Putz Construction, LLC: MoDOT bid record
Putz Construction, LLC submitted 53 bids on Missouri DOT contracts in the data, from 17 JAN 2020 to 18 JUN 2026, and was the low bidder on 19 of them (36%). When it was not low, its total sat a median +29% above the low bid.
- Owner
- Missouri DOT
- Low bid volume
- $10,242,212
- Latest bid
- 18 JUN 2026
- Data through
- 16 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 3 | 3 | 100% |
| 2021 | 9 | 4 | 44% |
| 2022 | 4 | 1 | 25% |
| 2023 | 10 | 3 | 30% |
| 2024 | 11 | 2 | 18% |
| 2025 | 8 | 3 | 38% |
| 2026 | 8 | 3 | 38% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Southeast | 51 | 19 | 37% |
| Southwest | 1 | 0 | 0% |
| Central | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Permanent erosion control geotextile | 6240103A | SY | 19 | 11 (58%) | $3.00 | $4.00 |
| Additional mobilization for seeding | 6181020 | EACH | 10 | 10 (100%) | $600.00 | $600.00 |
| Seeding - cool season grasses | 8051000A | ACRE | 27 | 9 (33%) | $3,190.00 | $3,600.47 |
| Mulching | 8025006 | ACRE | 22 | 8 (36%) | $2,500.00 | $2,500.00 |
| Sediment removal | 8061016 | CY | 29 | 7 (24%) | $40.00 | $25.69 |
| Construction signs | 6161005 | SF | 34 | 6 (18%) | $8.00 | $7.00 |
| Furnishing type 1 rock ditch liner | 6096010A | CY | 7 | 5 (71%) | $39.00 | $58.00 |
| Misc. normal work adjustment factor | 6189916 | DLR | 6 | 5 (83%) | $1.26 | $1.42 |
| Slab on concrete NU-girder | 7034221 | SY | 5 | 5 (100%) | $495.00 | $478.00 |
| Silt fence | 8061019 | LF | 32 | 4 (13%) | $4.50 | $3.45 |
| Channelizer (trim line) | 6161025 | EACH | 19 | 4 (21%) | $22.00 | $18.00 |
| Type 5 aggregate for base (6 in. thick) | 3040506 | SY | 11 | 4 (36%) | $12.75 | $15.50 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Fronabarger Concreters, Inc. | 21 | 10 of 21 |
| RL Persons Construction, Inc. | 21 | 8 of 21 |
| H.R. Quadri Contractors, LLC | 17 | 13 of 17 |
| Joe's Bridge & Grading, Inc. | 8 | 8 of 8 |
| Robertson Contractors, Inc. | 8 | 7 of 8 |
| Hessling Construction, Inc. | 7 | 3 of 7 |
| Lappe Cement Finishing, Inc. | 6 | 4 of 6 |
| Penzel Construction Company, Inc. | 6 | 6 of 6 |
| Mera Excavating, LLC | 5 | 4 of 5 |
| Courtney Construction, LLC dba Courtney Excavating & Construction | 4 | 3 of 4 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 18 JUN 2026 | 260618-H03 | Southeast | J9S3738 - ROUTE Z - CAPE GIRARDEAU ROUTE | 6 of 6 | $3,893,755 | +15% |
| 17 APR 2026 | 260417-H04 | Southeast | JSE0173 - VARIOUS ROUTES - VARIOUS COUNTIES | 1 of 2 | $2 | Low, 1.0% under the second |
| 17 APR 2026 | 260417-H05 | Southeast | JSE0174 - VARIOUS ROUTES - VARIOUS COUNTIES | 1 of 2 | $1 | Low, 5.0% under the second |
| 17 APR 2026 | 260417-H06 | Southeast | JSE0175 - ROUTES I-55, I-57, I-155 - VARIOUS COUNTIES | 1 of 2 | $1 | Low, 23% under the second |
