MoDOT contract 251017-C01 bid tabulation
JKR0079 - ROUTE 20 - LAFAYETTE COUNTY. Let by Missouri DOT on October 17, 2025, Saline, Kansas City. 6 bids received; low bid $2,757,083 by Emery Sapp & Sons, Inc..
- Owner
- Missouri DOT
- Letting
- 17 OCT 2025
- Pay items
- 13
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Emery Sapp & Sons, Inc. | $2,757,083 | Low |
| 2 | R.A. Knapp Construction, Inc. | $2,763,830 | 0.0% |
| 3 | Realm Construction Inc. | $2,824,460 | +2.0% |
| 4 | Iowa Civil Contracting, Inc. | $3,010,442 | +9.0% |
| 5 | Interstate Improvement, Inc. | $3,326,602 | +21% |
| 6 | Clarkson Construction Company | $4,598,280 | +67% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Emery Sapp & Sons, Inc. | 2. R.A. Knapp Construction, Inc. | 3. Realm Construction Inc. | 4. Iowa Civil Contracting, Inc. | 5. Interstate Improvement, Inc. | 6. Clarkson Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Furnishing and placing concrete material for full depth pavement repair (6131010) | SY | 13,895.50 | $158.25 | $135.00 | $159.35 | $157.12 | $155.00 | $205.00 |
| 0020 | Subgrade compaction (6 in. depth) (pavement repair) (6131012) | SY | 1,390 | $1.00 | $1.00 | $1.00 | $5.55 | $6.00 | $20.00 |
| 0030 | Type 1 or 5 aggregate for base (4 in. thick) (pavement repair) (6131013) | SY | 1,390 | $1.00 | $1.00 | $1.00 | $17.13 | $10.00 | $29.00 |
| 0040 | Full depth pavement repair saw cut (for perimeter and internal saw cuts) (6131014) | LF | 40,578 | $2.90 | $3.00 | $1.10 | $4.32 | $2.65 | $10.00 |
| 0050 | Dowel bar (drilling, furnishing and installation) for full depth pavement repair (6131015) | EACH | 13,712 | $4.10 | $3.80 | $3.60 | $9.65 | $8.00 | $19.50 |
| 0060 | Dowel bar (furnishing and installation with baskets) for full depth pavement repair (6131017) | EACH | 2,443 | $10.75 | $7.50 | $7.75 | $11.53 | $14.00 | $19.00 |
| 0070 | Tie bar (drilling, furnishing and installation) for full depth pavement repair (type L joints) (6131018) | EACH | 3,070 | $2.80 | $2.30 | $3.75 | $7.77 | $8.00 | $11.00 |
| 0080 | Dowel bar retrofit (6134001) | EACH | 2,766 | $92.00 | $75.00 | $86.85 | $86.57 | $125.00 | $147.00 |
| 0090 | Construction signs (6161005) | SF | 459 | $12.80 | $11.50 | $12.40 | $6.60 | $12.00 | $60.00 |
| 0100 | Channelizer (trim-line) (6161025) | EACH | 532 | $3.60 | $3.15 | $3.45 | $19.80 | $3.35 | $27.00 |
| 0110 | Mobilization (6181000) | LS | 1 | $61,000 | $450,000 | $208,320 | $152,500 | $500,000 | $460,000 |
| 0120 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 127,459 | $0.13 | $0.12 | $0.15 | $0.17 | $0.12 | $0.11 |
| 0130 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 51,958 | $0.13 | $0.12 | $0.15 | $0.17 | $0.12 | $0.11 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of October 17, 2025. Compiled by Mirage Metrics.