KYTC letting results, May 23, 2024
34 contracts let by Kentucky Transportation Cabinet on May 23, 2024, $62,688,141 in low bids, a median of 1.5 bidders per contract. On the 34 with an engineer's estimate, the low bid came in under it 18 times; median low bid -1.0% against the estimate.
- Owner
- Kentucky Transportation Cabinet
- Contracts
- 34
- Low bids, total
- $62,688,141
- Data through
- 22 OCT 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 24-1311 | GRADE & DRAIN WITH ASPHALT SURFACE SKYVIEW LANE (CR 2156) | District 10 | 4 | Frederick & May Construction Co | $12,655,206 | $14,139,572 | +12% | -22% | KYTC |
| 24-5351 | BRIDGE REPAIRS KY 644 | District 12 | 1 | Bush & Burchett Inc | $8,553,398 | +160% | KYTC | ||
| 24-5347 | BRIDGE REPLACEMENT KY 7 | District 12 | 3 | Bush & Burchett Inc | $5,221,632 | $7,433,414 | +42% | -24% | KYTC |
| 24-5348 | BRIDGE REPLACEMENT VARIOUS ROUTES IN DISTRICT 1 | District 1 | 2 | Jim Smith Contracting Company LLC | $4,229,832 | $4,806,747 | +14% | +3.0% | KYTC |
| 24-1105 | GRADE & DRAIN WITH ASPHALT SURFACE US 127 (US 127) | District 5 | 6 | L-M Asphalt Partners LTD D/B/A Ats Construction | $3,998,634 | $4,377,516 | +9.0% | -24% | KYTC |
| 24-2992 | BRIDGE STEEL REPAIRS CARROL CROPPER BRIDGE (I-275) | District 6 | 5 | M & M Services Co Inc | $3,625,993 | $3,796,951 | +5.0% | -44% | KYTC |
| 24-2022 | ASPHALT RESURFACING CHRISTIAN COUNTY (US 41A & KY 107) | District 2 | 1 | Rogers Group Inc | $3,059,915 | +3.0% | KYTC | ||
| 24-5346 | BRIDGE REPLACEMENT KY 1950 | District 10 | 5 | Frederick & May Construction Co | $2,338,741 | $2,434,593 | +4.0% | -30% | KYTC |
| 24-2184 | ASPHALT RESURFACING INDUSTRIAL BYPASS N (KY 1008) | District 3 | 1 | Scotty'S Contracting & Stone LLC | $2,144,791 | +4.0% | KYTC | ||
| 24-2182 | ASPHALT RESURFACING SOMERSET TO LEVEL GREEN ROAD (KY 461) | District 8 | 1 | Hinkle Contracting Company LLC | $1,890,054 | +7.0% | KYTC | ||
| 24-2977 | BRIDGE VARIOUS ROUTES IN LEWIS COUNTY ~ 2 LOCATIONS | District 9 | 3 | Frederick & May Construction Co | $1,821,820 | $1,894,123 | +4.0% | -20% | KYTC |
| 24-2169 | ASPHALT RESURFACING CRITTENDEN COUNTY (KY 91, US 60, AND KY 981) | District 1 | 1 | Rogers Group Inc | $1,630,638 | +9.0% | KYTC | ||
| 24-5349 | BRIDGE REPLACEMENT VARIOUS ROUTES IN DISTRICT 4 | District 4 | 6 | Galusha Contracting LLC | $1,518,227 | $1,555,137 | +2.0% | -3.0% | KYTC |
| 24-2213 | ASPHALT RESURFACING DAVIESS COUNTY (KY 54 & KY 298) | District 2 | 2 | E & B Paving LLC | $975,721 | $1,009,753 | +3.0% | -4.0% | KYTC |
| 24-2166 | ASPHALT RESURFACING STRAIGHT CREEK ROAD (KY 221) | District 11 | 1 | Hinkle Contracting Company LLC | $852,816 | +9.0% | KYTC | ||
| 24-2196 | ASPHALT RESURFACING BEAVER DAMN TO ROSINE ROAD (US 62) | District 2 | 1 | Scotty'S Contracting & Stone LLC | $782,637 | +7.0% | KYTC | ||
