KYTC contract 25-5382 bid tabulation
BRIDGE REPLACEMENT KY 138. Let by Kentucky Transportation Cabinet on July 24, 2025. 4 bids received; low bid $6,633,271 by Galusha Contracting LLC, -2.4% against the engineer's estimate of $6,799,163.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 24 JUL 2025
- Pay items
- 84
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Galusha Contracting LLC | $6,633,271 | Low | -2.0% |
| 2 | Scott and Murphy Inc | $7,318,766 | +10% | +8.0% |
| 3 | Ragle Inc | $7,379,967 | +11% | +9.0% |
| 4 | Haydon Bridge Company Inc | $8,892,890 | +34% | +31% |
Engineer's estimate: $6,799,163.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Galusha Contracting LLC | 2. Scott and Murphy Inc | 3. Ragle Inc | 4. Haydon Bridge Company Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 5,517 | $38.00 | $41.45 | $37.98 | $37.98 |
| 0020 | Traffic bound base | TON A A | 123 | $38.00 | $57.25 | $37.98 | $45.00 |
| 0030 | Asphalt seal aggregate | TON A A | 49 | $358.24 | $358.24 | $358.24 | $358.24 |
| 0040 | Asphalt seal coat | TON A A | 8 | $1,380.00 | $1,378.78 | $1,378.78 | $1,378.78 |
| 0050 | CL2 asph base 1.00D PG64-22 | TON A A | 3,058 | $119.00 | $118.71 | $118.71 | $125.00 |
| 0060 | CL2 asph surf 0.38D PG64-22 | TON A A | 575 | $156.25 | $156.25 | $156.25 | $165.00 |
| 0070 | Asphalt wedge curb | LF A A | 87 | $30.00 | $28.00 | $35.00 | $85.00 |
| 0080 | Delineator for barrier - white | EACH A A | 8 | $18.00 | $17.85 | $17.85 | $19.00 |
| 0090 | Delineator for guardrail BI directional white | EACH A A | 18 | $17.00 | $16.19 | $16.19 | $17.00 |
| 0100 | Barricade-type III | EACH A A | 2 | $200.00 | $355.00 | $400.00 | $325.00 |
| 0110 | Remove pavement | SQYD A A | 2,083 | $4.25 | $7.25 | $5.00 | $3.98 |
| 0120 | Special excavation | CUYD A A | 1,072 | $7.26 | $24.00 | $20.00 | $7.26 |
| 0130 | Granular embankment | CUYD A A | 3,058 | $70.00 | $71.00 | $55.00 | $58.00 |
| 0140 | Embankment in place | CUYD A A | 20,610 | $24.25 | $27.10 | $26.00 | $23.09 |
| 0150 | Guardrail-steel W beam-S face | LF A A | 1,737.50 | $32.50 | $32.09 | $32.09 | $35.00 |
| 0160 | Guardrail terminal section no 1 | EACH A A | 4 | $80.00 | $79.11 | $79.11 | $85.00 |
| 0170 | Guardrail end treatment type 1 | EACH A A | 2 | $3,700.00 | $3,698.29 | $3,698.29 | $4,000.00 |
| 0180 | Guardrail end treatment type 7 | EACH A A | 1 | $2,050.00 | $2,024.03 | $2,024.03 | $2,250.00 |
| 0190 | Remove guardrail | LF A A | 1,998 | $4.50 | $4.38 | $4.38 | $10.00 |
| 0200 | Guardrail end treatment type 4A | EACH A A | 1 | $3,900.00 | $3,863.84 | $3,863.84 | $4,150.00 |
| 0210 | Extra length guardrail post | EACH A A | 25 | $61.00 | $60.26 | $60.26 | $61.00 |
| 0220 | Right-of-way monument type 1 | EACH A A | 13 | $475.00 | $320.00 | $166.61 | $175.00 |
