MoDOT contract 260918-G01 bid tabulation
J8S0745, J8S3133, J8S3153 - ROUTE D - GREENE COUNTY. Let by Missouri DOT on September 18, 2026, Greene, Southwest. 6 bids received; low bid $6,565,904 by D & E Plumbing and Heating, Inc..
- Owner
- Missouri DOT
- Letting
- 18 SEP 2026
- Pay items
- 238
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D & E Plumbing and Heating, Inc. | $6,565,904 | Low |
| 2 | KCI Construction Company | $6,661,114 | +1.0% |
| 3 | Hunter Chase & Associates, Inc. | $6,769,000 | +3.0% |
| 4 | Branco Enterprises, Inc. | $7,255,998 | +11% |
| 5 | Ti-Zack Concrete, LLC | $7,295,089 | +11% |
| 6 | Radmacher Brothers Excavating Co., Inc. | $9,732,970 | +48% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D & E Plumbing and Heating, Inc. | 2. KCI Construction Company | 3. Hunter Chase & Associates, Inc. | 4. Branco Enterprises, Inc. | 5. Ti-Zack Concrete, LLC | 6. Radmacher Brothers Excavating Co., Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Asphaltic concrete mixture PG 70-22 (SP095C mix) (4030003) | TON | 10,120.60 | $75.00 | $75.00 | $88.66 | $84.75 | $94.60 | $93.00 |
| 0020 | Tack coat (4071005) | GAL | 10,305 | $3.65 | $3.65 | $3.14 | $3.00 | $3.30 | $3.30 |
| 0030 | Truck mounted attenuator (TMA) (6123001) | LS | 1 | $10,000 | $46,046 | $15,535 | $11,500 | $5,000.00 | $6,510.00 |
| 0040 | Construction signs (6161005) | SF | 1,400 | $6.50 | $6.50 | $6.73 | $6.50 | $6.60 | $6.60 |
| 0050 | Channelizer (trim-line) (6161025) | EACH | 250 | $15.00 | $15.00 | $15.54 | $15.00 | $33.00 | $30.75 |
| 0060 | Type 3 moveable barricade (6161030) | EACH | 2 | $175.00 | $175.00 | $181.25 | $175.00 | $220.00 | $550.00 |
| 0070 | Flashing arrow panel (6161040) | EACH | 2 | $1,100.00 | $1,100.00 | $1,139.24 | $1,100.00 | $1,320.00 | $3,300.00 |
| 0080 | Sequential flashing warning light (6161055) | EACH | 12 | $80.00 | $80.00 | $82.85 | $80.00 | $165.00 | $60.50 |
| 0090 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 2 | $3,200.00 | $3,200.00 | $3,314.15 | $3,200.00 | $4,950.00 | $8,250.00 |
| 0100 | Mobilization (6181000) | LS | 1 | $100,000 | $150,000 | $204,618 | $65,000 | $112,860 | $96,510 |
| 0110 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 4,682 | $20.00 | $22.00 | $22.78 | $22.00 | $16.50 | $22.00 |
| 0120 | Preformed thermoplastic pavement marking, 24 in. yellow (6200018) | LF | 263 | $22.00 | $22.00 | $22.78 | $22.00 | $16.50 | $24.20 |
| 0130 | Preformed thermoplastic pavement marking, left/right arrow (6200021) | EACH | 106 | $190.00 | $250.00 | $258.92 | $250.00 | $302.50 | $209.00 |
| 0140 | Preformed thermoplastic pavement marking, R/R crossing marker (6200033) | EACH | 5 | $1,100.00 | $410.00 | $424.63 | $410.00 | $1,100.00 | $1,210.00 |
| 0150 | Preformed thermoplastic pavement marking, 24 in. X 36 in., yield line triangle (6200042A) | EACH | 180 | $28.00 | $65.00 | $67.32 | $65.00 | $110.00 | $30.75 |
| 0160 | Preformed thermoplastic pavement marking, LT/RT fish hook arrow (6200045) | EACH | 3 | $550.00 | $350.00 | $362.49 | $350.00 | $550.00 | $605.00 |
| 0170 | 4 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205901B) | LF | 51,334 | $0.21 | $0.62 | $0.64 | $0.62 | $0.17 | $0.25 |
| 0180 | 6 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B) | LF | 36,534 | $0.28 | $0.80 | $0.83 | $0.80 | $0.28 | $0.30 |
| 0190 | 6 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205903B) | LF | 5,617 | $0.28 | $0.80 | $0.83 | $0.80 | $0.28 | $0.30 |
| 0200 | 12 in. white class 2 pavement marking paint (25-mil, type L beads) (6205906B) | LF | 556 | $1.05 | $1.50 | $1.55 | $1.50 | $0.55 | $1.15 |
| 0210 | Pavement marking removal (6207001) | LF | 281 | $1.00 | $1.50 | $1.55 | $1.50 | $1.10 | $1.10 |
| 0220 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 103,045 | $1.30 | $1.30 | $1.41 | $1.35 | $1.49 | $1.50 |
