KYTC contract 25-2931 bid tabulation
BRIDGE WITH GRADE & DRAIN STURGEON CREEK BRIDGE (KY 1334). Let by Kentucky Transportation Cabinet on October 23, 2025. 4 bids received; low bid $781,100 by Frederick & May Construction Co, -16% against the engineer's estimate of $933,442.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 OCT 2025
- Pay items
- 41
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Frederick & May Construction Co | $781,100 | Low | -16% |
| 2 | Walker Construction & Materials LLC | $869,420 | +11% | -7.0% |
| 3 | Landmark Construction LLC | $880,377 | +13% | -6.0% |
| 4 | M & M Services Co Inc | $916,457 | +17% | -2.0% |
Engineer's estimate: $933,442.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Frederick & May Construction Co | 2. Walker Construction & Materials LLC | 3. Landmark Construction LLC | 4. M & M Services Co Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 162 | $70.00 | $70.00 | $70.00 | $55.00 |
| 0020 | Crushed aggregate size no 2 | TON A A | 461 | $40.00 | $50.00 | $65.00 | $55.00 |
| 0030 | CL2 asph base 1.00D PG64-22 | TON A A | 215 | $220.75 | $220.75 | $220.75 | $135.00 |
| 0040 | Asphalt prime coat | TON A A | 0.49 | $5,105.00 | $5,105.00 | $5,105.00 | $1,350.00 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A A | 54 | $238.75 | $238.75 | $238.75 | $140.00 |
| 0060 | Fabric-geotextile class 1 | SQYD A A | 755 | $2.00 | $2.50 | $2.95 | $2.00 |
| 0070 | Fabric-geotextile class 1A | SQYD A A | 667 | $3.50 | $5.00 | $4.00 | $3.00 |
| 0080 | Asphalt material for tack non-tracking | TON A A | 0.44 | $10.00 | $10.00 | $10.00 | $1,450.00 |
| 0090 | Embankment in place | CUYD A A | 1,280 | $15.00 | $58.00 | $75.00 | $165.00 |
| 0100 | Channel lining class III | TON A A | 700 | $50.00 | $60.00 | $50.00 | $75.00 |
| 0110 | Clearing and grubbing | LS A A | 1 | $10,233 | $35,000 | $8,500.00 | $9,500.00 |
| 0120 | Object marker type 2 | EACH A A | 4 | $250.00 | $250.00 | $100.00 | $145.00 |
| 0130 | Maintain & control traffic | LS A A | 1 | $1,500.00 | $5,000.00 | $3,500.00 | $18,500 |
| 0140 | Portable changeable message sign | EACH A A | 2 | $1,500.00 | $1.00 | $4,250.00 | $2,800.00 |
| 0150 | Staking | LS A A | 1 | $12,000 | $4,250.00 | $4,000.00 | $11,500 |
| 0160 | Steel post type 1 | LF A A | 40 | $42.00 | $75.00 | $32.00 | $45.00 |
| 0170 | Pave striping-perm paint-4 in | LF A A | 802 | $2.50 | $4.50 | $3.00 | $2.00 |
| 0180 | Joint adhesive | LF A A | 401 | $17.50 | $17.50 | $17.50 | $1.00 |
| 0190 | Erosion control | LS A A | 1 | $7,500.00 | $4,140.40 | $2,500.00 | $7,500.00 |
| 0200 | Turf reinforcement mat 4 | SQYD A A | 1,072 | $54.00 | $10.00 | $30.00 | $5.00 |
| 0210 | Electronic delivery MGMT system - agg | LS A A | 1 | $500.00 | $500.00 | $200.00 | $4,500.00 |
| 0220 | Perforated pipe-6 in | LF A A | 758 | $12.50 | $17.00 | $12.00 | $11.00 |
| 0230 | Non-perforated pipe-6 in | LF A A | 48 | $20.00 | $27.00 | $20.00 | $11.00 |
| 0240 | Inspect & certify edge drain system | LS A A | 1 | $2,500.00 | $2,500.00 | $8,500.00 | $15,000 |
| 0250 | Perf pipe headwall TY 1-6 in | EACH A A | 4 | $1,100.00 | $1,250.00 | $900.00 | $2,100.00 |
| 0260 | Structure granular backfill | CUYD A A | 135 | $60.00 | $75.00 | $60.00 | $65.00 |
| 0270 | Armored edge for concrete | LF A A | 32 | $150.00 | $145.00 | $75.00 | $80.00 |
| 0280 | Structure excav-solid rock | CUYD A A | 38 | $100.00 | $145.00 | $250.00 | $150.00 |
| 0290 | Foundation preparation | LS A A | 1 | $45,500 | $35,000 | $91,500 | $32,000 |
| 0300 | Cyclopean stone rip rap | TON A A | 169 | $50.00 | $65.00 | $60.00 | $70.00 |
| 0310 | Test piles | LF A A | 28 | $155.00 | $120.00 | $288.00 | $255.00 |
| 0320 | Piles-steel HP12X53 | LF A A | 118 | $145.00 | $120.00 | $288.00 | $185.00 |
| 0330 | Pile points-12 in | EACH A A | 6 | $130.00 | $130.00 | $128.00 | $185.00 |
| 0340 | Concrete-class A | CUYD A A | 60.60 | $1,200.00 | $990.00 | $850.00 | $1,050.00 |
| 0350 | Concrete-class AA | CUYD A A | 36.90 | $2,100.00 | $2,990.00 | $1,400.00 | $1,450.00 |
| 0360 | Steel reinforcement | LB A A | 2,801 | $2.00 | $4.00 | $2.00 | $1.90 |
| 0370 | Steel reinforcement-epoxy coated | LB A A | 6,136 | $2.25 | $4.00 | $2.30 | $2.25 |
| 0380 | Precast PC box beam CB42-48 | LF A A | 392 | $580.00 | $625.00 | $615.00 | $580.00 |
| 0390 | Concrete sealing | SQFT A A | 2,542 | $2.50 | $2.00 | $2.00 | $2.80 |
| 0400 | Mobilization for concrete surf treatment | LS A A | 1 | $1,000.00 | $750.00 | $1,000.00 | $1,800.00 |
| 0410 | Demobilization | LS A A | 1 | $11,544 | $13,320 | $13,193 | $14,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of October 23, 2025. Compiled by Mirage Metrics.