MoDOT contract 250314-H02 bid tabulation
J9S3680, JSE0116, JSE0127 - ROUTE 102, O, E - MISSISSIPPI, NEW MADRID COUNTIESSTODDARD,. Let by Missouri DOT on March 14, 2025, Mississippi, Southeast. 6 bids received; low bid $2,288,286 by Penzel Construction Company, Inc..
- Owner
- Missouri DOT
- Letting
- 14 MAR 2025
- Pay items
- 112
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Penzel Construction Company, Inc. | $2,288,286 | Low |
| 2 | Plattin Creek Excavating, LLC dba PCX Construction, LLC | $2,499,382 | +9.0% |
| 3 | Robertson Contractors, Inc. | $2,615,175 | +14% |
| 4 | Joe's Bridge & Grading, Inc. | $2,648,476 | +16% |
| 5 | Louis-Company, LLC | $2,999,914 | +31% |
| 6 | Putz Construction, LLC | $3,201,575 | +40% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Penzel Construction Company, Inc. | 2. Plattin Creek Excavating, LLC dba PCX Construction, LLC | 3. Robertson Contractors, Inc. | 4. Joe's Bridge & Grading, Inc. | 5. Louis-Company, LLC | 6. Putz Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Signet dbe reporting (1081000) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0020 | Clearing and grubbing (2013000) | ACRE | 1 | $4,400.00 | $10,000 | $3,500.00 | $4,000.00 | $10,000 | $20,000 |
| 0030 | Removal of improvements (2022010) | LS | 1 | $6,000.00 | $10,000 | $5,500.00 | $12,000 | $20,000 | $24,000 |
| 0040 | Class A excavation (2031000) | CY | 139 | $31.00 | $76.00 | $18.00 | $27.00 | $30.00 | $24.00 |
| 0050 | Embankment in place (2035500) | CY | 1,376 | $57.00 | $25.00 | $36.00 | $48.00 | $50.00 | $50.00 |
| 0060 | Compacting embankment (2036000) | CY | 139 | $10.00 | $9.00 | $12.00 | $5.00 | $101.89 | $30.00 |
| 0070 | Type 1 aggregate for base (6 in. thick) (3040163) | SY | 722.30 | $19.80 | $16.00 | $22.00 | $18.00 | $21.03 | $28.00 |
| 0080 | Misc.optional pavement (4019905) | SY | 666.70 | $70.00 | $88.00 | $87.30 | $88.00 | $112.82 | $125.00 |
| 0090 | Furnishing type 1 rock blanket (6113010) | CY | 12 | $68.00 | $52.00 | $70.00 | $68.00 | $97.73 | $75.00 |
| 0100 | Furnishing type 2 rock blanket (6113020) | CY | 115 | $60.00 | $52.00 | $70.00 | $50.00 | $82.27 | $85.00 |
| 0110 | Placing type 1 rock blanket (6113030) | CY | 12 | $50.00 | $181.00 | $45.00 | $32.00 | $89.68 | $40.00 |
| 0120 | Placing type 2 rock blanket (6113040) | CY | 115 | $30.00 | $76.00 | $35.00 | $32.00 | $22.46 | $40.00 |
| 0130 | Changeable message sign without communication interface, contractor furnished, contractor retained (6161098A) | EACH | 3 | $3,000.00 | $3,000.00 | $2,750.00 | $3,000.00 | $3,663.46 | $3,300.00 |
| 0140 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $9,320.00 | $9,320.00 | $7,870.00 | $8,000.00 | $12,212 | $10,252 |
| 0150 | Mobilization (6181000) | LS | 1 | $60,000 | $206,000 | $65,000 | $125,000 | $75,000 | $75,000 |
| 0160 | 4 in. white standard waterborne pavement marking paint, type P beads (6206000C) | LF | 500 | $1.00 | $1.00 | $0.50 | $0.50 | $3.21 | $1.10 |