| 0230 | Contractor furnished surveying and staking (6274000) | LS | 1 | $3,600.00 | $17,500 | $17,261 | $15,500 | $17,500 | $5,500.00 |
| 0240 | Cable, loop detector, in duct (9028500) | LF | 3,390 | $7.55 | $7.55 | $7.82 | $7.55 | $8.31 | $8.30 |
| 0250 | Misc.contractor furnished contractor installed radar detection system (9029902) | EACH | 4 | $53,250 | $53,250 | $55,150 | $53,250 | $58,575 | $58,580 |
| 0260 | Misc.contractor furnished contractor installed radar detection system - plaza intersection (9029902) | EACH | 1 | $75,500 | $75,500 | $78,193 | $75,500 | $83,050 | $83,050 |
| 0270 | Misc.relocate signal head (9029902) | EACH | 20 | $1,100.00 | $1,100.00 | $1,139.24 | $1,100.00 | $1,210.00 | $1,210.00 |
| 0280 | Removal of improvements (2022010) | LS | 1 | $53,300 | $97,806 | $4,714.60 | $100,000 | $45,000 | $505,570 |
| 0290 | Unclassified excavation (2035000) | CY | 1,170 | $30.00 | $26.01 | $21.72 | $15.00 | $66.77 | $141.00 |
| 0300 | Compacting embankment (2036000) | CY | 144 | $20.00 | $8.70 | $41.14 | $10.00 | $54.25 | $32.50 |
| 0310 | Class 3 excavation (2063000) | CY | 237 | $30.00 | $23.81 | $150.98 | $29.00 | $65.92 | $141.00 |
| 0320 | Misc.linear grading for ADA facilities (2079903) | LF | 2,023 | $25.00 | $12.56 | $18.61 | $12.00 | $6.97 | $83.50 |
| 0330 | Type 1 aggregate for base (4 in. thick) (3040143) | SY | 1,744 | $20.00 | $17.40 | $15.00 | $13.00 | $8.58 | $22.40 |
| 0340 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 187 | $20.00 | $15.42 | $39.28 | $14.00 | $8.27 | $23.40 |
| 0350 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 2,015 | $30.00 | $15.39 | $15.00 | $18.00 | $10.47 | $27.50 |
| 0360 | Bituminous pavement mixture PG64-22, (BP-1) (4011209) | TON | 15 | $415.00 | $415.00 | $421.59 | $403.00 | $443.30 | $443.00 |
| 0370 | Misc.radii improvements optional pavement (4019905) | SY | 325.70 | $120.00 | $82.36 | $99.38 | $98.00 | $104.50 | $112.00 |
| 0380 | Misc.sunshine optional pavement (4019905) | SY | 1,688.60 | $80.00 | $101.37 | $64.86 | $65.00 | $68.20 | $112.00 |
| 0390 | Pipe collar, type A (6044011) | EACH | 2 | $2,000.00 | $3,022.59 | $2,151.07 | $3,874.00 | $3,300.00 | $4,530.00 |
| 0400 | Misc.steel plate (6049904) | SF | 24 | $500.00 | $257.81 | $434.15 | $225.00 | $61.59 | $488.00 |
| 0410 | Concrete curb ramp (6081010) | SY | 334.90 | $125.00 | $183.35 | $223.13 | $190.00 | $150.00 | $201.00 |
| 0420 | Truncated domes (6081012) | SF | 275 | $45.00 | $31.38 | $31.97 | $32.00 | $31.50 | $45.00 |
| 0430 | 8 in. concrete median strip (6083008) | SY | 1,797 | $147.00 | $110.22 | $104.09 | $143.00 | $171.14 | $112.00 |
| 0440 | Concrete sidewalk, 4 in. (6086004) | SY | 942.80 | $61.00 | $75.12 | $67.00 | $104.00 | $95.00 | $104.00 |
| 0450 | Concrete sidewalk, 8 in. (6086008) | SY | 23.90 | $87.00 | $113.63 | $351.91 | $216.00 | $171.14 | $137.00 |
| 0460 | Misc.modified paved approach, 8 in. (6089905) | SY | 140.40 | $140.00 | $150.00 | $154.85 | $159.00 | $148.13 | $137.00 |
| 0470 | Concrete curb (6 in. height and under) type S (6091010) | LF | 119 | $95.00 | $61.44 | $114.91 | $83.00 | $33.29 | $128.00 |
| 0480 | Curb and gutter type B (6091052) | LF | 1,190 | $55.00 | $81.19 | $48.75 | $71.00 | $66.59 | $79.00 |
| 0490 | Misc.curb and gutter (greene county STD) (6099903) | LF | 216 | $55.00 | $41.86 | $48.71 | $51.00 | $66.59 | $79.00 |
| 0500 | Misc.modified type A gutter (6099903) | LF | 28 | $68.00 | $63.92 | $104.47 | $154.00 | $81.29 | $104.00 |
| 0510 | Misc.modified type B curb (6099903) | LF | 55 | $68.00 | $57.75 | $76.92 | $75.00 | $81.29 | $90.00 |
| 0520 | Truck mounted attenuator (TMA) (6123001) | LS | 1 | $20,000 | $46,046 | $15,535 | $23,000 | $5,000.00 | $6,510.00 |
| 0530 | Manhole frame and cover, type 3 (6143013) | EACH | 7 | $500.00 | $573.36 | $1,634.15 | $786.00 | $290.00 | $683.00 |
