KYTC contract 26-5416 bid tabulation
BRIDGE SUPERSTRUCTURE REPLACEMENT KY 61. Let by Kentucky Transportation Cabinet on August 20, 2026. 3 bids received; low bid $819,057 by Jave LLC, -30% against the engineer's estimate of $1,168,848.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 AUG 2026
- Pay items
- 44
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jave LLC | $819,057 | Low | -30% |
| 2 | Scott and Murphy Inc | $827,319 | +1.0% | -29% |
| 3 | Hinkle Construction Services LLC | $949,819 | +16% | -19% |
Engineer's estimate: $1,168,848.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jave LLC | 2. Scott and Murphy Inc | 3. Hinkle Construction Services LLC |
|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 143 | $74.61 | $51.64 | $47.00 |
| 0012 | Asphalt seal aggregate | TON A A | 0.37 | $267.40 | $262.11 | $275.00 |
| 0015 | Asphalt seal coat | TON A A | 3.10 | $3,259.16 | $3,195.25 | $3,360.00 |
| 0020 | CL2 asph base 1.00D PG64-22 | TON A A | 115 | $267.04 | $261.80 | $275.00 |
| 0030 | CL2 asph surf 0.38D PG64-22 | TON A A | 8 | $520.37 | $510.17 | $540.00 |
| 0035 | Asphalt material for tack | TON A A | 0.04 | $695.39 | $681.75 | $720.00 |
| 0045 | Delineator for G/R BI directional white | EACH A A | 13 | $11.91 | $11.68 | $10.00 |
| 0050 | Barricade-type III | EACH A A | 2 | $153.00 | $310.00 | $150.00 |
| 0060 | Granular embankment | TON A A | 2,595 | $59.10 | $27.74 | $27.00 |
| 0070 | Embankment in place | CUYD A A | 280 | $70.56 | $75.86 | $29.00 |
| 0080 | G/R-W beam-S face TL-3 | LF A A | 100 | $32.70 | $32.06 | $40.00 |
| 0100 | G/R end treatment type 1 | EACH A A | 4 | $3,577.46 | $3,507.31 | $3,450.00 |
| 0105 | G/R end treatment type 7 | EACH A A | 4 | $2,192.65 | $2,149.66 | $1,860.00 |
| 0110 | Temp G/R | LF A A | 500 | $20.20 | $23.59 | $32.00 |
| 0120 | Clearing and grubbing | LS A A | 1 | $32,313 | $83,953 | $15,800 |
| 0130 | Temporary signs | SQFT A A | 500 | $8.16 | $8.00 | $9.00 |
| 0140 | Edge key | LF A A | 41.10 | $77.52 | $76.00 | $80.00 |
| 0150 | Maintain & control traffic | LS A A | 1 | $24,965 | $37,587 | $73,720 |
| 0160 | Diversions (by-pass detours) | LS A A | 1 | $124,611 | $114,730 | $293,375 |
| 0170 | Staking | LS A A | 1 | $5,974.48 | $5,330.00 | $11,150 |
| 0180 | Temp signal | LS A A | 1 | $10,710 | $7,000.00 | $7,810.00 |
| 0182 | Pave striping-temp paint-6 in | LF A A | 725.80 | $2.04 | $2.00 | $2.10 |
| 0185 | Pave striping-temp paint-12 in | LF A A | 20 | $4.08 | $4.00 | $4.20 |
| 0202 | Pave striping-thermo-6 in W | LF A A | 624 | $3.32 | $3.25 | $3.40 |
| 0205 | Pave striping-thermo-6 in Y | LF A A | 624 | $3.32 | $3.25 | $3.40 |
| 0212 | Pave striping-dur TY 1-6 in W | LF A A | 74 | $14.28 | $14.00 | $15.00 |
| 0215 | Pave striping-dur TY 1-6 in Y | LF A A | 37 | $14.28 | $14.00 | $15.00 |
| 0220 | Erosion control | LS A A | 1 | $7,952.00 | $21,850 | $4,975.00 |
| 0230 | Structure granular backfill | CUYD A A | 40 | $99.68 | $78.00 | $162.00 |
| 0240 | Retaining wall-gabion | CUYD A A | 48 | $336.00 | $277.00 | $683.00 |
| 0250 | Armored edge for concrete | LF A A | 48 | $156.80 | $105.00 | $74.00 |
| 0260 | Foundation preparation | LS A A | 1 | $5,185.60 | $2,000.00 | $5,280.00 |
| 0270 | Cyclopean stone rip rap | TON A A | 165 | $107.52 | $57.00 | $95.00 |
| 0280 | Concrete-class A | CUYD A A | 6 | $5,008.64 | $3,150.00 | $5,075.00 |
| 0290 | Concrete-class AA | CUYD A A | 14.50 | $2,266.88 | $3,620.00 | $2,800.00 |
| 0300 | Steel reinforcement-epoxy coated | LB A A | 3,000 | $6.14 | $5.20 | $2.00 |
| 0310 | Remove superstructure | LS A A | 1 | $28,227 | $52,450 | $32,000 |
| 0320 | Precast PC box beam CB17-48 | LF A A | 222 | $586.88 | $590.00 | $604.00 |
| 0330 | Concrete patching repair | SQFT A A | 20 | $198.90 | $325.00 | $205.00 |
| 0340 | Concrete sealing | SQFT A A | 1,910 | $1.41 | $2.40 | $2.00 |
| 0350 | Epoxy injection crack repair | LF A A | 100 | $66.30 | $40.00 | $68.00 |
| 0360 | Rail system side mounted MGS | LF A A | 74 | $205.67 | $300.00 | $237.00 |
| 0370 | Mobilization for concrete surf treatment | LS A A | 1 | $1,120.00 | $6,400.00 | $1,350.00 |
| 0380 | Demobilization | LS A A | 1 | $12,104 | $12,410 | $14,100 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of August 20, 2026. Compiled by Mirage Metrics.