.00 | $126.51 | $140.00 |
| 1420 | Install luminaire pole | EACH A A | 4 | $1,626.97 | $1,627.00 | $1,626.96 | $2,100.00 |
| 1430 | Wire-no. 10 | LF A A | 2,100 | $2.57 | $2.57 | $2.57 | $2.75 |
| 1440 | PVC conduit-2 in-schedule 80 | LF A A | 668 | $8.34 | $8.50 | $8.34 | $9.00 |
| 1450 | Mobilization | LS A A | 1 | $272,988 | $314,991 | $350,000 | $415,000 |
| 1460 | Demobilization | LS A A | 1 | $94,031 | $105,000 | $115,000 | $124,650 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of May 21, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.