| 0540 | Manhole frame and cover, type 4 (6143014) | EACH | 4 | $500.00 | $828.57 | $2,011.69 | $1,234.00 | $409.00 | $941.00 |
| 0550 | Construction signs (6161005) | SF | 867 | $6.50 | $6.50 | $6.73 | $6.50 | $6.60 | $6.60 |
| 0560 | Channelizer (trim-line) (6161025) | EACH | 300 | $15.00 | $15.00 | $15.54 | $15.00 | $33.00 | $30.75 |
| 0570 | Type 3 moveable barricade (6161030) | EACH | 10 | $175.00 | $175.00 | $181.24 | $175.00 | $220.00 | $550.00 |
| 0580 | Direction indicator barricade (6161033) | EACH | 28 | $80.00 | $80.00 | $82.85 | $80.00 | $55.00 | $165.00 |
| 0590 | Flashing arrow panel (6161040) | EACH | 2 | $1,100.00 | $1,100.00 | $1,139.24 | $1,100.00 | $1,320.00 | $3,300.00 |
| 0600 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 2 | $3,200.00 | $3,200.00 | $3,314.15 | $3,200.00 | $4,950.00 | $8,250.00 |
| 0610 | Misc.ADA compliant moveable barricade (6169902) | EACH | 8 | $155.00 | $155.00 | $160.53 | $155.00 | $82.50 | $220.00 |
| 0620 | Misc.traffic separator curb with delineators (6179903) | LF | 287 | $62.00 | $70.00 | $72.50 | $70.00 | $68.09 | $67.00 |
| 0630 | Mobilization (6181000) | LS | 1 | $100,000 | $240,000 | $210,576 | $156,001 | $225,720 | $645,260 |
| 0640 | Additional mobilization for seeding (6181020) | EACH | 2 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0650 | Contractor furnished surveying and staking (6274000) | LS | 1 | $39,000 | $44,000 | $17,261 | $30,000 | $44,000 | $44,000 |
| 0660 | 12 in. pipe group B (7250312A) | LF | 3 | $100.00 | $214.51 | $351.16 | $105.00 | $137.50 | $517.00 |
| 0670 | 30 in. pipe group B (7250330A) | LF | 10 | $100.00 | $124.74 | $209.44 | $230.00 | $170.50 | $207.00 |
| 0680 | 12 in. pipe group A (7261012) | LF | 44 | $100.00 | $86.98 | $100.99 | $120.00 | $137.50 | $142.00 |
| 0690 | 15 in. pipe group A (7261015) | LF | 166 | $100.00 | $85.57 | $82.59 | $100.00 | $170.50 | $142.00 |
| 0700 | Precast concrete manhole - 48 in. (7310048) | FT | 15 | $2,000.00 | $1,056.33 | $618.01 | $1,060.00 | $1,375.00 | $800.00 |
| 0710 | Precast concrete manhole - 60 in. (7310060) | FT | 6 | $3,000.00 | $1,121.47 | $836.23 | $1,147.00 | $2,200.00 | $908.00 |
| 0720 | Precast concrete drop inlet 3 FT X 2 FT-6 in. (7311030) | FT | 24 | $1,500.00 | $755.05 | $628.81 | $764.00 | $1,540.00 | $611.00 |
| 0730 | Precast concrete drop inlet 5 FT X 3 FT (7311053) | FT | 19 | $2,000.00 | $6,812.49 | $748.99 | $1,650.00 | $1,760.00 | $1,240.00 |
| 0740 | 30 in. or allowed substitute group B flared end section (7320030A) | EACH | 1 | $1,500.00 | $2,766.33 | $1,400.72 | $2,109.00 | $1,265.00 | $1,590.00 |
| 0750 | Turf type tall fescue sodding (8031000A) | SY | 454 | $15.00 | $13.00 | $12.03 | $13.00 | $12.38 | $14.30 |
| 0760 | Misc.seeding and mulching - cool season grasses (8059901) | LS | 1 | $10,000 | $3,850.00 | $4,956.83 | $3,850.00 | $4,235.00 | $4,240.00 |
| 0770 | Curb inlet check (8061007A) | EACH | 14 | $150.00 | $20.00 | $177.39 | $20.00 | $11.00 | $22.00 |
| 0780 | Sediment removal (8061016) | CY | 30 | $10.00 | $22.92 | $105.81 | $20.00 | $27.50 | $217.00 |
| 0790 | Silt fence (8061019) | LF | 1,315 | $5.00 | $1.00 | $4.56 | $1.00 | $1.10 | $1.10 |
| 0800 | Signal head, type 3S (9020213) | EACH | 1 | $1,175.00 | $1,175.00 | $1,216.91 | $1,175.00 | $1,292.50 | $1,290.00 |
| 0810 | Signal head, type 3B (9020513) | EACH | 18 | $1,750.00 | $1,750.00 | $1,812.43 | $1,750.00 | $1,925.00 | $1,930.00 |
| 0820 | Signal head, type 4B (9020514) | EACH | 8 | $1,860.00 | $1,860.00 | $1,926.35 | $1,860.00 | $2,046.00 | $2,050.00 |
| 0830 | Signal head, type 1S, pedestrian (9020811) | EACH | 18 | $750.00 | $750.00 | $776.75 | $750.00 | $825.00 | $825.00 |
| 0840 | SH-flat sheet - signal sign (9020833) | SF | 136 | $25.00 | $25.00 | $25.89 | $25.00 | $27.50 | $27.50 |