| 0170 | 4 in. yellow standard waterborne pavement marking paint, type P beads (6206001C) | LF | 500 | $1.00 | $1.00 | $0.50 | $0.50 | $3.21 | $1.10 |
| 0180 | Permanent erosion control geotextile (6240103A) | SY | 191 | $3.70 | $6.00 | $7.00 | $4.00 | $6.10 | $4.00 |
| 0190 | Bituminous shoulder rumble strip (6261000A) | STA | 5 | $400.00 | $1,730.00 | $1,000.00 | $675.00 | $852.51 | $966.66 |
| 0200 | Bituminous centerline rumble strip (6261001) | STA | 2.50 | $300.00 | $2,930.00 | $1,000.00 | $800.00 | $1,023.02 | $966.66 |
| 0210 | Contractor furnished surveying and staking (6274000) | LS | 1 | $7,500.00 | $3,720.00 | $12,500 | $12,000 | $11,569 | $15,000 |
| 0220 | Mulching (8025006) | ACRE | 1 | $2,400.00 | $4,750.00 | $2,000.00 | $1,800.00 | $3,085.02 | $3,000.00 |
| 0230 | Seeding - cool season grasses (8051000A) | ACRE | 1 | $2,100.00 | $4,000.00 | $1,650.00 | $3,500.00 | $2,699.39 | $3,850.00 |
| 0240 | Sediment trap rock (8061004) | CY | 1 | $100.00 | $392.00 | $25.00 | $100.00 | $578.45 | $110.00 |
| 0250 | Alternate ditch check (8061006) | LF | 60 | $15.00 | $20.00 | $15.00 | $18.00 | $19.28 | $50.00 |
| 0260 | Sediment removal (8061016) | CY | 16 | $25.00 | $100.00 | $1.00 | $10.00 | $107.62 | $50.00 |
| 0270 | Silt fence (8061019) | LF | 546 | $5.00 | $3.70 | $3.50 | $4.00 | $6.43 | $4.00 |
| 0280 | Class 4 excavation (2063300) | CY | 265 | $68.50 | $20.00 | $95.00 | $35.00 | $75.00 | $45.00 |
| 0290 | Misc.dewatering (2069901) | LS | 1 | $88,700 | $11,900 | $95,000 | $60,000 | $150,000 | $95,000 |
| 0300 | Removal of bridges (2160500) | LS | 1 | $26,000 | $44,200 | $25,000 | $60,000 | $40,000 | $40,000 |
| 0310 | Class B-1 concrete (culverts-bridge) (7034040) | CY | 404.30 | $1,050.00 | $968.00 | $1,240.00 | $1,250.00 | $1,200.00 | $1,400.00 |
| 0320 | Reinforcing steel (culverts-bridge) (7061020) | LB | 55,140 | $1.85 | $1.10 | $2.20 | $1.95 | $0.81 | $3.25 |
| 0330 | Clearing and grubbing (2013000) | ACRE | 1 | $3,000.00 | $9,210.00 | $3,250.00 | $4,000.00 | $10,000 | $10,000 |
| 0340 | Removal of improvements (2022010) | LS | 1 | $5,000.00 | $9,910.00 | $5,000.00 | $10,000 | $20,000 | $24,000 |
| 0350 | Class A excavation (2031000) | CY | 345 | $27.00 | $35.00 | $26.00 | $21.00 | $10.84 | $24.00 |
| 0360 | Compacting embankment (2036000) | CY | 223 | $10.00 | $5.00 | $12.00 | $5.00 | $22.69 | $50.00 |
| 0370 | Class 3 excavation (2063000) | CY | 110 | $20.00 | $67.00 | $45.00 | $32.00 | $13.67 | $34.00 |
| 0380 | Type 1 aggregate for base (6 in. thick) (3040163) | SY | 580 | $16.63 | $18.70 | $22.00 | $18.00 | $20.56 | $24.00 |
| 0390 | Gravel (A) (3101003) | SY | 100 | $23.00 | $11.30 | $20.00 | $18.00 | $22.75 | $80.00 |
| 0400 | Misc.optional pavement (4019905) | SY | 579.90 | $70.00 | $85.00 | $85.45 | $84.00 | $107.60 | $125.00 |
| 0410 | Pipe collar, type C (6044013) | EACH | 2 | $1,600.00 | $594.00 | $2,500.00 | $3,000.00 | $1,285.80 | $125.00 |
