MoDOT letting results, March 14, 2025
41 contracts let by Missouri DOT on March 14, 2025, $75,223,175 in low bids, a median of 2 bidders per contract.
- Owner
- Missouri DOT
- Contracts
- 41
- Low bids, total
- $75,223,175
- Data through
- 16 OCT 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| 250314-C01 | J3P3158, JKR0249 - ROUTE 24 - LAFAYETTE COUNTY | Kansas City | 3 | Emery Sapp & Sons, Inc. | $11,325,503 | $11,502,892 | +2.0% | MoDOT |
| 250314-F03 | J6S3626 - ROUTE D - ST. LOUIS COUNTY | St. Louis | 5 | Kozeny-Wagner, Inc. | $11,260,000 | $11,845,782 | +5.0% | MoDOT |
| 250314-A03 | JNW0148 - VARIOUS ROUTES - VARIOUS COUNTY | Northwest | 1 | Vance Brothers, Inc. | $4,844,774 | MoDOT | ||
| 250314-G03 | J8S3156 - ROUTE CRD 127 - GREENE COUNTY | Southwest | 3 | Hartman and Company, Inc. | $4,610,000 | $4,889,439 | +6.0% | MoDOT |
| 250314-D03 | J5S3480B, J5S3541, J5S3547, J5S3548, J5S3549, J5S3563 - ROUTE I-44 - PULASKI, PHELPS COUNTIES | Central | 2 | Concrete Strategies, LLC | $3,948,367 | $4,115,000 | +4.0% | MoDOT |
| 250314-H01 | J9P3448 - ROUTE 8 - ST FRANCIS COUNTY | Southeast | 2 | Plattin Creek Excavating, LLC dba PCX Construction, LLC | $3,440,171 | $3,539,869 | +3.0% | MoDOT |
| 250314-H14 | JST0126, JST0129 - ROUTE E,OO, AA, A,O,U - MISSISSIPPI, NEW MADRID COUNTY | Southeast | 2 | Apex Paving Co. | $3,021,561 | $3,080,000 | +2.0% | MoDOT |
| 250314-H02 | J9S3680, JSE0116, JSE0127 - ROUTE 102, O, E - MISSISSIPPI, NEW MADRID COUNTIESSTODDARD, | Southeast | 6 | Penzel Construction Company, Inc. | $2,288,286 | $2,499,382 | +9.0% | MoDOT |
| 250314-A02 | JNW0071 - ROUTE NN - NODAWAY COUNTY | Northwest | 1 | Louis-Company, LLC | $2,198,878 | MoDOT | ||
| 250314-F02 | J6S3575 - ROUTE MM - JEFFERSON COUNTY | St. Louis | 4 | N.B. West Contracting Company | $1,998,000 | $2,219,244 | +11% | MoDOT |
| 250314-F01 | J6I3573B - ROUTE AC - ST LOUIS COUNTY | St. Louis | 2 | Kozeny-Wagner, Inc. | $1,922,080 | $1,951,234 | +2.0% | MoDOT |
| 250314-C03 | JKR0134 - HIGHWAY 50 - JOHNSON COUNTY | Kansas City | 4 | Leavenworth Excavating & Equipment Company, Inc. | $1,904,947 | $2,028,359 | +6.0% | MoDOT |
| 250314-C05 | JKR0412 - VARIOUS ROUTES - JOHNSON, LAFAYETTE, PETTIS, SALINE COUNTIES | Kansas City | 1 | Concrete Strategies, LLC | $1,750,000 | MoDOT | ||
| 250314-D01 | J5P3537 - ROUTE 63 - PHELPS COUNTY | Central | 3 | Kozeny-Wagner, Inc. | $1,560,000 | $1,622,194 | +4.0% | MoDOT |
| 250314-C07 | JKU0040 - ROUTE 24 - JACKSON COUNTY | Kansas City | 1 | Concrete Strategies, LLC | $1,492,497 | MoDOT | ||
| 250314-H09 | JSE0123-ROUTE H-SCOTT COUNTY | Southeast | 2 | Pace Construction Company, LLC | $1,475,000 | $1,491,632 | +1.0% | MoDOT |
| 250314-B02 | JST0128-ROUTE Y-AUDRAIN, MONROE COUNTY | Northeast | 3 | Emery Sapp & Sons, Inc. | $1,342,724 | $1,469,960 | +9.0% | MoDOT |
| 250314-H08 | JSE0122-ROUTE BB-STODDARD COUNTY | Southeast | 2 | Apex Paving Co. | $1,128,055 | $1,260,000 | +12% | MoDOT |
| 250314-H12 | JSE0137-VARIOUS ROUTES-VARIOUS COUNTIES | Southeast | 2 | James H. Drew Corporation | $990,000 | $1,020,000 | +3.0% | MoDOT |