| 0850 | Signal sign, mounting hardware (9020834) | EACH | 18 | $65.50 | $65.50 | $67.84 | $65.50 | $72.05 | $72.00 |
| 0860 | Post, signal 8 FT. (9022708) | EACH | 14 | $1,605.00 | $1,605.00 | $1,662.25 | $1,605.00 | $1,765.50 | $1,770.00 |
| 0870 | Post, signal 15 FT. (9022715) | EACH | 1 | $2,075.00 | $2,075.00 | $2,149.02 | $2,075.00 | $2,282.50 | $2,280.00 |
| 0880 | Post, type C, 30 FT. arm or 9.1 M arm (9023230) | EACH | 2 | $18,500 | $18,500 | $19,160 | $18,500 | $20,350 | $20,350 |
| 0890 | Post, type C, 35 FT. arm or 10.7 M arm (9023235) | EACH | 1 | $1,875.00 | $1,875.00 | $1,941.88 | $1,875.00 | $2,062.50 | $2,060.00 |
| 0900 | Post, type C, 40 FT. arm or 12.2 M arm (9023240) | EACH | 3 | $21,500 | $21,500 | $22,267 | $21,500 | $23,650 | $23,650 |
| 0910 | Post, type C, 45 FT. arm or 13.7 M arm (9023245) | EACH | 1 | $22,000 | $22,000 | $22,785 | $22,000 | $24,200 | $24,200 |
| 0920 | Post, type C, 55 FT. arm (9023255) | EACH | 1 | $24,500 | $24,500 | $25,374 | $24,500 | $26,950 | $26,950 |
| 0930 | Accessible pedestrian signal (9024921) | EACH | 18 | $985.00 | $985.00 | $1,020.14 | $985.00 | $1,083.50 | $1,080.00 |
| 0940 | Conduit, 2 in., trench with tracer wire (9025200) | LF | 37 | $24.50 | $24.50 | $25.37 | $24.50 | $26.95 | $27.00 |
| 0950 | Conduit, 3 in., trench with tracer wire (9025300) | LF | 132 | $27.85 | $27.85 | $28.84 | $27.85 | $30.64 | $30.75 |
| 0960 | Conduit, 4 in., trench with tracer wire (9025400) | LF | 345 | $29.50 | $29.50 | $30.55 | $29.50 | $32.45 | $32.50 |
| 0970 | Conduit, 3 in., pushed with tracer wire (9027300) | LF | 93 | $41.50 | $41.50 | $42.98 | $41.50 | $45.65 | $45.75 |
| 0980 | Conduit, 4 in., pushed with tracer wire (9027400) | LF | 514 | $44.25 | $44.25 | $45.83 | $44.25 | $48.68 | $48.75 |
| 0990 | Cable, 8 AWG 1 conductor, power (9028208) | LF | 460 | $2.30 | $2.30 | $2.38 | $2.30 | $2.53 | $2.55 |
| 1000 | Cable, 16 AWG 2 conductor (9028308) | LF | 2,570 | $2.02 | $2.02 | $2.09 | $2.02 | $2.22 | $2.20 |
| 1010 | Cable, 16 AWG 5 conductor (9028310) | LF | 2,600 | $2.75 | $2.75 | $2.85 | $2.75 | $3.03 | $3.05 |
| 1020 | Cable, 16 AWG 7 conductor (9028311) | LF | 4,420 | $2.70 | $2.70 | $2.80 | $2.70 | $2.97 | $2.95 |
| 1030 | Power supply assembly, type 2 (9028620) | EACH | 3 | $10,200 | $10,200 | $10,564 | $10,200 | $11,220 | $11,220 |
| 1040 | Pull box, concrete, standard (9028820) | EACH | 6 | $3,500.00 | $3,500.00 | $3,624.85 | $3,500.00 | $3,850.00 | $3,850.00 |
| 1050 | Pull box, concrete, double, type A (9028821) | EACH | 3 | $5,150.00 | $5,150.00 | $5,333.71 | $5,150.00 | $5,665.00 | $5,670.00 |
| 1060 | Base, concrete (9029100) | CY | 32.10 | $2,250.00 | $2,250.00 | $2,330.26 | $2,250.00 | $2,475.00 | $2,480.00 |
| 1070 | Misc.2070 controller (9029902) | EACH | 3 | $38,000 | $38,000 | $39,356 | $38,000 | $41,800 | $41,800 |
| 1080 | Misc.contractor furnished, contractor installed radar detection system (9029902) | EACH | 2 | $53,250 | $53,250 | $55,150 | $53,250 | $58,575 | $58,580 |
| 1090 | Misc.remote pushbutton post (9029902) | EACH | 1 | $1,350.00 | $1,350.00 | $1,398.16 | $1,350.00 | $1,485.00 | $1,490.00 |
| 1100 | Concrete footings, embedded (9031010) | CY | 2.70 | $1,560.00 | $1,560.00 | $1,615.65 | $1,560.00 | $68.09 | $1,720.00 |
| 1110 | Pipe posts (9031220) | LB | 1,622 | $6.90 | $6.90 | $7.15 | $6.90 | $7.59 | $7.60 |
| 1120 | 2 in. PSST post - 12 GA. (9031270A) | LF | 334 | $11.50 | $11.50 | $11.91 | $11.50 | $12.65 | $12.65 |
| 1130 | Driven post anchor for 2 in. PSST - 7 GA. (9031273A) | EACH | 36 | $168.50 | $168.50 | $174.51 | $168.50 | $185.35 | $185.00 |
| 1140 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 108 | $12.35 | $12.35 | $12.79 | $12.35 | $13.59 | $13.60 |
