MoDOT contract 250516-C09 bid tabulation

JKU0039 - CLAY COUNTY - ROUTE 169. Let by Missouri DOT on May 16, 2025, Clay, Kansas City. 2 bids received; low bid $2,098,819 by Louis-Company, LLC.

Owner
Missouri DOT
Letting
16 MAY 2025
Pay items
48
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Louis-Company, LLC$2,098,819Low
2Clarkson Construction Company$3,315,666+58%
MoDOT contract 250516-C09: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Louis-Company, LLC2. Clarkson Construction Company
0010Signet dbe reporting (1081000)LS1$1,000.00$1,000.00
0020Removal of improvements (2022010)LS1$13,788$5,000.00
0030Misc.ditch cleanout (2079903)LF1,480$10.00$30.34
0040Misc.permanent aggregate edge treatment (3049910)TON12.80$106.32$163.04
0050Asphaltic concrete mixture PG 70-22 (SP125BSM mix) (4030130)TON97.10$674.16$525.00
0060Tack coat (4071005)GAL118$4.49$3.50
0064Furnishing type 1 rock blanket (6113010)CY47$114.75$163.66
0066Placing type 1 rock blanket (6113030)CY47$36.60$169.91
0070Truck mounted attenuator (TMA) (6123001)LS1$12,841$15,306
0080Construction signs (6161005)SF1,702$8.35$7.00
0090Channelizer (trim-line) (6161025)EACH400$23.11$18.00
0100Type 3 moveable barricade (6161030)EACH54$199.04$155.00
0110Flashing arrow panel (6161040)EACH1$1,431.79$800.00
0120Changeable message sign without communication interface, contractor furnished retained (6161098A)EACH9$3,659.74$3,125.00
0130Mobilization (6181000)LS1$74,000$661,040
0140Temporary removable marking tape 4 in., yellow (6205303B)LF3,380$2.54$1.63
01506 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902A)LF5,317$0.35$0.48
01606 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205903A)LF2,530$0.35$0.48
0170Pavement marking removal (6207001)LF4,858$0.71$0.76
0180Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001)SY1,175$34.67$27.00
0185Separation geotextile (6240104A)SY70$38.52$20.29
0190Seeding - cool season grasses (8051000A)ACRE0.70$9,630.90$8,900.00
0200Type 1A erosion control blanket (8064131)SY3,344$1.93$2.10
0210Removal of miscellaneous acm (non-friable) (2024043)SF28$600.00$350.00
0220Removal of asphalt wearing surface (2161501)SF1,786$2.14$23.00
0230Removal of existing bridge deck (2162500)SF10,915$13.00$20.00
0240Removal of existing expansion joint & adjacent concrete (2164500)LF87$164.60$800.00
0250Bridge approach slab (major) (5031010A)SY182$375.00$324.19
0260Low slump concrete wearing surface (5051000)SY200$129.59$606.52
0270Slab on steel (7034212)SY1,205$376.00$550.00
0280Type D barrier (7034219A)LF627$189.85$152.38
0290Substructure repair (formed) (7040101)SF15$118.11$573.70
0300Half-sole repair (7040104)SF50$118.11$350.00
0310Protective coating - concrete bents and piers (epoxy) (7110200)LS1$12,841$10,000
0320Strengthening existing beams (7121250)LS1$60,000$57,386
0330Surface preparation for applying epoxy-mastic primer (7125102)LS1$130,980$102,000
0340Gray epoxy-mastic primer (7125961)LS1$66,774$52,000
0350Strip seal expansion joint system (7172001)LF87$690.07$785.71
0360Removal of miscellaneous acm (non-friable) (2024043)SF17$500.00$350.00
0370Removal of existing bridge deck (2162500)SF6,626$16.00$25.00
0380Bridge approach slab (major) (5031010A)SY181$350.00$324.20
0390Class B concrete (substructure) (7032003)CY5.70$3,049.57$5,200.00
0400Slab on steel (7034212)SY736$412.00$575.00
0410Type D barrier (7034219A)LF346$169.59$176.51
0420Substructure repair (formed) (7040101)SF45$125.00$527.71
0430Protective coating - concrete bents and piers (epoxy) (7110200)LS1$12,841$10,000
0440Non-destructive testing (7126000)LF51$150.00$75.00
0450Vertical drain at end bents (7151001)EACH2$1,617.99$14,249
MoDOT contract 250516-C09: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of May 16, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy