Kozeny-Wagner, Inc.: MoDOT bid record
Kozeny-Wagner, Inc. submitted 57 bids on Missouri DOT contracts in the data, from 17 JAN 2020 to 18 SEP 2026, and was the low bidder on 14 of them (25%). When it was not low, its total sat a median +22% above the low bid.
- Owner
- Missouri DOT
- Low bid volume
- $77,459,378
- Latest bid
- 18 SEP 2026
- Data through
- 16 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 9 | 2 | 22% |
| 2021 | 11 | 2 | 18% |
| 2022 | 6 | 1 | 17% |
| 2023 | 6 | 4 | 67% |
| 2024 | 2 | 0 | 0% |
| 2025 | 19 | 5 | 26% |
| 2026 | 4 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| St. Louis | 38 | 12 | 32% |
| Central | 17 | 2 | 12% |
| Northeast | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Type A crashworthy end terminal (MASH) | 6063014 | EACH | 33 | 30 (91%) | $3,800.00 | $3,300.00 |
| MGS bridge approach transition section (regular/no curb) | 6061069 | EACH | 33 | 28 (85%) | $4,000.00 | $3,800.00 |
| Silt fence | 8061019 | LF | 46 | 27 (59%) | $3.00 | $3.45 |
| MGS guardrail | 6061060 | LF | 31 | 27 (87%) | $28.00 | $30.00 |
| Replacement sand barrel | 6122020 | EACH | 25 | 20 (80%) | $460.00 | $350.00 |
| Rock ditch check | 8061005 | LF | 30 | 18 (60%) | $15.00 | $20.00 |
| MGS end anchor | 6061080 | EACH | 19 | 17 (89%) | $1,800.00 | $1,500.00 |
| Temporary traffic barrier, contractor furnished retained | 6173600D | LF | 27 | 16 (59%) | $24.50 | $31.50 |
| Pavement marking removal | 6207001 | LF | 24 | 16 (67%) | $1.00 | $1.04 |
| 4 in. white standard waterborne pavement marking paint, type P beads | 6206000C | LF | 22 | 16 (73%) | $0.85 | $0.20 |
| Additional mobilization for seeding | 6181020 | EACH | 16 | 16 (100%) | $600.00 | $600.00 |
| Sediment removal | 8061016 | CY | 46 | 15 (33%) | $25.00 | $25.69 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Concrete Strategies, LLC | 17 | 9 of 17 |
| Pace Construction Company, LLC | 15 | 8 of 15 |
| Millstone Weber, LLC | 13 | 9 of 13 |
| Gershenson Construction Co., Inc. | 11 | 5 of 11 |
| R. V. Wagner, Inc. | 11 | 7 of 11 |
| KCI Construction Company | 10 | 2 of 10 |
| Don Schnieders Excavating Company, Inc. | 7 | 6 of 7 |
| E & C Bridge, LLC | 7 | 7 of 7 |
| Emery Sapp & Sons, Inc. | 7 | 5 of 7 |
| Lehman Construction, LLC | 6 | 5 of 6 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 18 SEP 2026 | 260918-F03 | St. Louis | JSL0305 - I-70 - ST. CHARLES COUNTY | 2 of 2 | $3,100,000 | +32% |
| 18 JUN 2026 | 260618-F01 | St. Louis | J6I3020D, J6I350B, JSL0021 - I-270 - ST. LOUIS COUNTY | 2 of 4 | $44,000,000 | +8.0% |
| 15 MAY 2026 | 260515-D05 | Central | JCD0228 - ROUTE A - WASHINGTON COUNTY | 4 of 6 | $2,458,311 | +8.0% |
| 16 JAN 2026 | 260116-F07 | St. Louis | JSLM0071 - ROUTE 141, 21 - ST. LOUIS, JEFFERSON COUNTIES | 5 of 9 | $310,000 | +50% |