| 1150 | Driven post anchor for 2.5 in. PSST - 7 GA. (9031281A) | EACH | 8 | $183.60 | $183.60 | $190.15 | $183.60 | $201.96 | $202.00 |
| 1160 | SH-flat sheet (9035004A) | SF | 314 | $19.15 | $19.15 | $19.83 | $19.15 | $21.07 | $21.10 |
| 1170 | Conduit, 2 in., trench with tracer wire (9025200) | LF | 115 | $24.00 | $24.00 | $24.86 | $24.00 | $26.95 | $26.50 |
| 1180 | Conduit, 2 in., pushed with tracer wire (9027200) | LF | 2,145 | $33.00 | $33.00 | $34.18 | $33.00 | $36.30 | $36.25 |
| 1190 | Misc.ITS cabinet (9029902) | EACH | 3 | $11,750 | $11,750 | $12,169 | $11,750 | $12,925 | $12,930 |
| 1200 | Cable, 6 AWG, 1 conductor, power (9108206) | LF | 90 | $2.75 | $2.75 | $2.85 | $2.75 | $302.50 | $3.05 |
| 1210 | Pull box, preformed class 5 (9108816) | EACH | 1 | $3,150.00 | $3,150.00 | $3,262.37 | $3,150.00 | $3,465.00 | $3,470.00 |
| 1220 | Pull box, concrete, standard (9108820) | EACH | 3 | $3,565.00 | $3,565.00 | $3,692.17 | $3,565.00 | $3,850.00 | $3,920.00 |
| 1230 | Misc.48 port fiber distribution unit (9109902) | EACH | 3 | $1,450.00 | $1,450.00 | $1,501.72 | $1,450.00 | $1,595.00 | $1,600.00 |
| 1240 | Misc.furnishing and installing ethernet switch (9109902) | EACH | 1 | $1,550.00 | $1,550.00 | $1,605.29 | $1,550.00 | $1,705.00 | $1,710.00 |
| 1250 | Misc.relocate existing ethernet switch (9109902) | EACH | 2 | $275.00 | $275.00 | $284.81 | $275.00 | $302.50 | $303.00 |
| 1260 | Misc.ethernet cable (CAT6) (9109903) | LF | 135 | $3.00 | $3.00 | $3.11 | $3.00 | $3.30 | $3.30 |
| 1270 | Misc.misc - fiber optic cable, 24 - fiber, single mode (9109903) | LF | 2,930 | $7.50 | $7.50 | $7.77 | $7.50 | $8.25 | $8.25 |
| 1280 | Misc.pigmenting and texturing concrete (6089905) | SY | 1,797 | $42.00 | $39.00 | $39.89 | $58.00 | $180.47 | $33.50 |
| 1290 | Misc.concrete streetlight pole foundation W/ rebar (CF24) (9019902) | EACH | 9 | $2,085.00 | $2,085.00 | $2,159.38 | $2,085.00 | $2,293.50 | $2,290.00 |
| 1300 | Misc.furnish/install secondary riser start (SR-2CP) (9019902) | EACH | 2 | $1,550.00 | $1,550.00 | $1,605.29 | $1,550.00 | $1,705.00 | $1,710.00 |
| 1310 | Misc.install secondary pedestal (SP-2C) (9019902) | EACH | 2 | $1,205.00 | $1,205.00 | $1,247.99 | $1,205.00 | $1,325.50 | $1,330.00 |
| 1320 | Misc.install secondary pedestal for sidewalk installation (SP-SW) (9019902) | EACH | 1 | $1,205.00 | $1,205.00 | $1,247.98 | $1,205.00 | $1,325.50 | $1,330.00 |
| 1330 | Misc.remove concrete streetlight pole foundation (9019902) | EACH | 8 | $295.00 | $295.00 | $305.52 | $295.00 | $324.50 | $325.00 |
| 1340 | Misc.remove secondary pedestal (9019902) | EACH | 1 | $150.00 | $150.00 | $155.35 | $150.00 | $165.00 | $165.00 |
| 1350 | Misc.remove secondary riser (9019902) | EACH | 1 | $150.00 | $150.00 | $155.35 | $150.00 | $165.00 | $165.00 |
| 1360 | Misc.remove steel streetlight pole foundation (9019902) | EACH | 1 | $295.00 | $295.00 | $305.52 | $295.00 | $324.50 | $325.00 |
| 1370 | Misc.install (1) 2" HDPE conduit bored (9019903) | LF | 1,030 | $26.50 | $26.50 | $27.45 | $26.50 | $29.15 | $29.25 |
| 1380 | Misc.install 2" PVC conduit in trench (PVC-2) (9019903) | LF | 1,371 | $25.50 | $25.50 | $26.41 | $25.50 | $28.05 | $28.00 |
| 1390 | Removal of improvements (2022010) | LS | 1 | $195,000 | $3,495.38 | $5,053.42 | $141,000 | $100,000 | $4,350.00 |
| 1400 | Misc.sidewalk manicuring (2029903) | LF | 4,500 | $2.00 | $0.44 | $5.14 | $3.00 | $2.20 | $5.55 |
| 1410 | Misc.linear grading for ADA facilities (2079903) | LF | 5,701 | $25.00 | $11.46 | $18.52 | $9.00 | $6.97 | $83.50 |
| 1420 | Type 1 aggregate for base (4 in. thick) (3040143) | SY | 2,917 | $20.00 | $11.38 | $15.00 | $12.00 | $8.58 | $22.40 |
| 1430 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 4,118 | $20.00 | $13.58 | $14.93 | $11.00 | $8.27 | $23.40 |
| 1440 | Adjusting manhole (6042010) | EACH | 2 | $1,500.00 | $2,299.27 | $1,971.11 | $2,457.00 | $781.20 | $4,270.00 |