| 250314-G04 | JSR0098 - ROUTE I-49, 76, 39 - MCDONALD, TANEY, LAWRENCE COUNTIES | Southwest | 4 | WJ Surface Treatments, LLC | $986,920 | $1,191,191 | +21% | MoDOT |
| 250314-H03 | J9S3699-ROUTE O-STE. GENEVIEVE | Southeast | 3 | N.B. West Contracting Company | $984,000 | $1,110,000 | +13% | MoDOT |
| 250314-D07 | JCD0076 - VARIOUS ROUTES - BOONE, CALLAWAY, OSAGE, PHELS COUNTIES | Central | 4 | Aplex, Inc. | $967,082 | $1,096,918 | +13% | MoDOT |
| 250314-H5A | JSE0090-ROUTE M-BUTLER COUNTY | Southeast | 2 | Apex Paving Co. | $938,874 | $1,003,000 | +7.0% | MoDOT |
| 250314-C06 | JKU0014 - VARIOUS ROUTES - VARIOUS COUNTIES | Kansas City | 3 | Collins & Hermann, Inc. | $912,000 | $947,755 | +4.0% | MoDOT |
| 250314-A05 | JST0132 - ROUTE DD - SULLIVAN COUNTY | Northwest | 2 | Above And Below Contracting, LLC | $791,022 | $817,226 | +3.0% | MoDOT |
| 250314-H04 | JSE0058-ROUTE 412-DUNKLIN COUNTY | Southeast | 1 | Pace Construction Company, LLC | $789,000 | MoDOT | ||
| 250314-C13 | JST0130 - ROUTE YY - JOHNSON COUNTY | Kansas City | 2 | Emery Sapp & Sons, Inc. | $675,995 | $710,676 | +5.0% | MoDOT |
| 250314-F04 | JST0134 - ROUTE V - FRANKLIN COUNTY | St. Louis | 4 | Byrne & Jones Enterprises, Inc. dba Byrne & Jones Construction | $607,364 | $609,000 | 0.0% | MoDOT |
| 250314-H11 | JSE0135-VARIOUS ROUTES-VARIOUS COUNTIES | Southeast | 1 of 2 | $599,000 | $775,000 | +29% | MoDOT | |
| 250314-D04 | J5S3540 - ROUTE 47 - WASHINGTON COUNTY | Central | 3 | Udt, LLC | $588,738 | $716,371 | +22% | MoDOT |
| 250314-H10 | JSE0134-I-55, I-57, I-155-VARIOUS COUNTIES | Southeast | 1 of 2 | $552,500 | $650,000 | +18% | MoDOT | |
| 250314-D06 | JCD0008 - ROUTE I-70 - COOPER, BOONE, CALLAWAY COUNTIES | Central | 3 | Geromini Concrete Paving, LLC dba GC Paving | $503,496 | $709,429 | +41% | MoDOT |
| 250314-G05 | JST0135 - ROUTE FF - POLK COUNTY | Southwest | 3 | APAC-Central, Inc. | $451,711 | $512,522 | +13% | MoDOT |
| 250314-B01 | JNE0145 - ROUTES V,M,K,W - SCHUYLER, ADAIR COUNTIES, | Northeast | 1 | Stanton Contracting, L.L.C. | $448,567 | MoDOT | ||
| 250314-H07 | JSE0112-ROUTES I-55, I-155, I-57-VARIOUS COUNTIES | Southeast | 1 | Apex Paving Co. | $417,500 | MoDOT | ||
| 250314-H13 | JSE0198 - ROUTE 67 - WAYNE COUNTY | Southeast | 3 | Concrete Strategies, LLC | $376,051 | $408,170 | +9.0% | MoDOT |
| 250314-C14 | JKU0370-VARIOUS ROUTES-JACKSON, CLAY COUNTIES | Kansas City | 2 | WJ Surface Treatments, LLC | $306,132 | $439,439 | +44% | MoDOT |
| 250314-A06 | JST0133 - ROUTE YY - HARRISON COUNTY | Northwest | 2 | Herzog Contracting Corp. | $285,586 | $476,110 | +67% | MoDOT |
| 250314-H5B | JSE0092-ROUTE 67 OR-BUTLER COUNTY | Southeast | 2 | Apex Paving Co. | $259,014 | $285,000 | +10% | MoDOT |
| 250314-C08 | JKU0113 - VARIOUS - JACKSON, PLATTE, RAY COUNTIES | Kansas City | 2 | Collins & Hermann, Inc. | $198,000 | $198,164 | 0.0% | MoDOT |
| 250314-H15 | JSEM0084-ROUTE 67-MADISON COUNTY | Southeast | 2 | Clarkson Construction Company | $83,781 | $93,856 | +12% | MoDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than MoDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.