MoDOT contract 260417-C04 bid tabulation
JKRM0123 - ROUTE 50 - PETTIS COUNTY. Let by Missouri DOT on April 17, 2026, Pettis, Kansas City. 2 bids received; low bid $66,976 by Capital Paving & Construction, LLC.
- Owner
- Missouri DOT
- Letting
- 17 APR 2026
- Pay items
- 14
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Capital Paving & Construction, LLC | $66,976 | Low |
| 2 | Do-Rite Construction & Excavating, LLC | $89,066 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Capital Paving & Construction, LLC | 2. Do-Rite Construction & Excavating, LLC |
|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $8,410.94 | $15,500 |
| 0020 | Concrete pavement (10 in. non-reinf) (5021110) | SY | 23.20 | $430.07 | $585.00 |
| 0030 | Integral curb (6 in. height and under) type A (6092011) | LF | 32 | $105.33 | $86.50 |
| 0040 | Curved vane grate and frame (4 FT. X 2 FT. or 1200MM X 600MM) (6141121) | EACH | 4 | $1,204.65 | $2,350.00 |
| 0050 | Construction signs (6161005) | SF | 370 | $6.34 | $7.50 |
| 0060 | Channelizer (trim-line) (6161025) | EACH | 70 | $10.56 | $12.25 |
| 0070 | Type 3 moveable barricade (6161030) | EACH | 4 | $132.06 | $155.00 |
| 0080 | Direction indicator barricade (6161033) | EACH | 18 | $42.26 | $48.50 |
| 0090 | Flashing arrow panel (6161040) | EACH | 2 | $369.77 | $425.00 |
| 0100 | Sequential flashing warning light (6161055) | EACH | 18 | $36.98 | $45.00 |
| 0110 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 2 | $1,558.31 | $1,800.00 |
| 0120 | Mobilization (6181000) | LS | 1 | $21,979 | $25,000 |
| 0130 | Precast concrete drop inlet 4 FT X 2 FT (7311042) | FT | 4 | $2,093.79 | $2,500.00 |
| 0140 | Curb inlet check (8061007A) | EACH | 4 | $287.11 | $610.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of April 17, 2026. Compiled by Mirage Metrics.