MoDOT contract 260918-D07 bid tabulation
JCD0214 - ROUTE 50 - MONITEAU COUNTY. Let by Missouri DOT on September 18, 2026, Callaway, Central. 5 bids received; low bid $847,850 by Ti-Zack Concrete, LLC.
- Owner
- Missouri DOT
- Letting
- 18 SEP 2026
- Pay items
- 38
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ti-Zack Concrete, LLC | $847,850 | Low |
| 2 | Capital Paving & Construction, LLC | $1,052,656 | +24% |
| 3 | N.B. West Contracting Company | $1,121,328 | +32% |
| 4 | Watson Concrete, Inc. | $1,355,290 | +60% |
| 5 | Don Schnieders Excavating Company, Inc. | $1,394,556 | +64% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ti-Zack Concrete, LLC | 2. Capital Paving & Construction, LLC | 3. N.B. West Contracting Company | 4. Watson Concrete, Inc. | 5. Don Schnieders Excavating Company, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $36,480 | $115,044 | $62,200 | $116,632 | $107,000 |
| 0020 | Misc.remove and relocate bench & planters (2029901) | LS | 1 | $4,840.00 | $1,219.63 | $2,440.00 | $1,500.00 | $10,000 |
| 0030 | Class 3 excavation (2063000) | CY | 28 | $81.43 | $60.91 | $44.00 | $73.25 | $84.00 |
| 0040 | Misc.linear grading for ADA facilities (2079903) | LF | 2,187 | $2.09 | $15.68 | $11.00 | $21.21 | $34.30 |
| 0050 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 1,807 | $3.81 | $27.40 | $25.00 | $57.10 | $28.35 |
| 0060 | Concrete pavement ( 8 in. non-reinf) (5021108) | SY | 79 | $275.04 | $149.95 | $262.00 | $451.70 | $525.00 |
| 0070 | Misc.adjusting manholes, water valves, and other appurtenances (6049901) | LS | 1 | $456.00 | $14,002 | $7,920.00 | $1,444.35 | $15,000 |
| 0080 | Misc.drop inlet modification (6049902) | EACH | 22 | $414.55 | $2,645.84 | $2,000.00 | $1,453.90 | $2,700.00 |
| 0090 | Concrete median (6081000) | SY | 48.60 | $200.81 | $545.95 | $437.00 | $108.60 | $753.00 |
| 0100 | Concrete curb ramp (6081010) | SY | 713 | $200.81 | $177.30 | $265.00 | $358.50 | $165.00 |
| 0110 | Truncated domes (6081012) | SF | 1,480 | $38.25 | $30.12 | $55.00 | $43.10 | $35.00 |
| 0120 | Paved approach, 8 in. (6085008) | SY | 139 | $275.04 | $153.24 | $290.00 | $270.85 | $273.00 |
| 0130 | Concrete sidewalk, 4 in. (6086004) | SY | 550.10 | $133.41 | $85.28 | $193.00 | $192.70 | $145.00 |
| 0140 | Concrete sidewalk, 7 in. (6086007) | SY | 62.70 | $236.87 | $95.63 | $522.00 | $195.60 | $284.00 |
| 0150 | Integral curb (6 in. height and under) type A (6092011) | LF | 221 | $55.81 | $35.81 | $51.00 | $47.70 | $124.00 |
| 0160 | Misc.type A concrete gutter (modified) with steel plate (6099903) | LF | 18 | $267.87 | $605.14 | $341.00 | $90.50 | $110.00 |
| 0170 | Misc.type B concrete curb and gutter (modified) (6099903) | LF | 583 | $97.05 | $87.78 | $122.00 | $99.00 | $89.00 |
| 0180 | Truck mounted attenuator (TMA) (6123001) | LS | 1 | $1.10 | $1,229.88 | $16,600 | $15,000 | $30,000 |
| 0190 | Misc.temporary traffic control (6169901) | LS | 1 | $14,300 | $32,301 | $13,000 | $15,375 | $13,000 |
| 0200 | Misc.detectable pedestrian channelizer barricade (6169902) | EACH | 6 | $110.00 | $250.00 | $100.00 | $118.25 | $100.00 |
| 0210 | Mobilization (6181000) | LS | 1 | $75,317 | $140,797 | $116,000 | $171,020 | $315,000 |
| 0220 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 3,164 | $19.80 | $20.00 | $20.00 | $19.35 | $18.00 |
| 0230 | Pavement marking removal (6207001) | LF | 2,108 | $3.30 | $2.50 | $3.00 | $3.23 | $3.00 |
| 0240 | Contractor furnished surveying and staking (6274000) | LS | 1 | $60,500 | $34,250 | $20,000 | $36,348 | $25,000 |
| 0250 | 12 in. pipe group C (7250412) | LF | 31 | $170.50 | $133.56 | $149.00 | $159.10 | $81.00 |
| 0260 | 12 in. or allowed substitute group C flared end section (7320812A) | EACH | 4 | $1,925.00 | $284.20 | $1,170.00 | $850.00 | $225.00 |
| 0270 | Misc.seeding and mulching - cool season grasses (8059901) | LS | 1 | $16,500 | $27,739 | $10,000 | $25,000 | $45,000 |
| 0280 | Alternate ditch check (8061006) | LF | 40 | $71.50 | $22.97 | $25.00 | $35.00 | $25.00 |
| 0290 | Curb inlet check (8061007A) | EACH | 26 | $170.50 | $99.54 | $200.00 | $125.00 | $190.00 |
| 0300 | Sediment removal (8061016) | CY | 123 | $1.10 | $68.86 | $43.00 | $86.70 | $20.00 |
| 0310 | Silt fence (8061019) | LF | 2,218 | $5.50 | $4.23 | $4.00 | $4.00 | $5.50 |
| 0320 | Accessible pedestrian signal (9024921) | EACH | 25 | $1,485.00 | $1,350.00 | $1,350.00 | $2,032.25 | $1,890.00 |
| 0330 | Misc.pedestrian push button extension (9029902) | EACH | 7 | $236.50 | $215.00 | $215.00 | $408.60 | $380.00 |
| 0340 | Concrete footings, embedded (9031010) | CY | 0.20 | $2,200.00 | $8,179.32 | $2,000.00 | $430.10 | $2,000.00 |
| 0350 | 2 in. PSST post - 12 GA. (9031270A) | LF | 684 | $16.50 | $19.20 | $15.00 | $17.75 | $15.00 |
| 0360 | Driven post anchor for 2 in. PSST - 12 GA. (9031271A) | EACH | 57 | $220.00 | $168.29 | $200.00 | $236.55 | $200.00 |
| 0370 | SHF-flat sheet fluorescent (9035069A) | SF | 625 | $22.00 | $37.51 | $20.00 | $23.65 | $20.00 |
| 0380 | Misc.relocate sign (9039902) | EACH | 9 | $605.00 | $1,005.25 | $1,000.00 | $865.00 | $1,100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of September 18, 2026. Compiled by Mirage Metrics.