KYTC letting results, October 24, 2024
57 contracts let by Kentucky Transportation Cabinet on October 24, 2024, $62,803,893 in low bids, a median of 2 bidders per contract. On the 57 with an engineer's estimate, the low bid came in under it 34 times; median low bid -12% against the estimate.
- Owner
- Kentucky Transportation Cabinet
- Contracts
- 57
- Low bids, total
- $62,803,893
- Data through
- 22 OCT 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 24-1111 | ASPHALT PAVEMENT & ROADWAY REHAB I-69 | District 2 | 1 | Scotty'S Contracting & Stone LLC | $10,043,110 | +2.0% | KYTC | ||
| 24-1318 | GRADE, DRAIN & SURFACE WITH BRIDGE HARTFORD-SEBREE ROAD (KY 136) | District 2 | 2 | Scott and Murphy Inc | $9,588,072 | $11,533,813 | +20% | +5.0% | KYTC |
| 24-2353 | ASPHALT RESURFACING HYDEN - HAZARD - HINDMAN ROAD (KY 80) | District 10 | 1 | Mountain Enterprises Inc | $4,867,853 | +15% | KYTC | ||
| 24-2329 | ASPHALT RESURFACING CANTON ROAD (US 68) | District 1 | 1 | Rogers Group Inc | $3,163,949 | -9.0% | KYTC | ||
| 24-1015 | SLIDE REPAIR BURNSIDE - WHITLEY CITY ROAD (US-27) | District 8 | 5 | Rock & Dirt LLC | $2,930,435 | $4,817,447 | +64% | -24% | KYTC |
| 24-2959 | BRIDGE STEEL REPAIRS COVINGTON-CINCINNATI ROAD (I-275) | District 6 | 3 | M & M Services Co Inc | $2,263,849 | $2,449,683 | +8.0% | -35% | KYTC |
| 24-5366 | BRIDGE REPLACEMENT KY 72 | District 11 | 7 | Kay & Kay Contracting LLC | $1,553,751 | $1,572,520 | +1.0% | -18% | KYTC |
| 24-2339 | ASPHALT RESURFACING LOUISVILLE TO CINCINNATI ROAD (US 42) | District 5 | 5 | E & B Paving LLC | $1,539,000 | $1,582,900 | +3.0% | -25% | KYTC |
| 24-2324 | ASPHALT RESURFACING PORTER PIKE (KY 1402) | District 3 | 1 | Scotty'S Contracting & Stone LLC | $1,504,198 | +9.0% | KYTC | ||
| 24-2352 | ASPHALT RESURFACING BRECKINRIDGE/GRAYSON COUNTIES (KY 259, KY 401, & KY 84) | District 2 | 2 | Scotty'S Contracting & Stone LLC | $1,487,805 | $1,706,838 | +15% | -18% | KYTC |
| 24-2219 | ASPHALT RESURFACING MCCLELLAND CIRCLE (US 62) | District 7 | 2 | Mac Construction & Excavating Inc | $1,419,026 | $1,597,974 | +13% | 0.0% | KYTC |
| 24-2957 | BRIDGE REPAIRS BRANDENBURG ROAD (KY 259) | District 4 | 7 | E & B Paving LLC | $1,415,154 | $1,576,918 | +11% | -28% | KYTC |
| 24-2320 | ASPHALT RESURFACING CAIRO ROAD (KY 305) | District 1 | 1 | Jim Smith Contracting Company LLC | $1,154,266 | -10% | KYTC | ||
| 24-2333 | SLIDE REPAIR BIG SUGAR ROAD (US 127) | District 6 | 2 | Guardian Fence and Construction LLC DBA Guardian Constr | $1,026,382 | $1,050,606 | +2.0% | -35% | KYTC |
| 24-2318 | ASPHALT RESURFACING GREENVILLE ROAD (KY 181) | District 2 | 1 | Scotty'S Contracting & Stone LLC | $997,988 | +9.0% | KYTC | ||
| 24-2348 | ASPHALT RESURFACING HYDEN-HAZARD ROAD (KY 80) | District 11 | 1 | Mountain Enterprises Inc | $916,720 | +9.0% | KYTC | ||
| 24-5365 | BRIDGE REPLACEMENT KY 143 | District 2 | 4 | Galusha Contracting LLC | $897,986 | $1,152,117 | +28% | -32% | KYTC |
