KYTC contract 25-5400 bid tabulation
BRIDGE REPLACEMENT KY 1046. Let by Kentucky Transportation Cabinet on December 11, 2025. 7 bids received; low bid $813,571 by Cambry Contracting Inc, -7.9% against the engineer's estimate of $883,042.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 11 DEC 2025
- Pay items
- 53
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cambry Contracting Inc | $813,571 | Low | -8.0% |
| 2 | Galusha Contracting LLC | $872,540 | +7.0% | -1.0% |
| 3 | Jave LLC | $927,058 | +14% | +5.0% |
| 4 | Scott and Murphy Inc | $951,364 | +17% | +8.0% |
| 5 | Ragle Inc | $961,192 | +18% | +9.0% |
| 6 | Hall Contracting of Kentucky Inc | $1,065,000 | +31% | +21% |
| 7 | Adams Contracting LLC | $1,142,482 | +40% | +29% |
Engineer's estimate: $883,042.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cambry Contracting Inc | 2. Galusha Contracting LLC | 3. Jave LLC | 4. Scott and Murphy Inc | 5. Ragle Inc | 6. Hall Contracting of Kentucky Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 505 | $59.50 | $60.00 | $62.48 | $59.50 | $59.50 | $59.50 |
| 0020 | Asphalt seal aggregate | TON A A | 5 | $210.00 | $300.00 | $220.50 | $210.00 | $210.00 | $210.00 |
| 0030 | Asphalt seal coat | TON A A | 1 | $720.00 | $800.00 | $756.00 | $720.00 | $720.00 | $720.00 |
| 0040 | CL2 asph base 1.00D PG64-22 | TON A A | 265 | $222.50 | $226.00 | $233.63 | $222.50 | $222.50 | $222.50 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A A | 46 | $326.50 | $330.00 | $342.62 | $326.50 | $326.50 | $326.50 |
| 0060 | Asphalt material for tack | TON A A | 1 | $849.50 | $850.00 | $891.98 | $849.50 | $849.50 | $849.50 |
| 0070 | Entrance pipe-24 in | LF A A | 107 | $100.00 | $160.00 | $106.22 | $115.88 | $105.00 | $90.00 |
| 0080 | Delineator for guardrail BI directional white | EACH A A | 10 | $17.39 | $18.00 | $18.26 | $17.39 | $17.39 | $17.39 |
| 0090 | Barricade-type III | EACH A A | 8 | $100.00 | $100.00 | $78.75 | $150.00 | $300.00 | $100.00 |
| 0100 | Roadway excavation | CUYD A A | 458 | $35.00 | $62.00 | $63.78 | $70.68 | $30.00 | $50.00 |
| 0110 | Granular embankment | CUYD A A | 112 | $50.00 | $71.00 | $158.20 | $160.35 | $105.00 | $85.00 |
| 0120 | Guardrail terminal section no 1 | EACH A A | 2 | $101.57 | $102.00 | $106.65 | $101.57 | $101.57 | $101.57 |
| 0130 | Guardrail end treatment type 7 | EACH A A | 2 | $2,132.57 | $2,135.00 | $2,239.16 | $2,132.57 | $2,132.57 | $2,132.57 |
| 0140 | Right-of-way monument type 1 | EACH A A | 10 | $208.65 | $210.00 | $332.22 | $335.88 | $208.65 | $208.65 |
| 0150 | Witness post | EACH A A | 10 | $171.56 | $175.00 | $53.11 | $320.31 | $171.56 | $171.56 |
| 0160 | Channel lining class II | TON A A | 262 | $45.00 | $85.00 | $98.31 | $60.25 | $65.00 | $65.00 |
| 0170 | Clearing and grubbing | LS A A | 1 | $5,000.00 | $5,500.00 | $25,222 | $10,988 | $10,000 | $25,000 |
| 0180 | Temporary signs | SQFT A A | 216 | $8.00 | $10.00 | $8.93 | $12.77 | $20.00 | $9.00 |
| 0190 | Edge key | LF A A | 43 | $67.00 | $70.00 | $70.35 | $67.00 | $67.00 | $67.00 |
| 0200 | Fabric-geotextile class 1 | SQYD A A | 510 | $2.50 | $3.00 | $2.44 | $3.97 | $2.50 | $2.50 |
| 0210 | Maintain & control traffic | LS A A | 1 | $5,565.00 | $10,000 | $2,825.00 | $11,973 | $20,000 | $60,000 |
| 0220 | Portable changeable message sign | EACH A A | 2 | $2,000.00 | $2,400.00 | $2,467.50 | $2,760.00 | $3,500.00 | $2,500.00 |
| 0230 | Staking | LS A A | 1 | $5,000.00 | $6,000.00 | $7,345.00 | $4,472.65 | $12,500 | $40,000 |
