MoDOT letting results, September 18, 2026
27 contracts let by Missouri DOT on September 18, 2026, $58,842,369 in low bids, a median of 3 bidders per contract.
- Owner
- Missouri DOT
- Contracts
- 27
- Low bids, total
- $58,842,369
- Data through
- 16 OCT 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| 260918-C04 | JKU0066 - ROUTE 40 - JACKSON COUNTY | Kansas City | 3 | Amino Bros. Co., Inc. | $8,957,977 | $8,993,900 | 0.0% | MoDOT |
| 260918-G02 | JSR0028, JSR0033, JSR0442, JSR0487 - VARIOUS ROUTES, VARIOUS COUNTIES | Southwest | 4 | APAC-Central, Inc. | $7,502,528 | $8,625,758 | +15% | MoDOT |
| 260918-G01 | J8S0745, J8S3133, J8S3153 - ROUTE D - GREENE COUNTY | Southwest | 6 | D & E Plumbing and Heating, Inc. | $6,565,904 | $6,661,114 | +1.0% | MoDOT |
| 260918-B02 | JNE0024, JNE0254 - ROUTE 11, 6 - ADAIR, KNOX, LINN, AND SULLIVAN COUNTIES | Northeast | 5 | W. L. Miller Company | $4,324,043 | $4,708,627 | +9.0% | MoDOT |
| 260918-D01 | JCD0178 - ROUTES MM, TT, F, O - CAMDEN AND MORGAN COUNTIES | Central | 3 | Emery Sapp & Sons, Inc. | $4,092,731 | $4,181,929 | +2.0% | MoDOT |
| 260918-H02 | JST0144-VARIOUS ROUTES-VARIOUS COUNTIES | Southeast | 2 | West Plains Bridge & Grading, LLC | $3,160,000 | $3,432,765 | +9.0% | MoDOT |
| 260918-C01 | JKU0056 - ROUTE 92 - PLATTE, CLAY COUNTIES | Kansas City | 3 | Herzog Contracting Corp. | $2,908,918 | $3,100,372 | +7.0% | MoDOT |
| 260918-D04 | JCD0185 - ROUTE A, Y - GASCONADE COUNTY | Central | 3 | Capital Paving & Construction, LLC | $2,593,302 | $2,597,125 | 0.0% | MoDOT |
| 260918-A01 | 19 BRIDGE REHABILITATIONS | Northwest | 2 | Louis-Company, LLC | $2,463,881 | $3,602,917 | +46% | MoDOT |
| 260918-F03 | JSL0305 - I-70 - ST. CHARLES COUNTY | St. Louis | 2 | Concrete Strategies, LLC | $2,347,998 | $3,100,000 | +32% | MoDOT |
| 260918-H03 | JST0144B-VARIOUS ROUTES-VARIOUS COUNTIES | Southeast | 2 | West Plains Bridge & Grading, LLC | $2,200,000 | $3,266,117 | +48% | MoDOT |
| 260918-H01 | J9P3570 - ROUTE 21 - IRON COUNTY | Southeast | 1 | Pace Construction Company, LLC | $1,943,169 | MoDOT | ||
| 260918-D06 | JCD0191, JCD0198 - ROUTE MM, DD - BOONE COUNTY | Central | 2 | Christensen Construction Co. | $1,486,028 | $1,542,622 | +4.0% | MoDOT |
| 260918-D03 | JCD0184 - VARIOUS ROUTES - COLE COUNTY | Central | 1 | Capital Paving & Construction, LLC | $1,128,062 | MoDOT | ||
| 260918-F01 | JSL0129 - ROUTE 64 - ST LOUIS CITY COUNTY | St. Louis | 3 | Sweetens Sealing Services LLC | $1,122,833 | $1,696,404 | +51% | MoDOT |
| 260918-D05 | JCD0190 - ROUTE 163 - BOONE COUNTY | Central | 2 | Christensen Construction Co. | $863,699 | $919,106 | +6.0% | MoDOT |
| 260918-C03 | JKU0512 - ROUTE I-435 - JACKSON COUNTY | Kansas City | 2 | Raising Solutions, LLC | $856,433 | $1,103,422 | +29% | MoDOT |
| 260918-D07 | JCD0214 - ROUTE 50 - MONITEAU COUNTY | Central | 5 | Ti-Zack Concrete, LLC | $847,850 | $1,052,656 | +24% | MoDOT |
| 260918-F02 | JSL0194, JSL0194B - VARIOUS ROUTES - VARIOUS COUNTIES | St. Louis | 2 | AAD Contracting, Inc. | $847,000 | $2,358,000 | +178% | MoDOT |
| 260918-C02 | JKU0321-VARIOUS ROUTES-JACKSON, CLAY COUNTIES | Kansas City | 6 of 7 | Skidabrader Group LLC | $659,525 | $794,500 | +20% | MoDOT |
| 260918-B01 | JNE0112 - ROUTE J - AUDRAIN COUNTY | Northeast | 5 | W. L. Miller Company | $598,302 | $661,079 | +10% | MoDOT |
| 260918-A03 | JNWM0130 - ROUTE I-35 - HARRISON COUNTY | Northwest | 5 | Parking Lot Maintenance, LLC | $444,355 | $543,552 | +22% | MoDOT |
| 260918-D11 | JCD0219B-ROUTE 54 - COLE COUNTY | Central | 6 | TB Dozing & Excavation, LLC | $359,181 | $377,195 | +5.0% | MoDOT |
| 260918-F05 | JSLM0078 - ROUTE BB - JEFDFERSON COUNTY | St. Louis | 1 | Gershenson Construction Co., Inc. | $348,836 | MoDOT | ||
| 260918-D08 | JCD0340 - ROUTE B - DENT COUNTY | Central | 6 | H.R. Quadri Contractors, LLC | $219,812 | $280,048 | +27% | MoDOT |
| 260918-D09 | JST0141-VARIOUS ROUTES-VARIOUS COUNTIES | Central | 2 | Collins & Hermann, Inc. | $1 | $1 | +41% | MoDOT |
| 260918-D10 | JST0141B-VARIOUS ROUTES-VARIOUS COUNTIES | Central | 2 | Collins & Hermann, Inc. | $1 | $1 | +41% | MoDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than MoDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.