MoDOT contract 260320-D04 bid tabulation
JCD0342 - ROUTE 8 - CRAWFORD COUNTY. Let by Missouri DOT on March 20, 2026, Crawford, Central. 3 bids received; low bid $297,146 by BuildTec Construction, LLC.
- Owner
- Missouri DOT
- Letting
- 20 MAR 2026
- Pay items
- 22
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | BuildTec Construction, LLC | $297,146 | Low |
| 2 | Midwest Mechanical and Welding, LLC | $341,067 | +15% |
| 3 | N.B. West Contracting Company | $410,000 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. BuildTec Construction, LLC | 2. Midwest Mechanical and Welding, LLC | 3. N.B. West Contracting Company |
|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $13,606 | $3,000.00 | $11,510 |
| 0020 | Concrete pavement ( 8 in. non-reinf) (5021108) | SY | 24 | $175.00 | $320.00 | $425.14 |
| 0030 | Integral curb (6 in. height and under) type A (6092011) | LF | 19 | $85.00 | $30.00 | $371.24 |
| 0040 | Furnishing type 2 rock ditch liner (6096020) | CY | 4 | $130.00 | $125.00 | $150.44 |
| 0050 | Placing type 2 rock ditch liner (6096042) | CY | 4 | $125.00 | $1,500.00 | $1,098.06 |
| 0060 | Misc.furnishing & placing class V rip rap (6119907) | CY | 503 | $165.00 | $185.00 | $238.79 |
| 0070 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 2 | $3,650.00 | $2,800.00 | $1,000.00 |
| 0080 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $4,680.00 | $36,000 | $2,000.00 |
| 0090 | Mobilization (6181000) | LS | 1 | $49,200 | $38,000 | $40,222 |
| 0100 | Flowable backfill (6214600A) | CY | 14 | $425.00 | $1,800.00 | $786.59 |
| 0110 | Permanent erosion control geotextile (6240103A) | SY | 654 | $8.00 | $13.00 | $4.28 |
| 0120 | Contractor furnished surveying and staking (6274000) | LS | 1 | $8,450.00 | $10,000 | $3,400.00 |
| 0130 | Select granular backfill for structural systems (7201200) | CY | 29 | $200.00 | $160.00 | $220.17 |
| 0140 | Misc.seeding & mulching (8059901) | LS | 1 | $5,950.00 | $3,000.00 | $6,850.00 |
| 0150 | Sediment removal (8061016) | CY | 3 | $1,075.00 | $2,500.00 | $930.96 |
| 0160 | Type C berm (8061050) | LF | 310 | $95.00 | $42.00 | $8.06 |
| 0170 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 1 | $5,460.00 | $20,000 | $4,200.00 |
| 0180 | Misc.temporary formwork (2069901) | LS | 1 | $25,480 | $6,500.00 | $49,958 |
| 0190 | Seal concrete (7033001) | CY | 26.10 | $565.00 | $1,000.00 | $496.11 |
| 0200 | Surface preparation for applying epoxy-mastic primer (7125102) | LS | 1 | $4,586.00 | $4,600.00 | $3,850.00 |
| 0210 | Gray epoxy-mastic primer (7125961) | LS | 1 | $2,800.00 | $4,800.00 | $3,850.00 |
| 0220 | Misc.prefabricated modular block retaining wallw/unreinforced soil (7209904) | SF | 140 | $110.00 | $120.00 | $724.01 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of March 20, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.