KYTC contract 25-5374 bid tabulation
BRIDGE REPLACEMENT KY 36. Let by Kentucky Transportation Cabinet on March 20, 2025, Carroll, District 6. 4 bids received; low bid $2,869,393 by Haydon Bridge Company Inc, +7.8% against the engineer's estimate of $2,660,774.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 MAR 2025
- Pay items
- 61
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Haydon Bridge Company Inc | $2,869,393 | Low | +8.0% |
| 2 | Hinkle Construction Services LLC | $2,980,599 | +4.0% | +12% |
| 3 | Galusha Contracting LLC | $2,985,258 | +4.0% | +12% |
| 4 | E & B Paving LLC | $3,470,500 | +21% | +30% |
Engineer's estimate: $2,660,774.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Haydon Bridge Company Inc | 2. Hinkle Construction Services LLC | 3. Galusha Contracting LLC | 4. E & B Paving LLC |
|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A | 2,920 | $36.00 | $39.00 | $36.85 | $54.00 |
| 0020 | Asphalt seal aggregate | TON A | 7 | $800.00 | $960.00 | $490.00 | $1,800.00 |
| 0030 | Asphalt seal coat | TON A | 1 | $2,500.00 | $1,910.00 | $1,575.00 | $1.00 |
| 0040 | CL2 asph base 1.00D PG64-22 | TON A | 1,551 | $85.00 | $97.00 | $93.00 | $93.00 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A | 258 | $120.00 | $133.00 | $133.00 | $138.00 |
| 0060 | Asphalt material for tack | TON A | 3 | $1.00 | $1.05 | $11.00 | $1.00 |
| 0070 | Culvert pipe-24 in | LF A | 73 | $140.00 | $200.00 | $155.00 | $240.00 |
| 0080 | Pipe culvert headwall-24 in | EACH A | 2 | $2,500.00 | $2,320.00 | $4,400.00 | $3,600.00 |
| 0090 | Plug pipe | EACH A | 2 | $500.00 | $900.00 | $900.00 | $1,000.00 |
| 0100 | Delineator for guardrail mono directional white | EACH A | 41 | $17.00 | $17.25 | $17.00 | $16.19 |
| 0110 | Barricade-type III | EACH A | 1 | $160.00 | $155.00 | $1,000.00 | $132.50 |
| 0120 | Remove pavement | SQYD A | 2,400 | $9.00 | $3.15 | $20.00 | $14.00 |
| 0130 | Embankment in place | CUYD A | 7,692 | $26.50 | $49.35 | $34.65 | $69.00 |
| 0140 | Guardrail-steel W beam-S face | LF A | 2,062.50 | $31.05 | $31.60 | $31.00 | $29.57 |
| 0150 | Guardrail terminal section no 1 | EACH A | 1 | $94.67 | $96.00 | $91.00 | $90.16 |
| 0160 | Guardrail end treatment type 1 | EACH A | 1 | $3,709.37 | $3,775.00 | $3,710.00 | $3,532.73 |
| 0170 | Guardrail end treatment type 4A | EACH A | 3 | $4,057.03 | $4,125.00 | $4,057.00 | $3,863.84 |
| 0180 | Extra length guardrail post | EACH A | 317 | $61.64 | $62.00 | $61.60 | $58.70 |
| 0190 | Clearing and grubbing | LS A | 1 | $95,000 | $16,025 | $27,000 | $39,870 |
| 0200 | Temporary signs | SQFT A | 110 | $10.00 | $7.80 | $4.00 | $7.42 |
| 0210 | Edge key | LF A | 36 | $50.00 | $55.00 | $32.00 | $65.00 |
| 0215 | Maintain & control traffic | LS A | 1 | $42,500 | $23,600 | $44,330 | $95,000 |
| 0220 | Portable changeable message sign | EACH A | 2 | $10,000 | $7,570.00 | $9,500.00 | $9,222.00 |
| 0230 | Edgeline rumble strips | LF A | 3,664 | $1.79 | $1.85 | $1.75 | $2.75 |
| 0240 | Staking | LS A | 1 | $15,000 | $30,000 | $20,000 | $63,000 |
| 0250 | Pave striping-thermo-6 in W | LF A | 2,814 | $1.68 | $1.70 | $1.50 | $1.60 |
