MoDOT contract 260417-H04 bid tabulation
JSE0173 - VARIOUS ROUTES - VARIOUS COUNTIES. Let by Missouri DOT on April 17, 2026, Various, Southeast. 2 bids received; low bid $2 by Putz Construction, LLC.
- Owner
- Missouri DOT
- Letting
- 17 APR 2026
- Pay items
- 1
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Putz Construction, LLC | $2 | Low |
| 2 | Fronabarger Concreters, Inc. | $2 | +1.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Putz Construction, LLC | 2. Fronabarger Concreters, Inc. |
|---|---|---|---|---|---|
| 0010 | Misc.adjustment factor (6189916) | DLR | 1 | $1.78 | $1.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of April 17, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.