| 0230 | Witness post | EACH A A | 13 | $152.00 | $306.00 | $150.06 | $175.00 |
| 0240 | Clearing and grubbing | LS A A | 1 | $30,000 | $54,400 | $32,000 | $495,000 |
| 0250 | Concrete-class B | CUYD A A | 200 | $1,020.00 | $580.00 | $950.00 | $1,200.00 |
| 0260 | Temporary signs | SQFT A A | 81 | $16.05 | $12.75 | $22.00 | $20.00 |
| 0270 | Edge key | LF A A | 93 | $45.00 | $44.79 | $13.00 | $44.79 |
| 0280 | Fabric-geotextile class 2 | SQYD A A | 906 | $2.05 | $2.00 | $2.50 | $2.05 |
| 0290 | Remove headwall | EACH A A | 2 | $369.00 | $600.00 | $300.00 | $368.35 |
| 0300 | Maintain & control traffic | LS A A | 1 | $10,000 | $17,100 | $125,000 | $74,000 |
| 0310 | Portable changeable message sign | EACH A A | 5 | $10,500 | $10,550 | $12,000 | $10,000 |
| 0320 | Shoulder rumble strips | LF A A | 4,199 | $1.75 | $1.10 | $1.50 | $1.95 |
| 0330 | Staking | LS A A | 1 | $45,000 | $7,700.00 | $70,000 | $30,000 |
| 0340 | Remove structure | LS A A | 1 | $356,940 | $352,300 | $300,000 | $200,000 |
| 0350 | Pave striping-temp paint-6 in | LF A A | 2,000 | $0.32 | $0.32 | $0.32 | $0.35 |
| 0360 | Pave striping-thermo-4 in W | LF A A | 786 | $1.15 | $1.15 | $1.15 | $1.25 |
| 0370 | Pave striping-thermo-4 in Y | LF A A | 636 | $1.15 | $1.15 | $1.15 | $1.25 |
| 0380 | Pave striping-thermo-6 in W | LF A A | 3,413 | $1.40 | $1.40 | $1.40 | $1.60 |
| 0390 | Pave striping-thermo-6 in Y | LF A A | 4,154 | $1.40 | $1.40 | $1.40 | $1.60 |
| 0400 | Pave striping-dur TY 1-6 in W | LF A A | 750 | $9.00 | $9.00 | $9.00 | $10.00 |
| 0410 | Pave striping-dur TY 1-6 in Y | LF A A | 750 | $9.00 | $9.00 | $9.00 | $10.00 |
| 0420 | Pave marking-thermo stop bar-24IN | LF A A | 36 | $20.00 | $20.00 | $20.00 | $25.00 |
| 0430 | Structure excavation-common | CUYD A A | 60 | $55.00 | $68.00 | $35.00 | $75.00 |
| 0440 | Fuel adjustment | DOLL A A | 10,829 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0450 | Asphalt adjustment | DOLL A A | 14,125 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0460 | Object marker TY 3 | EACH A A | 3 | $50.00 | $46.00 | $46.00 | $50.00 |
| 0470 | Remove & relocate signs | EACH A A | 21 | $427.84 | $427.84 | $427.84 | $450.00 |
| 0480 | Erosion control | LS A A | 1 | $21,500 | $18,100 | $100,000 | $45,000 |
| 0490 | Drain pond | LS A A | 1 | $10,483 | $8,700.00 | $20,000 | $10,483 |
| 0500 | Pipeline inspection | LF A A | 202 | $13.00 | $12.38 | $15.00 | $12.38 |
| 0510 | Asphalt material for tack non-tracking | TON A A | 4.90 | $770.00 | $769.62 | $769.62 | $769.62 |
| 0520 | Thrie beam guardrail transition TL-3 | EACH A A | 4 | $5,450.00 | $4,443.00 | $3,947.95 | $5,600.00 |
| 0530 | Electronic delivery MGMT system - agg | LS A A | 1 | $500.00 | $0.01 | $1,500.00 | $0.01 |
| 0540 | Turf reinforcement mat | SQYD A A | 815 | $12.00 | $11.13 | $11.13 | $12.00 |