| 1450 | Adjusting basin or inlet (6042020) | EACH | 1 | $1,500.00 | $2,299.27 | $2,849.98 | $5,132.00 | $781.20 | $3,120.00 |
| 1460 | Misc.city sanitary manhole adjust to grade (6049902) | EACH | 4 | $1,500.00 | $2,299.27 | $2,143.11 | $9,066.00 | $868.00 | $3,120.00 |
| 1470 | Misc.steel plate (6049904) | SF | 43 | $500.00 | $249.69 | $424.48 | $188.00 | $61.59 | $488.00 |
| 1480 | Concrete curb ramp (6081010) | SY | 806.50 | $125.00 | $190.80 | $192.97 | $190.00 | $150.00 | $201.00 |
| 1490 | Truncated domes (6081012) | SF | 603 | $45.00 | $31.22 | $32.00 | $50.00 | $31.50 | $45.00 |
| 1500 | 8 in. concrete median strip (6083008) | SY | 18 | $147.00 | $102.61 | $541.76 | $135.00 | $171.14 | $111.00 |
| 1510 | Sidewalk hand-railing with balusters (6084024) | LF | 89 | $151.00 | $101.76 | $156.39 | $151.00 | $166.10 | $166.00 |
| 1520 | Paved approach, 8 in. (6085008) | SY | 4,117.50 | $120.00 | $114.01 | $107.00 | $172.00 | $148.13 | $137.00 |
| 1530 | Concrete sidewalk, 4 in. (6086004) | SY | 2,079 | $61.00 | $78.17 | $61.00 | $111.00 | $95.00 | $104.00 |
| 1540 | Concrete sidewalk, 8 in. (6086008) | SY | 13.70 | $87.00 | $129.37 | $361.78 | $184.00 | $171.14 | $137.00 |
| 1550 | Concrete curb (6 in. height and under) type S (6091010) | LF | 222 | $95.00 | $69.04 | $156.02 | $83.00 | $33.29 | $128.00 |
| 1560 | Curb and gutter type A (6091051) | LF | 93 | $55.00 | $78.91 | $84.16 | $65.00 | $81.29 | $104.00 |
| 1570 | Misc.modified type A gutter (6099903) | LF | 31 | $55.00 | $70.75 | $105.41 | $161.00 | $81.29 | $106.00 |
| 1580 | Misc.modified type S curb, 6 in. to 30 in. (6099903) | LF | 197 | $55.00 | $71.68 | $95.08 | $83.00 | $81.29 | $213.00 |
| 1590 | Truck mounted attenuator (TMA) (6123001) | LS | 1 | $20,000 | $46,046 | $15,535 | $40,000 | $5,000.00 | $6,510.00 |
| 1600 | Construction signs (6161005) | SF | 831 | $6.50 | $6.50 | $6.73 | $6.50 | $6.60 | $6.60 |
| 1610 | Channelizer (trim-line) (6161025) | EACH | 300 | $15.00 | $15.00 | $15.54 | $15.00 | $33.00 | $30.75 |
| 1620 | Type 3 moveable barricade (6161030) | EACH | 10 | $175.00 | $175.00 | $181.24 | $175.00 | $220.00 | $550.00 |
| 1630 | Direction indicator barricade (6161033) | EACH | 28 | $80.00 | $80.00 | $82.85 | $80.00 | $55.00 | $165.00 |
| 1640 | Flashing arrow panel (6161040) | EACH | 2 | $1,100.00 | $1,100.00 | $1,139.24 | $1,100.00 | $1,320.00 | $3,300.00 |
| 1650 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 2 | $3,200.00 | $3,200.00 | $3,314.15 | $3,200.00 | $4,950.00 | $8,250.00 |
| 1660 | Misc.ADA compliant type III moveable barricade (6169902) | EACH | 30 | $155.00 | $155.00 | $160.53 | $155.00 | $55.00 | $220.00 |
| 1670 | Mobilization (6181000) | LS | 1 | $100,000 | $240,000 | $269,967 | $306,000 | $112,860 | $827,990 |
| 1680 | Additional mobilization for seeding (6181020) | EACH | 3 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 |
| 1690 | Misc.sidewalk joint grinding (6229903) | LF | 600 | $2.00 | $3.92 | $8.65 | $28.00 | $38.50 | $44.75 |
| 1700 | Contractor furnished surveying and staking (6274000) | LS | 1 | $47,000 | $36,000 | $17,261 | $30,000 | $36,000 | $11,000 |
| 1710 | Mulching (8025006) | ACRE | 0.60 | $5,000.00 | $400.00 | $2,725.92 | $400.00 | $440.00 | $440.00 |
| 1720 | Turf type tall fescue sodding (8031000A) | SY | 5,140 | $15.00 | $11.25 | $11.85 | $11.25 | $12.38 | $12.40 |
| 1730 | Alternate ditch check (8061006) | LF | 300 | $50.00 | $3.00 | $3.51 | $3.00 | $3.30 | $3.30 |
| 1740 | Curb inlet check (8061007A) | EACH | 137 | $150.00 | $10.00 | $177.43 | $10.00 | $11.00 | $11.00 |
| 1750 | Sediment removal (8061016) | CY | 244 | $10.00 | $20.42 | $42.58 | $17.00 | $27.50 | $217.00 |
| 1760 | Temporary seeding (8061017) | ACRE | 0.60 | $6,000.00 | $400.00 | $3,034.87 | $400.00 | $440.00 | $440.00 |
