MoDOT contract 260918-B02 bid tabulation
JNE0024, JNE0254 - ROUTE 11, 6 - ADAIR, KNOX, LINN, AND SULLIVAN COUNTIES. Let by Missouri DOT on September 18, 2026, Adair, Northeast. 5 bids received; low bid $4,324,043 by W. L. Miller Company.
- Owner
- Missouri DOT
- Letting
- 18 SEP 2026
- Pay items
- 23
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | W. L. Miller Company | $4,324,043 | Low |
| 2 | Emery Sapp & Sons, Inc. | $4,708,627 | +9.0% |
| 3 | Herzog Contracting Corp. | $5,145,313 | +19% |
| 4 | Magruder Paving, LLC | $5,752,502 | +33% |
| 5 | Capital Paving & Construction, LLC | $6,208,866 | +44% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. W. L. Miller Company | 2. Emery Sapp & Sons, Inc. | 3. Herzog Contracting Corp. | 4. Magruder Paving, LLC | 5. Capital Paving & Construction, LLC |
|---|---|---|---|---|---|---|---|---|
| 0010 | Misc.perm. aggr. edge treatment (3049910) | TON | 6,543.50 | $35.70 | $42.70 | $45.00 | $69.74 | $50.73 |
| 0020 | Gravel (A) or crushed stone (B) (3105002) | TON | 999 | $95.00 | $51.15 | $45.00 | $69.74 | $74.98 |
| 0030 | Bituminous pavement mixture PG58-28H (surface leveling) (4020521) | TON | 38,987.20 | $88.05 | $96.50 | $100.50 | $115.07 | $125.05 |
| 0040 | Tack coat (4071005) | GAL | 44,030 | $3.00 | $2.80 | $3.00 | $3.85 | $2.79 |
| 0050 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 2 | $2,500.00 | $2,700.00 | $2,280.00 | $3,000.00 | $3,807.02 |
| 0060 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $20,821 | $22,200 | $30,440 | $21,994 | $20,821 |
| 0070 | Mobilization (6181000) | LS | 1 | $91,500 | $115,000 | $250,000 | $156,150 | $254,518 |
| 0080 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 443,956 | $0.12 | $0.13 | $0.13 | $0.12 | $0.12 |
| 0090 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 360,357 | $0.12 | $0.13 | $0.13 | $0.12 | $0.12 |
| 0100 | Modified coldmilling (depth transitions) (6224010) | SY | 3,874 | $11.13 | $5.60 | $35.47 | $16.81 | $35.30 |
| 0110 | Gravel (A) or crushed stone (B) (3105002) | TON | 14 | $125.00 | $205.00 | $743.92 | $226.29 | $351.13 |
| 0120 | Bituminous pavement mixture PG64-22, (BP-3) (4011213) | TON | 1,238.50 | $91.00 | $111.80 | $123.00 | $127.20 | $162.98 |
| 0130 | Tack coat - non-tracking (4071007) | GAL | 1,658 | $3.00 | $4.25 | $3.75 | $3.85 | $4.47 |
| 0140 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $4,378.00 | $4,700.00 | $4,785.00 | $5,778.00 | $4,378.00 |
| 0150 | Mobilization (6181000) | LS | 1 | $7,200.00 | $30,388 | $11,500 | $18,000 | $17,141 |
| 0160 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 42 | $30.00 | $32.00 | $35.00 | $30.00 | $30.00 |
| 0170 | Preformed thermoplastic pavement marking, left/right arrow (6200021) | EACH | 1 | $400.00 | $485.00 | $525.00 | $400.00 | $400.00 |
| 0180 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 5,550 | $0.50 | $0.55 | $0.37 | $0.50 | $0.50 |
| 0190 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 3,040 | $1.00 | $1.10 | $0.37 | $1.00 | $1.00 |
| 0200 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 5,366 | $4.55 | $4.00 | $4.62 | $2.74 | $6.87 |
| 0210 | Coldmilling bituminous pavement for removal of surfacing (greater than 3 in. thick) (6221003) | SY | 112 | $4.55 | $18.00 | $34.35 | $15.86 | $22.09 |
| 0220 | Coldmilling concrete pavement for removal of surface (6221011) | SY | 80 | $7.00 | $25.00 | $22.79 | $21.67 | $30.92 |
| 0230 | Modified coldmilling (depth transitions) (6224010) | SY | 752 | $12.90 | $8.70 | $10.29 | $11.14 | $3.47 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of September 18, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.