| 0550 | Culvert pipe-18 in | LF A A | 195 | $187.00 | $85.00 | $140.00 | $186.80 |
| 0560 | Remove pipe | LF A A | 139 | $6.75 | $43.00 | $35.00 | $6.62 |
| 0570 | S & F box inlet-outlet-18 in | EACH A A | 4 | $3,110.00 | $3,500.00 | $3,600.00 | $3,101.57 |
| 0580 | Drop box inlet type 1 | EACH A A | 2 | $9,285.00 | $5,800.00 | $8,500.00 | $9,278.87 |
| 0590 | Flume inlet type 2 | EACH A A | 4 | $8,000.00 | $6,500.00 | $4,500.00 | $10,800 |
| 0600 | Structure granular backfill | CUYD A A | 180 | $68.00 | $122.00 | $125.00 | $105.00 |
| 0610 | Armored edge for concrete | LF A A | 56 | $94.00 | $137.00 | $100.00 | $125.00 |
| 0620 | Foundation preparation | LS A A | 1 | $175,000 | $448,400 | $300,000 | $1,250,000 |
| 0630 | Cyclopean stone rip rap | TON A A | 1,700 | $65.00 | $67.00 | $60.00 | $75.00 |
| 0640 | Test piles | LF A A | 405 | $135.00 | $163.00 | $125.00 | $400.00 |
| 0650 | Piles-steel HP14X89 | LF A A | 4,570 | $116.66 | $135.00 | $100.00 | $125.00 |
| 0660 | Pile points-14 in | EACH A A | 58 | $195.00 | $208.00 | $225.00 | $250.00 |
| 0670 | Concrete-class A | CUYD A A | 355 | $1,244.00 | $1,395.00 | $1,265.00 | $1,150.00 |
| 0680 | Concrete-class AA | CUYD A A | 405 | $1,280.00 | $1,204.00 | $1,425.00 | $1,395.00 |
| 0690 | Mechanical reinf coupler #11 | EACH A A | 128 | $225.00 | $250.00 | $195.00 | $250.00 |
| 0700 | Steel reinforcement | LB A A | 66,000 | $1.54 | $1.54 | $2.00 | $1.84 |
| 0710 | Steel reinforcement-epoxy coated | LB A A | 108,689 | $1.67 | $1.65 | $2.10 | $1.99 |
| 0720 | Concrete sealing | SQFT A A | 29,800 | $1.50 | $2.00 | $2.10 | $3.00 |
| 0730 | PPC I-beam type HN 66-49 | LF A A | 1,460 | $763.00 | $984.00 | $1,050.00 | $995.00 |
| 0740 | Rail system type C411 | LF A A | 733.50 | $492.00 | $520.00 | $400.00 | $475.00 |
| 0750 | Mobilization for concrete surf treatment | LS A A | 1 | $1,000.00 | $700.00 | $2,500.00 | $1,750.00 |
| 0760 | Cable-no. 14/5C | LF A A | 315 | $6.05 | $2.11 | $6.02 | $3.00 |
| 0770 | Messenger-10800 LB | LF A A | 89 | $11.60 | $26.28 | $11.55 | $30.00 |
| 0780 | Install steel strain pole | EACH A A | 2 | $15,000 | $4,840.30 | $15,000 | $10,000 |
| 0790 | Install LED beacon-12 in | EACH A A | 8 | $500.00 | $199.24 | $500.00 | $500.00 |
| 0800 | Traffic signal pole base | CUYD A A | 6.80 | $300.00 | $1,693.97 | $300.00 | $1,750.00 |
| 0810 | Install-beacon controller-2 circuit | EACH A A | 1 | $19,700 | $21,168 | $19,626 | $35,000 |
| 0820 | Remove signal equipment | EACH A A | 1 | $10,000 | $4,776.95 | $10,000 | $10,000 |
| 0830 | Mobilization | LS A A | 1 | $308,000 | $258,000 | $343,000 | $415,500 |
| 0840 | Demobilization | LS A A | 1 | $93,300 | $110,513 | $108,000 | $125,743 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of July 24, 2025. Compiled by Mirage Metrics.