| 0415 | Type C crashworthy end terminal (MASH) (6063020) | EACH | 4 | $28,310 | $24,500 | $32,500 | $28,000 | $40,383 | $26,950 |
| 0420 | Furnishing type 2 rock blanket (6113020) | CY | 147 | $62.00 | $52.00 | $50.00 | $48.00 | $300.11 | $65.00 |
| 0430 | Placing type 2 rock blanket (6113040) | CY | 147 | $30.00 | $59.00 | $38.00 | $32.00 | $46.85 | $35.00 |
| 0440 | Misc.auto 18 in. auto flap gate (6149902) | EACH | 4 | $1,280.00 | $2,260.00 | $1,550.00 | $750.00 | $1,416.26 | $1,500.00 |
| 0450 | Changeable message sign without communication interface, contractor furnished, contractor retained (6161098A) | EACH | 4 | $2,750.00 | $3,000.00 | $2,750.00 | $3,000.00 | $3,599.19 | $3,300.00 |
| 0460 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $5,833.00 | $8,350.00 | $5,833.00 | $6,000.00 | $10,926 | $9,185.00 |
| 0470 | Mobilization (6181000) | LS | 1 | $59,500 | $31,900 | $50,000 | $75,000 | $75,000 | $80,000 |
| 0480 | 4 in. white standard waterborne pavement marking paint, type P beads (6206000C) | LF | 2,400 | $0.50 | $0.50 | $0.50 | $0.50 | $1.61 | $1.10 |
| 0490 | 4 in. yellow standard waterborne pavement marking paint, type P beads (6206001C) | LF | 2,400 | $0.50 | $0.50 | $0.50 | $0.50 | $1.61 | $1.10 |
| 0500 | Permanent erosion control geotextile (6240103A) | SY | 220 | $4.00 | $5.05 | $5.85 | $4.00 | $7.39 | $4.00 |
| 0510 | Bituminous centerline rumble strip (6261001) | STA | 9 | $300.00 | $1,330.00 | $1,000.00 | $750.00 | $1,023.02 | $966.66 |
| 0520 | Contractor furnished surveying and staking (6274000) | LS | 1 | $9,000.00 | $4,500.00 | $10,000 | $7,500.00 | $12,854 | $15,000 |
| 0530 | 18 in. pipe group C (7250418) | LF | 304 | $65.00 | $72.00 | $85.00 | $65.00 | $36.21 | $125.00 |
| 0540 | 18 in. or allowed substitute group C flared end section (7320818A) | EACH | 3 | $470.00 | $716.00 | $600.00 | $750.00 | $783.95 | $400.00 |
| 0550 | Mulching (8025006) | ACRE | 1 | $2,400.00 | $4,750.00 | $2,000.00 | $1,800.00 | $3,085.02 | $3,000.00 |
| 0560 | Seeding - cool season grasses (8051000A) | ACRE | 1 | $2,100.00 | $4,000.00 | $1,650.00 | $3,500.00 | $2,699.39 | $3,850.00 |
| 0570 | Sediment trap rock (8061004) | CY | 6 | $85.00 | $169.00 | $20.00 | $100.00 | $109.26 | $100.00 |
| 0580 | Sediment removal (8061016) | CY | 69 | $25.00 | $100.00 | $1.00 | $10.00 | $12.48 | $50.00 |
| 0590 | Silt fence (8061019) | LF | 709 | $4.50 | $3.70 | $3.50 | $4.00 | $5.78 | $4.00 |
| 0600 | Class 1 excavation (2061000) | CY | 60 | $30.00 | $89.00 | $35.00 | $30.00 | $21.52 | $42.00 |
| 0610 | Removal of bridges (2160500) | LS | 1 | $18,000 | $33,300 | $35,000 | $45,000 | $70,000 | $50,000 |
| 0620 | Bridge approach slab (minor road) (5031011A) | SY | 109 | $115.00 | $131.00 | $255.00 | $195.00 | $262.50 | $265.00 |
| 0630 | Galvanized structural steel piles (12 in) (7021212) | LF | 360 | $84.50 | $151.00 | $135.00 | $110.00 | $111.90 | $310.00 |