| 1770 | Silt fence (8061019) | LF | 7,655 | $5.00 | $1.00 | $4.55 | $1.00 | $1.10 | $1.10 |
| 1780 | Signal head, type 4T (9020114) | EACH | 2 | $1,215.00 | $1,215.00 | $1,258.34 | $1,215.00 | $1,336.50 | $1,340.00 |
| 1790 | Signal head, type 4S (9020214) | EACH | 5 | $1,615.00 | $1,615.00 | $1,672.61 | $1,615.00 | $1,776.50 | $1,780.00 |
| 1800 | Signal head, type 3B (9020513) | EACH | 9 | $1,725.00 | $1,725.00 | $1,786.53 | $1,725.00 | $1,925.00 | $1,900.00 |
| 1810 | Signal head, type 4B (9020514) | EACH | 9 | $2,005.00 | $2,005.00 | $2,076.52 | $2,005.00 | $2,046.00 | $2,210.00 |
| 1820 | Signal head, type 5B (9020515) | EACH | 1 | $2,055.00 | $2,055.00 | $2,128.31 | $2,055.00 | $1,897.50 | $2,260.00 |
| 1830 | Signal head, type 1S, pedestrian (9020811) | EACH | 46 | $655.00 | $655.00 | $678.36 | $655.00 | $825.00 | $721.00 |
| 1840 | SH-flat sheet - signal sign (9020833) | SF | 45 | $21.25 | $21.25 | $22.01 | $21.25 | $27.50 | $23.40 |
| 1850 | Signal sign, mounting hardware (9020834) | EACH | 6 | $36.50 | $36.50 | $37.80 | $36.50 | $72.05 | $40.25 |
| 1860 | Post, signal 8 FT. (9022708) | EACH | 33 | $1,550.00 | $1,550.00 | $1,605.29 | $1,550.00 | $1,765.00 | $1,710.00 |
| 1870 | Post, type C, 45 FT. arm or 13.7 M arm (9023245) | EACH | 1 | $21,000 | $21,000 | $21,749 | $21,000 | $24,200 | $23,100 |
| 1880 | Accessible pedestrian signal (9024921) | EACH | 55 | $985.00 | $985.00 | $1,020.14 | $985.00 | $1,083.50 | $1,080.00 |
| 1890 | Conduit, 3 in., trench with tracer wire (9025300) | LF | 608 | $28.00 | $28.00 | $29.00 | $28.00 | $30.64 | $30.75 |
| 1900 | Conduit, 3 in., pushed with tracer wire (9027300) | LF | 649 | $34.25 | $34.25 | $35.47 | $34.25 | $45.65 | $37.75 |
| 1910 | Cable, 16 AWG 2 conductor (9028308) | LF | 12,510 | $2.05 | $2.05 | $2.12 | $2.05 | $2.22 | $2.25 |
| 1920 | Cable, 16 AWG 5 conductor (9028310) | LF | 12,130 | $2.75 | $2.75 | $2.85 | $2.75 | $3.03 | $3.05 |
| 1930 | Pull box, preformed class 1 (9028810) | EACH | 5 | $1,985.00 | $1,985.00 | $2,055.81 | $1,985.00 | $2,183.50 | $2,180.00 |
| 1940 | Pull box, preformed class 2 (9028811) | EACH | 3 | $2,820.00 | $2,820.00 | $2,920.59 | $2,820.00 | $3,102.00 | $3,100.00 |
| 1950 | Pull box, concrete, standard (9028820) | EACH | 2 | $3,405.00 | $3,405.00 | $3,526.46 | $3,405.00 | $3,850.00 | $3,750.00 |
| 1960 | Base, concrete (9029100) | CY | 17.80 | $1,450.00 | $1,450.00 | $1,501.72 | $1,450.00 | $2,475.00 | $1,600.00 |
| 1970 | Misc.adjust pull box (9029902) | EACH | 6 | $1,100.00 | $1,100.00 | $1,139.24 | $1,100.00 | $1,210.00 | $1,210.00 |
| 1980 | Misc.pushbutton extension (9029902) | EACH | 3 | $195.00 | $195.00 | $201.96 | $195.00 | $214.50 | $215.00 |
| 1990 | Misc.remote pushbutton post (9029902) | EACH | 16 | $1,350.00 | $1,350.00 | $1,398.16 | $1,350.00 | $1,485.00 | $1,490.00 |
| 2000 | Misc.retroreflective backplates (9029902) | EACH | 8 | $465.00 | $465.00 | $481.59 | $465.00 | $511.50 | $512.00 |
| 2010 | 2 in. PSST post - 12 GA. (9031270A) | LF | 64 | $11.50 | $11.50 | $11.91 | $11.50 | $12.65 | $12.65 |
| 2020 | Concrete post anchor for 2 in. PSST. - 7 GA. (9031274) | EACH | 4 | $430.00 | $430.00 | $445.34 | $430.00 | $473.00 | $473.00 |
| 2030 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 64 | $12.35 | $12.35 | $12.79 | $12.35 | $13.59 | $13.60 |
| 2040 | Concrete post anchor for 2.5 in. PSST. - 7 GA. (9031285) | EACH | 4 | $445.00 | $445.00 | $460.88 | $445.00 | $486.50 | $490.00 |
| 2050 | SH-flat sheet (9035004A) | SF | 21 | $19.15 | $19.15 | $19.83 | $19.15 | $21.07 | $21.10 |
| 2060 | Removal of improvements (2022010) | LS | 1 | $5,000.00 | $6,067.83 | $4,925.58 | $26,468 | $100,000 | $564.00 |
| 2070 | Misc.linear grading for ADA facilities (2079903) | LF | 3,491 | $25.00 | $11.44 | $24.27 | $24.00 | $6.97 | $74.50 |