| 24-2168 | ASPHALT RESURFACING DYCUSBURG TO FRANCES ROAD (KY 70) | District 1 | 1 | Rogers Group Inc | $748,444 | +10% | KYTC | ||
| 24-2177 | ASPHALT RESURFACING HENSLEY TO BASIN SPRINGS ROAD (US 60) | District 4 | 3 | Mago Construction Company LLC | $704,062 | $747,266 | +6.0% | -25% | KYTC |
| 24-2197 | ASPHALT RESURFACING PELLVILLE TO CLOVERPORT ROAD (KY 144) | District 2 | 2 | Mago Construction Company LLC | $667,381 | $690,697 | +3.0% | -19% | KYTC |
| 24-2180 | ASPHALT RESURFACING SOUTH DIXIE STREET (US 31W) | District 4 | 2 | Scotty'S Contracting & Stone LLC | $613,828 | $616,599 | 0.0% | +5.0% | KYTC |
| 24-2993 | BRIDGE WITH GRADE, DRAIN & SURFACE SANDY CREEK ROAD (KY 1153) | District 3 | 4 | Knight Construction & Excavating Inc | $567,559 | $594,772 | +5.0% | +5.0% | KYTC |
| 24-5350 | BRIDGE REPLACEMENT KY 225 | District 11 | 7 | Irvine Contracting Limited Liability Company | $546,813 | $580,675 | +6.0% | -26% | KYTC |
| 24-2181 | ASPHALT RESURFACING 9TH STREET (KY 3240) OMIT MP'S 1.100-1.500 | District 3 | 1 | Scotty'S Contracting & Stone LLC | $537,731 | +4.0% | KYTC | ||
| 24-2178 | GUARDRAIL KY 727 & KY 779 IN WHITLEY COUNTY | District 11 | 2 | George B Stone Co LLC | $494,021 | $921,446 | +87% | -3.0% | KYTC |
| 24-2139 | ASPHALT RESURFACING BUTLER TO GRANT LICKS ROAD (US 27) | District 6 | 2 | Mago Construction Company LLC | $470,897 | $561,965 | +19% | -7.0% | KYTC |
| 24-3022 | ASPHALT RESURFACING VARIOUS ROADS IN MERCER CO | District 7 | 1 | Mago Construction Company LLC | $470,584 | +1.0% | KYTC | ||
| 24-2192 | ASPHALT RESURFACING SILER ROAD (KY 92) | District 11 | 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $330,652 | +1.0% | KYTC | ||
| 24-2218 | MICROSURFACING HARDINSBURG ROAD (KY 86) | District 4 | 1 | Strawser Construction Inc | $321,897 | +16% | KYTC | ||
| 24-2183 | GUARDRAIL KY 11 & KY 2418 (KNOX COUNTY) | District 11 | 2 | George B Stone Co LLC | $288,546 | $424,064 | +47% | +3.0% | KYTC |
| 24-2179 | ASPHALT RESURFACING NORTH 25TH STREET (KY 441) | District 11 | 1 | Hinkle Contracting Company LLC | $198,488 | -12% | KYTC | ||
| 24-2150 | ASPHALT RESURFACING MICHIGAN AVE (KY 92) | District 8 | 1 | Mago Construction Company LLC | $180,595 | -2.0% | KYTC | ||
| 24-2212 | ASPHALT RESURFACING MY OLD KENTUCKY HOME STATE PARK | District 4 | 1 | Mago Construction Company LLC | $97,780 | -1.0% | KYTC | ||
| 24-2170 | ASPHALT RESURFACING FIRE DEPARTMENT ROAD (KY 967) | District 1 | 1 | Jim Smith Contracting Company LLC | $88,151 | -12% | KYTC | ||
| 24-2135 | ASPHALT RESURFACING BUCKHORN STATE PARK LODGE ROAD | District 10 | 1 | Mountain Enterprises Inc | $60,657 | -13% | KYTC |
Gap is the second bid over the low bid. Where a contract shows fewer bids than KYTC received, the others did not match their published totals and are left out.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.