MoDOT contract 250919-F04 bid tabulation

JSL0246-ROUTE 67-ST CHARLES COUNTY. Let by Missouri DOT on September 19, 2025, St Charles, St. Louis. 2 bids received; low bid $590,368 by KCI Construction Company.

Owner
Missouri DOT
Letting
19 SEP 2025
Pay items
15
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1KCI Construction Company$590,368Low
2CSD Environmental Services, Inc.$2,378,200+303%
MoDOT contract 250919-F04: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. KCI Construction Company2. CSD Environmental Services, Inc.
0010Clearing and grubbing (2013000)ACRE18$11,575$89,330
0020Removal of improvements (2022010)LS1$3,500.00$3,429.00
0030Changeable message sign without communication interface, contractor furnished retained (6161098A)EACH2$2,500.00$6,500.00
0040Misc.lump sum temporary traffic control (6169901)LS1$40,000$96,500
0050Mobilization (6181000)LS1$40,212$120,239
0060Contractor furnished surveying and staking (6274000)LS1$15,000$19,250
0070Mulching (8025006)ACRE18$2,000.00$4,250.00
0080Rock ditch check (8061005)LF300$20.00$45.00
0090Sediment removal (8061016)CY183$15.00$102.00
0100Temporary seeding (8061017)ACRE18$880.00$2,250.00
0110Silt fence (8061019)LF19,853$2.70$8.00
0120Misc.modified shaping slopes class III (2159910)100F3$1,200.00$5,297.00
0130MGS guardrail, 8 FT. posts, 6 FT. - 3 in. spacing (6061061)LF4,038$36.00$44.40
0140MGS end anchor (6061080)EACH2$1,800.00$6,257.00
0150Type A crashworthy end terminal (MASH) (6063014)EACH3$3,850.00$720.00
MoDOT contract 250919-F04: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of September 19, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.