| 17 APR 2026 | 260417-H09 | Southeast | JSE0179-VARIOUS ROUTES-VARIOUS COUNTIES | 2 of 2 | $1 | +5.0% |
| 17 APR 2026 | 260417-H11 | Southeast | Rank vendor id vendor name total bid percent of low bid | 3 of 4 | $81,680 | +69% |
| 20 MAR 2026 | 260320-H04 | Southeast | JSE0332 - ROUTE I-57 - MISSISSIPPI COUNTY | 4 of 6 | $2,397,363 | +24% |
| 16 JAN 2026 | 260116-H02 | Southeast | J9P3772, J9S3810 - ROUTE 25, 61 - CAPE GIRARDEAU COUNTY | 4 of 5 | $1,497,948 | +10% |
| 12 DEC 2025 | 251212-H06 | Southeast | J9M0283 - ROUTE 77 - CAPE GIRARDEAU, SCOTT COUNTIES | 1 of 2 | $1,298,162 | Low, 11% under the second |
| 14 NOV 2025 | 251114-H09 | Southeast | JSEM0114 - ROUTE 95 - WRIGHT COUNTY | 6 of 6 | $658,051 | +89% |
| 17 OCT 2025 | 251017-H02 | Southeast | J9S3798 - VARIOUS ROUTES - VARIOUS COUNTIES | 1 of 4 | $297,533 | Low, 10% under the second |
| 17 OCT 2025 | 251017-H04 | Southeast | JSE0141 - VARIOUS ROUTES - VARIOUS COUNTIES | 1 of 5 | $962,808 | Low, 35% under the second |
| 19 SEP 2025 | 250919-D01 | Central | JCD0011 - ROUTE I-70 - COOPER, BOONE, CALLAWY COUNTY | 2 of 2 | $2 | +40% |
| 15 AUG 2025 | 250815-H03 | Southeast | JSE0150 - ROUTE Y - SCOTT COUNTY | 6 of 6 | $3,368,020 | +44% |
| 18 APR 2025 | 250418-H02 | Southeast | J9P3835 - ROUTE 60 - CARTER, HOWELL, SHANNON COUNTIES | 6 of 6 | $1,459,525 | +96% |
| 14 MAR 2025 | 250314-H02 | Southeast | J9S3680, JSE0116, JSE0127 - ROUTE 102, O, E - MISSISSIPPI, NEW MADRID COUNTIESSTODDARD, | 6 of 6 | $3,201,575 | +40% |
| 18 OCT 2024 | 241018-H01 | Southeast | J9P3575 - ROUTE 61 - CAPE GIRARDEAU COUNTY | 1 of 3 | $1,585,744 | Low, 23% under the second |
| 18 OCT 2024 | 241018-H07 | Southeast | JSEM0061 - ROUTE I-55 - CAPE GIRARDEAU COUNTY | 3 of 5 | $2,539,033 | +24% |
| 16 AUG 2024 | 240816-G05 | Southwest | JSR0010 - ROUTE 265 - STONE COUNTY | 4 of 4 | $882,540 | +109% |
| 21 JUN 2024 | 240621-H02 | Southeast | JSEM0059 - ROUTE 67 - BUTLER COUNTY | 7 of 8 | $474,428 | +148% |
| 17 MAY 2024 | 240517-H09 | Southeast | JSEM0040 - ROUTE 5 - DOUGLAS COUNTY | 2 of 5 | $188,351 | +27% |
| 17 MAY 2024 | 240517-H10 | Southeast | JSEM0048-ROUTE HH-NEW MADRID COUNTY | 3 of 7 | $74,139 | +26% |
| 19 APR 2024 | 240419-H04 | Southeast | J9P3739 - ROUTE 61 - STE. GENEVIEVE | 3 of 3 | $1,481,400 | +31% |
| 19 APR 2024 | 240419-H08 | Southeast | J9S3589 - ROUTE Y - CAPE GIRARDEAU COUNTY | 3 of 5 | $1,016,384 | +4.0% |
| 19 APR 2024 | 240419-H10 | Southeast | J9S3833 - Various Routes - Various Counties | 1 of 2 | $178,000 | Low, 10% under the second |
How this record was read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Every bid counted here matched its published total to within one dollar; MoDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.