| 2080 | Type 1 aggregate for base (4 in. thick) (3040143) | SY | 1,999 | $20.00 | $11.30 | $15.00 | $12.00 | $8.58 | $22.40 |
| 2090 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 1,321 | $20.00 | $11.23 | $15.00 | $11.00 | $8.27 | $23.40 |
| 2100 | Adjusting manhole (6042010) | EACH | 3 | $1,500.00 | $2,299.27 | $1,593.82 | $2,457.00 | $781.20 | $4,270.00 |
| 2110 | Adjusting basin or inlet (6042020) | EACH | 1 | $1,500.00 | $2,299.27 | $2,849.98 | $5,132.00 | $781.20 | $3,120.00 |
| 2120 | Misc.city sanitary manhole adjust to grade (6049902) | EACH | 5 | $1,500.00 | $2,299.26 | $1,483.97 | $9,066.00 | $868.00 | $3,120.00 |
| 2130 | Concrete curb ramp (6081010) | SY | 418 | $125.00 | $218.71 | $230.58 | $197.00 | $150.00 | $201.00 |
| 2140 | Truncated domes (6081012) | SF | 235 | $45.00 | $31.05 | $31.35 | $66.00 | $31.50 | $45.00 |
| 2150 | Paved approach, 8 in. (6085008) | SY | 1,320.80 | $120.00 | $116.11 | $122.27 | $170.00 | $148.13 | $124.00 |
| 2160 | Concrete sidewalk, 4 in. (6086004) | SY | 1,562.30 | $61.00 | $77.55 | $67.00 | $111.00 | $95.00 | $104.00 |
| 2170 | Concrete sidewalk, 8 in. (6086008) | SY | 18.80 | $87.00 | $108.40 | $273.72 | $189.00 | $171.14 | $137.00 |
| 2180 | Concrete curb (6 in. height and under) type S (6091010) | LF | 26 | $95.00 | $66.07 | $163.04 | $83.00 | $33.29 | $128.00 |
| 2190 | Mulching (8025006) | ACRE | 0.30 | $5,000.00 | $400.00 | $2,726.07 | $400.00 | $440.00 | $440.00 |
| 2200 | Turf type tall fescue sodding (8031000A) | SY | 2,130 | $15.00 | $11.25 | $12.08 | $11.25 | $12.38 | $12.40 |
| 2210 | Alternate ditch check (8061006) | LF | 90 | $50.00 | $3.00 | $3.52 | $3.00 | $3.30 | $3.30 |
| 2220 | Curb inlet check (8061007A) | EACH | 38 | $150.00 | $10.00 | $177.44 | $10.00 | $11.00 | $11.00 |
| 2230 | Sediment removal (8061016) | CY | 80 | $10.00 | $39.44 | $98.94 | $25.55 | $27.50 | $217.00 |
| 2240 | Temporary seeding (8061017) | ACRE | 0.30 | $6,000.00 | $400.00 | $3,200.43 | $400.00 | $440.00 | $440.00 |
| 2250 | Silt fence (8061019) | LF | 3,340 | $5.00 | $1.00 | $4.56 | $1.00 | $1.00 | $1.10 |
| 2260 | Signal head, type 1S, pedestrian (9020811) | EACH | 2 | $770.00 | $770.00 | $797.47 | $770.00 | $825.00 | $847.00 |
| 2270 | Post, signal 8 FT. (9022708) | EACH | 1 | $1,550.00 | $1,550.00 | $1,605.29 | $1,550.00 | $1,765.00 | $1,710.00 |
| 2280 | Accessible pedestrian signal (9024921) | EACH | 3 | $985.00 | $985.00 | $1,020.14 | $985.00 | $1,083.00 | $1,080.00 |
| 2290 | Conduit, 3 in., trench with tracer wire (9025300) | LF | 41 | $26.50 | $26.50 | $27.45 | $26.50 | $30.64 | $29.25 |
| 2300 | Cable, 16 AWG 2 conductor (9028308) | LF | 580 | $2.05 | $2.05 | $2.12 | $2.05 | $2.22 | $2.25 |
| 2310 | Cable, 16 AWG 5 conductor (9028310) | LF | 420 | $2.75 | $2.75 | $2.85 | $2.75 | $3.03 | $3.05 |
| 2320 | Pull box, preformed class 1 (9028810) | EACH | 1 | $1,915.00 | $1,915.00 | $1,983.31 | $1,915.00 | $2,183.50 | $2,110.00 |
| 2330 | Pull box, preformed class 2 (9028811) | EACH | 2 | $2,685.00 | $2,685.00 | $2,780.78 | $2,685.00 | $3,102.00 | $2,950.00 |
| 2340 | Base, concrete (9029100) | CY | 0.40 | $1,505.00 | $1,505.00 | $1,558.68 | $1,505.00 | $2,475.00 | $1,660.00 |
| 2350 | Misc.adjust pull box (9029902) | EACH | 7 | $840.00 | $840.00 | $869.96 | $840.00 | $1,210.00 | $924.00 |
| 2360 | Misc.remote pushbutton post (9029902) | EACH | 2 | $1,350.00 | $1,350.00 | $1,398.16 | $1,350.00 | $1,485.00 | $1,490.00 |
| 2370 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 16 | $12.35 | $12.35 | $12.79 | $12.35 | $13.59 | $13.60 |
| 2380 | Concrete post anchor for 2.5 in. PSST. - 7 GA. (9031285) | EACH | 1 | $450.00 | $450.00 | $466.05 | $450.00 | $489.50 | $495.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of September 18, 2026. Compiled by Mirage Metrics.