| 0240 | Remove structure | LS A A | 1 | $58,500 | $18,500 | $21,221 | $51,410 | $83,500 | $55,000 |
| 0250 | Pave striping-perm paint-4 in | LF A A | 268 | $3.00 | $5.00 | $4.99 | $4.00 | $4.75 | $3.50 |
| 0260 | Pave striping-dur TY 1-4 in Y | LF A A | 63 | $3.00 | $17.00 | $16.80 | $16.00 | $16.00 | $10.00 |
| 0270 | Erosion control | LS A A | 1 | $1,000.00 | $5,500.00 | $9,853.60 | $6,620.85 | $20,000 | $26,000 |
| 0280 | G/R steel W beam-S face (7 FT post) | LF A A | 150 | $45.11 | $47.00 | $47.37 | $45.11 | $45.11 | $45.11 |
| 0290 | Sloped and mitered headwall-24 in | EACH A A | 4 | $3,500.00 | $4,200.00 | $3,580.97 | $3,219.25 | $3,200.00 | $3,800.00 |
| 0300 | Electronic delivery MGMT system - agg | LS A A | 1 | $2,000.00 | $2,500.00 | $2,100.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 0301 | W cap existing main | EACH A A | 2 | $3,800.00 | $3,876.00 | $3,990.00 | $3,800.00 | $3,800.00 | $4,000.00 |
| 0302 | W directional bore | LF A A | 221 | $695.00 | $708.00 | $729.75 | $695.00 | $695.00 | $700.00 |
| 0303 | W pipe PVC 04 inch | LF A A | 32 | $220.00 | $224.00 | $231.00 | $220.00 | $220.00 | $230.00 |
| 0304 | W tapping sleeve and valve size 1 | EACH A A | 2 | $7,400.00 | $7,548.00 | $7,770.00 | $7,400.00 | $7,400.00 | $7,500.00 |
| 0305 | W valve special | EACH A A | 2 | $15,000 | $15,300 | $15,750 | $15,000 | $15,000 | $16,000 |
| 0306 | W line marker | EACH A A | 4 | $150.00 | $153.00 | $157.50 | $150.00 | $150.00 | $160.00 |
| 0307 | W leak detection meter | EACH A A | 1 | $4,400.00 | $4,488.00 | $4,620.00 | $4,400.00 | $4,400.00 | $4,500.00 |
| 0308 | W blowoff assembly | EACH A A | 1 | $3,900.00 | $3,978.00 | $4,095.00 | $3,900.00 | $3,900.00 | $4,000.00 |
| 0310 | Structure granular backfill | CUYD A A | 91 | $70.00 | $51.00 | $123.17 | $95.13 | $130.00 | $100.00 |
| 0320 | Armored edge for concrete | LF A A | 50 | $85.00 | $102.21 | $103.96 | $117.28 | $96.50 | $85.00 |
| 0330 | Foundation preparation | LS A A | 1 | $25,000 | $35,000 | $15,667 | $8,988.39 | $20,000 | $43,000 |
| 0340 | Cyclopean stone rip rap | TON A A | 310 | $45.00 | $55.00 | $76.84 | $59.38 | $85.00 | $95.00 |
| 0350 | Test piles | LF A A | 90 | $200.00 | $118.40 | $144.64 | $134.34 | $100.00 | $200.00 |
| 0360 | Piles-steel HP12X53 | LF A A | 286 | $60.00 | $93.19 | $135.60 | $98.72 | $100.00 | $200.00 |
| 0370 | Pile points-12 in | EACH A A | 10 | $155.00 | $185.00 | $174.02 | $216.70 | $180.00 | $175.00 |
| 0380 | Concrete-class A | CUYD A A | 31 | $1,300.00 | $979.78 | $1,572.96 | $1,679.89 | $1,300.00 | $1,500.00 |
| 0390 | Concrete-class AA | CUYD A A | 23 | $2,000.00 | $3,060.30 | $2,107.45 | $4,166.47 | $2,750.00 | $2,500.00 |
| 0400 | Steel reinforcement-epoxy coated | LB A A | 5,800 | $1.95 | $2.05 | $2.75 | $2.14 | $3.50 | $2.05 |
| 0410 | Precast PC box beam CB21-48 | LF A A | 300 | $325.00 | $352.00 | $349.88 | $371.87 | $360.00 | $320.00 |
| 0420 | Concrete sealing | SQFT A A | 4,850 | $1.00 | $2.00 | $2.90 | $2.74 | $2.00 | $1.15 |
| 0430 | Rail system side mounted MGS | LF A A | 100 | $229.71 | $245.00 | $241.20 | $235.12 | $229.71 | $210.00 |
| 0440 | Mobilization for concrete surf treatment | LS A A | 1 | $1,500.00 | $750.00 | $5,650.00 | $2,130.20 | $750.00 | $2,500.00 |
| 0450 | Demobilization | LS A A | 1 | $12,204 | $12,895 | $13,700 | $14,270 | $15,000 | $17,475 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of December 11, 2025. Compiled by Mirage Metrics.