| 0640 | Pile wave analysis (7025002) | EACH | 2 | $2,500.00 | $750.00 | $1,250.00 | $5,000.00 | $1,156.89 | $1,200.00 |
| 0650 | Pile point reinforcement (7027000) | EACH | 8 | $145.00 | $125.00 | $220.00 | $150.00 | $160.68 | $375.00 |
| 0660 | Class B concrete (substructure) (7032003) | CY | 22.60 | $1,100.00 | $2,040.00 | $1,680.00 | $1,500.00 | $1,211.99 | $1,500.00 |
| 0670 | Type H barrier (7034216) | LF | 155 | $140.00 | $146.00 | $145.00 | $135.00 | $134.72 | $92.40 |
| 0680 | Slab on concrete NU-girder (7034221) | SY | 185 | $610.00 | $769.00 | $655.00 | $650.00 | $731.17 | $550.00 |
| 0690 | NU 35, prestressed concrete NU-girder (7056021) | LF | 182 | $400.00 | $400.00 | $430.00 | $445.00 | $503.54 | $475.00 |
| 0700 | Slab drain (7123610) | EACH | 12 | $435.00 | $404.00 | $450.00 | $495.00 | $457.14 | $750.00 |
| 0710 | Vertical drain at end bents (7151001) | EACH | 2 | $3,000.00 | $7,910.00 | $2,000.00 | $1,800.00 | $2,371.20 | $1,950.00 |
| 0720 | Plain neoprene bearing pad (7161000) | EACH | 6 | $265.00 | $397.00 | $365.00 | $375.00 | $127.26 | $450.00 |
| 0730 | Clearing and grubbing (2013000) | ACRE | 1 | $2,500.00 | $9,210.00 | $3,500.00 | $4,000.00 | $10,000 | $10,000 |
| 0740 | Removal of improvements (2022010) | LS | 1 | $3,500.00 | $14,100 | $6,000.00 | $8,000.00 | $20,000 | $50,000 |
| 0750 | Class A excavation (2031000) | CY | 346 | $25.00 | $36.00 | $22.00 | $30.00 | $50.00 | $24.00 |
| 0760 | Embankment in place (2035500) | CY | 7 | $45.00 | $101.00 | $85.00 | $30.00 | $1,104.57 | $50.00 |
| 0770 | Compacting embankment (2036000) | CY | 346 | $15.00 | $5.00 | $8.00 | $5.00 | $8.83 | $50.00 |
| 0780 | Class 3 excavation (2063000) | CY | 66 | $25.00 | $66.00 | $40.00 | $35.00 | $52.18 | $34.00 |
| 0790 | Type 1 aggregate for base (6 in. thick) (3040163) | SY | 863 | $19.63 | $19.00 | $19.50 | $18.00 | $27.42 | $24.00 |
| 0800 | Gravel (A) (3101003) | SY | 71 | $22.00 | $14.00 | $18.00 | $18.00 | $29.33 | $80.00 |
| 0810 | Misc.optional pavement (4019905) | SY | 783.70 | $70.00 | $84.90 | $79.66 | $85.00 | $109.07 | $125.00 |
| 0820 | Furnishing type 2 rock blanket (6113020) | CY | 121 | $56.00 | $52.00 | $65.00 | $48.00 | $106.23 | $65.00 |
| 0830 | Placing type 2 rock blanket (6113040) | CY | 121 | $25.00 | $72.00 | $35.00 | $32.00 | $21.35 | $35.00 |
| 0840 | Changeable message sign without communication interface, contractor furnished, contractor retained (6161098A) | EACH | 4 | $2,750.00 | $3,000.00 | $2,750.00 | $3,000.00 | $4,113.37 | $3,300.00 |
| 0850 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $6,302.00 | $8,270.00 | $6,302.00 | $6,500.00 | $10,926 | $9,101.40 |
| 0860 | Mobilization (6181000) | LS | 1 | $83,000 | $29,200 | $55,000 | $80,000 | $75,000 | $67,000 |
| 0870 | 4 in. white standard waterborne pavement marking paint, type P beads (6206000C) | LF | 840 | $0.50 | $1.00 | $0.50 | $0.50 | $2.57 | $1.10 |
