MoDOT contract 260918-D08 bid tabulation
JCD0340 - ROUTE B - DENT COUNTY. Let by Missouri DOT on September 18, 2026, Dent, Central. 6 bids received; low bid $219,812 by H.R. Quadri Contractors, LLC.
- Owner
- Missouri DOT
- Letting
- 18 SEP 2026
- Pay items
- 15
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | H.R. Quadri Contractors, LLC | $219,812 | Low |
| 2 | Gene Haile Excavating, Inc. | $280,048 | +27% |
| 3 | Mera Excavating, LLC | $300,436 | +37% |
| 4 | Courtney Construction, LLC dba Courtney Excavating & Construction | $336,583 | +53% |
| 5 | BuildTec Construction, LLC | $346,793 | +58% |
| 6 | Midwest Mechanical and Welding, LLC | $353,708 | +61% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. H.R. Quadri Contractors, LLC | 2. Gene Haile Excavating, Inc. | 3. Mera Excavating, LLC | 4. Courtney Construction, LLC dba Courtney Excavating & Construction | 5. BuildTec Construction, LLC | 6. Midwest Mechanical and Welding, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Misc.clearing and grubbing (2019901) | LS | 1 | $2,600.00 | $3,500.00 | $2,067.74 | $14,479 | $2,000.00 | $1,000.00 |
| 0020 | Class A excavation (2031000) | CY | 1,630 | $10.00 | $15.00 | $8.52 | $13.32 | $15.00 | $24.00 |
| 0030 | Compacting embankment (2036000) | CY | 33 | $3.00 | $50.00 | $22.18 | $140.70 | $70.00 | $500.00 |
| 0040 | Misc.furnishing and placing class V riprap (6119907) | CY | 2,900 | $55.00 | $67.50 | $75.18 | $70.47 | $95.00 | $70.00 |
| 0050 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $2,000.00 | $1,650.00 | $2,479.11 | $10,450 | $8,000.00 | $4,500.00 |
| 0060 | Mobilization (6181000) | LS | 1 | $15,000 | $28,400 | $21,689 | $29,900 | $7,500.00 | $22,000 |
| 0070 | Additional mobilization for seeding (6181020) | EACH | 4 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0080 | Permanent erosion control geotextile (6240103A) | SY | 1,163 | $3.00 | $3.00 | $3.36 | $7.30 | $5.00 | $15.00 |
| 0090 | Contractor furnished surveying and staking (6274000) | LS | 1 | $4,000.00 | $3,000.00 | $9,308.62 | $3,850.00 | $3,200.00 | $5,500.00 |
| 0100 | Misc.seeding and mulching cool season grasses (8059901) | LS | 1 | $500.00 | $4,235.00 | $9,608.40 | $7,878.19 | $4,500.00 | $6,500.00 |
| 0110 | Alternate ditch check (8061006) | LF | 40 | $15.00 | $2.50 | $23.41 | $87.60 | $3.00 | $45.00 |
| 0120 | Sediment removal (8061016) | CY | 3 | $1.00 | $200.00 | $31.82 | $545.61 | $100.00 | $500.00 |
| 0130 | Silt fence (8061019) | LF | 349 | $4.00 | $1.50 | $4.04 | $7.60 | $2.00 | $7.00 |
| 0140 | Surface preparation for applying epoxy-mastic primer (7125102) | LS | 1 | $6,000.00 | $5,300.00 | $6,946.10 | $16,500 | $5,500.00 | $14,000 |
| 0150 | Aluminum epoxy-mastic primer (7125960) | LS | 1 | $5,925.00 | $5,000.00 | $6,946.10 | $4,125.00 | $4,500.00 | $16,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of September 18, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.