| 24-2093 | ASPHALT RESURFACING HOPEWELL - ARGILLITE ROAD (KY 1) | District 9 | 1 | Mountain Enterprises Inc | $837,214 | +3.0% | KYTC | ||
| 24-2175 | ASPHALT RESURFACING FINNEY ROAD (KY 252) | District 3 | 1 | Scotty'S Contracting & Stone LLC | $804,432 | +7.0% | KYTC | ||
| 24-2321 | ASPHALT RESURFACING MANCHESTER - ONEIDA ROAD (KY 11) | District 11 | 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $759,429 | +8.0% | KYTC | ||
| 24-1317 | CULVERT REPLACEMENT KY 522 | District 11 | 6 | Boca Enterprises Inc | $739,654 | $742,518 | 0.0% | -42% | KYTC |
| 24-2332 | ASPHALT RESURFACING BEE CREEK ROAD (KY 1193) | District 11 | 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $679,877 | +11% | KYTC | ||
| 24-3112 | ASPHALT RESURFACING VARIOUS ROADS IN NELSON CO | District 4 | 3 | Mago Construction Company LLC | $677,972 | $718,265 | +6.0% | -16% | KYTC |
| 24-2962 | BRIDGE REPLACEMENT BEE SPRINGS ROAD (KY 238) | District 3 | 5 | Cambry Contracting Inc | $645,399 | $646,209 | 0.0% | -11% | KYTC |
| 24-3110 | ASPHALT RESURFACING VARIOUS ROADS IN MCCREARY CO | District 8 | 1 | Hinkle Contracting Company LLC | $639,556 | +8.0% | KYTC | ||
| 24-3113 | ASPHALT RESURFACING VARIOUS ROUTES IN BOONE CO | District 6 | 2 | Riegler Blacktop Inc | $567,545 | $579,910 | +2.0% | -10% | KYTC |
| 24-3111 | ASPHALT RESURFACING NORTH L AND N TURNPIKE (KY 470) | District 4 | 1 | Scotty'S Contracting & Stone LLC | $559,344 | -1.0% | KYTC | ||
| 24-2342 | ASPHALT RESURFACING BARDSTOWN ROAD (US 62) | District 7 | 3 | Mago Construction Company LLC | $509,539 | $544,000 | +7.0% | -12% | KYTC |
| 24-2349 | ASPHALT RESURFACING POND CREEK ROAD (KY 199) | District 12 | 1 | Mountain Enterprises Inc | $508,263 | +10% | KYTC | ||
| 24-2345 | ASPHALT RESURFACING OLNEY ROAD (KY 1220) | District 2 | 1 | Scotty'S Contracting & Stone LLC | $489,482 | +5.0% | KYTC | ||
| 24-2336 | SLIDE REPAIR MARY INGLES HIGHWAY (KY 8) | District 9 | 2 | Guardian Fence and Construction LLC DBA Guardian Constr | $488,874 | $521,763 | +7.0% | -15% | KYTC |
| 24-3107 | ASPHALT RESURFACING VARIOUS ROADS IN BULLITT CO | District 5 | 6 | Mago Construction Company LLC | $473,891 | $499,725 | +5.0% | -19% | KYTC |
| 24-2343 | ASPHALT RESURFACING LEXINGTON ROAD (US 25) | District 7 | 1 | The Allen Company Inc | $465,821 | +12% | KYTC | ||
| 24-2958 | BRIDGE SUPERSTRUCTURE REPLACEMENT BOSTON ROAD (KY 62) | District 4 | 8 | Galusha Contracting LLC | $457,163 | $491,464 | +8.0% | -13% | KYTC |
| 24-2347 | ASPHALT RESURFACING KEAVY ROAD (KY 363) | District 11 | 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $444,453 | +10% | KYTC | ||
| 24-2331 | SLIDE REPAIR RINGOS MILLS ROAD (KY 158) | District 9 | 2 | Guardian Fence and Construction LLC DBA Guardian Constr | $439,755 | $460,131 | +5.0% | -25% | KYTC |
| 24-2325 | ASPHALT RESURFACING BATTLE TRAINING ROAD (KY 434) | District 4 | 4 | Mac Construction & Excavating Inc | $439,647 | $442,353 | +1.0% | -14% | KYTC |