| 0880 | 4 in. yellow standard waterborne pavement marking paint, type P beads (6206001C) | LF | 840 | $0.50 | $1.00 | $0.50 | $0.50 | $2.57 | $1.10 |
| 0890 | Permanent erosion control geotextile (6240103A) | SY | 181 | $3.50 | $6.15 | $6.50 | $4.00 | $9.51 | $4.00 |
| 0900 | Contractor furnished surveying and staking (6274000) | LS | 1 | $8,500.00 | $4,500.00 | $12,500 | $7,500.00 | $12,854 | $15,000 |
| 0910 | 60 in. pipe group C (7250460) | LF | 56 | $211.00 | $427.00 | $435.00 | $210.00 | $419.94 | $250.00 |
| 0920 | 60 in. or allowed substitute group C flared end section (7320860A) | EACH | 2 | $3,800.00 | $7,040.00 | $3,500.00 | $3,500.00 | $4,865.20 | $5,800.00 |
| 0930 | Mulching (8025006) | ACRE | 1 | $2,400.00 | $4,750.00 | $2,000.00 | $1,800.00 | $3,085.02 | $3,000.00 |
| 0940 | Seeding - cool season grasses (8051000A) | ACRE | 1 | $2,100.00 | $4,000.00 | $1,650.00 | $3,500.00 | $2,699.39 | $3,850.00 |
| 0950 | Sediment trap rock (8061004) | CY | 5 | $100.00 | $125.00 | $20.00 | $100.00 | $128.54 | $110.00 |
| 0960 | Sediment removal (8061016) | CY | 63 | $25.00 | $100.00 | $1.00 | $10.00 | $13.67 | $50.00 |
| 0970 | Silt fence (8061019) | LF | 850 | $4.50 | $3.70 | $3.50 | $4.00 | $5.78 | $4.00 |
| 0980 | U-channel post, 3 LB (9031250A) | LF | 119 | $24.00 | $24.00 | $18.00 | $18.00 | $51.42 | $26.40 |
| 0990 | SHF-flat sheet fluorescent (9035069A) | SF | 49 | $28.00 | $28.00 | $35.00 | $35.00 | $38.56 | $30.80 |
| 1000 | Class 1 excavation (2061000) | CY | 70 | $28.00 | $76.30 | $30.00 | $30.00 | $24.60 | $42.00 |
| 1010 | Removal of bridges (2160500) | LS | 1 | $26,500 | $33,300 | $35,000 | $45,000 | $64,000 | $50,000 |
| 1020 | Bridge approach slab (minor road) (5031011A) | SY | 109 | $120.00 | $155.00 | $255.00 | $230.00 | $295.19 | $265.00 |
| 1030 | Galvanized cast-in-place concrete piles (16 in) (7021316) | LF | 720 | $153.00 | $191.00 | $220.00 | $175.00 | $197.27 | $310.00 |
| 1040 | Dynamic pile testing (7025001) | EACH | 2 | $3,900.00 | $4,000.00 | $4,500.00 | $5,000.00 | $6,170.05 | $6,500.00 |
| 1050 | Class B concrete (substructure) (7032003) | CY | 23.80 | $1,150.00 | $2,060.00 | $1,680.00 | $1,500.00 | $1,154.69 | $1,500.00 |
| 1060 | Type H barrier (7034216) | LF | 207 | $128.15 | $129.00 | $145.00 | $152.00 | $147.76 | $83.60 |
| 1070 | Slab on concrete NU-girder (7034221) | SY | 250 | $580.00 | $624.00 | $655.00 | $650.00 | $696.95 | $550.00 |
| 1080 | NU 43, prestressed concrete NU-girder (7056022) | LF | 248 | $380.00 | $387.00 | $430.00 | $428.00 | $474.28 | $475.00 |
| 1090 | Slab drain (7123610) | EACH | 16 | $440.00 | $436.00 | $450.00 | $575.00 | $492.17 | $750.00 |
| 1100 | Vertical drain at end bents (7151001) | EACH | 2 | $2,750.00 | $7,910.00 | $2,000.00 | $1,800.00 | $2,888.06 | $1,950.00 |
| 1110 | Plain neoprene bearing pad (7161000) | EACH | 6 | $260.00 | $393.00 | $365.00 | $375.00 | $127.26 | $450.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of March 14, 2025. Compiled by Mirage Metrics.