| 12 DEC 2025 | 251212-F01 | St. Louis | J6I3618-ROUTE I-270-ST LOUIS COUNTY | 5 of 5 | $1,025,000 | +57% |
| 14 NOV 2025 | 251114-F08 | St. Louis | J6I3290 - ROUTE I-55 - ST LOUIS, JEFFERSON COUNTIES | 1 of 4 | $16,519,421 | Low, 7.0% under the second |
| 17 OCT 2025 | 251017-F04 | St. Louis | J6S3289, J6S3391 - ROUTE 61/67 - JEFFERSON COUNTY | 3 of 3 | $23,000,000 | +28% |
| 15 AUG 2025 | 250815-F06 | St. Louis | JSLM0112 - ROUTE I-270 - ST LOUIS COUNTY | 1 of 3 | $481,000 | Low, 27% under the second |
| 16 MAY 2025 | 250516-D03 | Central | 2 Bridge deck replacements | 6 of 7 | $3,289,000 | +52% |
| 16 MAY 2025 | 250516-F11 | St. Louis | JSL0112 - ROUTE I-64 NOR - ST CHARLES COUNTY | 4 of 4 | $4,929,842 | +29% |
| 16 MAY 2025 | 250516-F15 | St. Louis | JSLM0066 - ROUTE I-64 EB - ST LOUIS CITY | 3 of 3 | $538,000 | +25% |
| 18 APR 2025 | 250418-D01 | Central | J5S3552 - ROUTE J - CRAWFORD COUNTY | 2 of 2 | $748,000 | +22% |
| 14 MAR 2025 | 250314-D01 | Central | J5P3537 - ROUTE 63 - PHELPS COUNTY | 1 of 3 | $1,560,000 | Low, 4.0% under the second |
| 14 MAR 2025 | 250314-D03 | Central | J5S3480B, J5S3541, J5S3547, J5S3548, J5S3549, J5S3563 - ROUTE I-44 - PULASKI, PHELPS COUNTIES | 2 of 2 | $4,115,000 | +4.0% |
| 14 MAR 2025 | 250314-F01 | St. Louis | J6I3573B - ROUTE AC - ST LOUIS COUNTY | 1 of 2 | $1,922,080 | Low, 2.0% under the second |
| 14 MAR 2025 | 250314-F03 | St. Louis | J6S3626 - ROUTE D - ST. LOUIS COUNTY | 1 of 5 | $11,260,000 | Low, 5.0% under the second |
| 21 FEB 2025 | 250221-B02 | Northeast | J2S3438, J2S3439 - ROUTE A/B, E/Y - WAREN, MONTGOMERY COUNTIES | 3 of 4 | $14,462,000 | +5.0% |
| 21 FEB 2025 | 250221-B03 | Northeast | JNE0053, JNE0154 - ROUTE K - MONTGOMERY | 8 of 10 | $4,836,647 | +23% |
| 21 FEB 2025 | 250221-D02 | Central | J5S3533 - ROUTES OR I-44 - CRAWFORD COUNTY | 2 of 5 | $739,000 | +28% |
| 17 JAN 2025 | 250117-D01 | Central | J5I3561 - ROUTE I-44 - PHELPS COUNTY | 3 of 3 | $992,200 | +17% |
| 17 JAN 2025 | 250117-D02 | Central | J5P3560, JCD0157 - ROUTE 54 - COLE COUNTY | 3 of 3 | $3,545,000 | +24% |
| 17 JAN 2025 | 250117-F07 | St. Louis | J6I3624B - ROUTE I-170 - ST LOUIS COUNTY | 2 of 4 | $3,340,000 | +16% |
| 17 JAN 2025 | 250117-F08 | St. Louis | JSLM0045- ROUTE I-270 - ST LOUIS COUNTY | 4 of 8 | $589,649 | +36% |
| 15 NOV 2024 | 241115-F01 | St. Louis | J6I3538 - ROUTE I-64 - ST LOUIS, ST CHARLES COUNTIES | 2 of 5 | $17,100,000 | +1.0% |
| 15 MAR 2024 | 240315-F04 | St. Louis | J6S3621-ROUTE 67/180-ST LOUIS COUNTY | 3 of 4 | $2,090,000 | +2.0% |
How this record was read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Every bid counted here matched its published total to within one dollar; MoDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.