| 24-2997 | BRIDGE DECK RESTORATION & WATERPROOFING MARY INGLES HIGHWAY (KY 8) AND SANTA FE ROAD (KY 539) | District 6 | 5 | M & M Services Co Inc | $403,297 | $554,804 | +38% | -46% | KYTC |
| 24-2326 | ASPHALT RESURFACING SHREWSBURY ROAD (KY 187) | District 4 | 1 | Scotty'S Contracting & Stone LLC | $401,171 | +15% | KYTC | ||
| 24-3108 | ASPHALT RESURFACING VARIOUS ROADS IN ESTILL CO | District 10 | 1 | Hinkle Contracting Company LLC | $382,737 | +9.0% | KYTC | ||
| 24-2335 | SLIDE REPAIR BLACKBURN - RALEIGH RD (KY 667) | District 2 | 2 | Geostabilization International LLC | $371,773 | $495,603 | +33% | -45% | KYTC |
| 24-2354 | ASPHALT RESURFACING ELKFORK - CROCKETT ROAD (KY 172) | District 10 | 1 | Hinkle Contracting Company LLC | $319,679 | +8.0% | KYTC | ||
| 24-2350 | ASPHALT RESURFACING SEMIWAY TO UNDERWOOD ROAD (KY 1589) | District 2 | 2 | Scotty'S Contracting & Stone LLC | $301,863 | $381,267 | +26% | -24% | KYTC |
| 24-2334 | ASPHALT RESURFACING WINCHESTER ROAD (KY 186) | District 11 | 1 | Hinkle Contracting Company LLC | $275,700 | +15% | KYTC | ||
| 24-3109 | ASPHALT RESURFACING VARIOUS ROADS IN OWSLEY CO | District 10 | 1 | Hinkle Contracting Company LLC | $272,558 | +6.0% | KYTC | ||
| 24-2346 | ASPHALT RESURFACING PASCAL-KING ROAD (KY 140) | District 2 | 2 | Scotty'S Contracting & Stone LLC | $252,595 | $312,610 | +24% | -30% | KYTC |
| 24-2956 | BRIDGE STEEL REPAIRS CERULEAN ROAD (KY 124) | District 1 | 3 | Taylor Bridge Contracting LLC | $248,380 | $266,836 | +7.0% | -37% | KYTC |
| 24-2337 | SLIDE REPAIR HILLSBORO ROAD (KY 111) | District 9 | 4 | M & M Services Co Inc | $247,063 | $297,754 | +21% | -19% | KYTC |
| 24-2327 | ASPHALT RESURFACING CUB RUN HIGHWAY (KY 88) | District 4 | 1 | Scotty'S Contracting & Stone LLC | $215,195 | +28% | KYTC | ||
| 24-2319 | ASPHALT RESURFACING CADIZ ROAD (KY 139 FD05 & FE01) | District 2 | 1 | Rogers Group Inc | $203,831 | -15% | KYTC | ||
| 24-2322 | ASPHALT RESURFACING MOREN ROAD (KY 1769) | District 11 | 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $130,754 | +8.0% | KYTC | ||
| 24-2286 | ASPHALT RESURFACING UPTON MELROSE ROAD (KY 1921) | District 4 | 2 | Scotty'S Contracting & Stone LLC | $88,144 | $92,630 | +5.0% | -17% | KYTC |
| 24-2323 | GUARDRAIL MAGOFFIN COUNTY KY 1081 & MORGAN COUNTY KY 191 | District 10 | 3 | N W K Construction Inc | $81,700 | $89,758 | +10% | -28% | KYTC |
| 24-2351 | GUARDRAIL VANCEBURG - SOUTH SHORE ROAD (KY 8) | District 9 | 3 | George B Stone Co LLC | $68,107 | $81,678 | +20% | -27% | KYTC |
| 24-2311 | ASPHALT RESURFACING INDUSTRIAL ACCESS ROAD (KY 3488) | District 4 | 1 | Haydon Materials LLC | $53,770 | -31% | KYTC | ||
| 24-2344 | GUARDRAIL RAIDER HOLLOW ROAD (KY 1140) | District 4 | 3 | George B Stone Co LLC | $44,982 | $56,242 | +25% | -20% | KYTC |
| 24-2328 | GUARDRAIL CENTER POINT ROAD (KY 100) | District 3 | 3 | George B Stone Co LLC | $43,742 | $50,372 | +15% | -19% | KYTC |
Gap is the second bid over the low bid. Where a contract shows fewer bids than KYTC received, the others did not match their published totals and are left out.