| 0260 | Pave striping-thermo-6 in Y | LF A | 2,814 | $1.68 | $1.70 | $1.50 | $1.60 |
| 0270 | Pave striping-dur TY 1-6 in W | LF A | 508 | $7.88 | $7.90 | $10.00 | $7.50 |
| 0280 | Pave striping-dur TY 1-6 in Y | LF A | 508 | $7.88 | $7.90 | $10.00 | $7.50 |
| 0290 | S directional bore | LF A | 418 | $165.00 | $210.00 | $210.00 | $61.19 |
| 0300 | S force main air RLS/vac VLV 02 in | EACH A | 2 | $8,500.00 | $15,400 | $15,300 | $8,669.50 |
| 0310 | S force main PE/plastic 06 inch | LF A | 1,495 | $68.00 | $40.00 | $40.00 | $68.88 |
| 0320 | S force main tie-in 06 inch | EACH A | 2 | $3,250.00 | $2,645.00 | $2,625.00 | $4,089.50 |
| 0330 | S force main valve gate | EACH A | 2 | $2,500.00 | $1,900.00 | $1,890.00 | $9,782.00 |
| 0340 | S line marker | EACH A | 4 | $195.00 | $105.00 | $105.00 | $1,625.50 |
| 0350 | Erosion control | LS A | 1 | $30,000 | $48,000 | $35,000 | $90,000 |
| 0360 | Mobilization for concrete surf treatment | LS A | 1 | $1,500.00 | $1,780.00 | $500.00 | $3,000.00 |
| 0370 | Structure granular backfill | CUYD A | 100 | $95.00 | $120.00 | $72.00 | $100.00 |
| 0380 | Remove structure | LS A | 1 | $125,000 | $114,075 | $125,000 | $179,534 |
| 0390 | Armored edge for concrete | LF A | 139 | $175.00 | $100.00 | $147.00 | $160.00 |
| 0400 | Structure excav-solid rock | CUYD A | 68 | $0.01 | $12.00 | $125.00 | $392.00 |
| 0410 | Foundation preparation | LS A | 1 | $125,000 | $126,420 | $185,000 | $22,000 |
| 0420 | Cyclopean stone rip rap | TON A | 1,013 | $72.00 | $72.50 | $58.00 | $135.00 |
| 0430 | Test piles | LF A | 94 | $325.00 | $126.00 | $173.00 | $350.00 |
| 0440 | Piles-steel HP12X53 | LF A | 369 | $95.00 | $148.00 | $92.00 | $145.00 |
| 0450 | Pile points-12 in | EACH A | 17 | $225.00 | $150.00 | $180.00 | $192.00 |
| 0460 | Concrete-class A | CUYD A | 105 | $1,695.00 | $2,530.00 | $2,023.00 | $1,935.00 |
| 0470 | Concrete-class AA | CUYD A | 130 | $2,100.00 | $1,835.00 | $2,575.00 | $2,250.00 |
| 0480 | Steel reinforcement | LB A | 20,535 | $1.86 | $1.25 | $1.86 | $1.60 |
| 0490 | Steel reinforcement-epoxy coated | LB A | 42,425 | $1.63 | $1.45 | $1.70 | $1.70 |
| 0495 | Approach slab | SQYD A | 112 | $695.00 | $920.00 | $686.00 | $468.00 |
| 0500 | Precast PC box beam SB27 | LF A | 576 | $425.00 | $382.00 | $440.00 | $410.00 |
| 0502 | Rock soundings | LF A | 29.40 | $115.00 | $95.00 | $100.00 | $25.00 |
| 0504 | Rock corings | LF A | 84 | $215.00 | $210.00 | $210.00 | $80.00 |
| 0510 | CSL testing (4 tubes) | EACH A | 4 | $1,275.00 | $2,420.00 | $1,500.00 | $4,180.00 |
| 0520 | Concrete sealing | SQFT A | 8,682 | $2.45 | $2.00 | $1.75 | $1.30 |
| 0522 | Drilled shaft-48 in-common | LF A | 22.40 | $2,800.00 | $2,320.00 | $2,460.00 | $2,785.00 |
| 0524 | Drilled shaft-42 in-rock | LF A | 42 | $3,000.00 | $2,320.00 | $1,660.00 | $3,538.00 |
| 0530 | Rail system side mounted MGS | LF A | 394 | $258.13 | $260.00 | $258.15 | $245.84 |
| 0540 | Mobilization | LS A | 1 | $134,400 | $130,000 | $140,152 | $142,000 |
| 0550 | Demobilization | LS A | 1 | $40,685 | $60,100 | $42,046 | $53,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of March 20, 2025. Compiled by Mirage Metrics.