MoDOT contract 250516-D03 bid tabulation
2 Bridge deck replacements. Let by Missouri DOT on May 16, 2025, Maries, Central. 7 bids received; low bid $2,167,455 by Louis-Company, LLC.
- Owner
- Missouri DOT
- Letting
- 16 MAY 2025
- Pay items
- 88
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Louis-Company, LLC | $2,167,455 | Low |
| 2 | E & C Bridge, LLC | $2,479,915 | +14% |
| 3 | S & A Equipment & Builders, LLC | $2,510,699 | +16% |
| 4 | West Plains Bridge & Grading, LLC | $2,947,500 | +36% |
| 5 | Gene Haile Excavating, Inc. | $2,979,204 | +37% |
| 6 | Kozeny-Wagner, Inc. | $3,289,000 | +52% |
| 7 | Don Schnieders Excavating Company, Inc. | $3,733,957 | +72% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Louis-Company, LLC | 2. E & C Bridge, LLC | 3. S & A Equipment & Builders, LLC | 4. West Plains Bridge & Grading, LLC | 5. Gene Haile Excavating, Inc. | 6. Kozeny-Wagner, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Signet dbe reporting (1081000) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $12,825 | $25,000 | $32,849 | $37,000 | $25,000 | $36,981 |
| 0030 | Shaping slopes, class III (2153000) | 100F | 18 | $1,938.09 | $1,600.00 | $311.81 | $1,675.00 | $1,250.00 | $1,500.00 |
| 0040 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 344 | $7.68 | $16.50 | $11.20 | $23.00 | $15.00 | $19.00 |
| 0050 | Bituminous pavement mixture PG64-22, (BP-1) (4011209) | TON | 90 | $288.29 | $238.00 | $310.74 | $238.00 | $341.00 | $238.00 |
| 0060 | Bituminous pavement mixture PG64-22 (base) (4013000) | TON | 88 | $284.66 | $235.00 | $245.58 | $235.00 | $270.00 | $235.00 |
| 0070 | Tack coat (4071005) | GAL | 83 | $4.54 | $3.75 | $5.01 | $3.75 | $6.00 | $3.75 |
| 0080 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 5 | $3,876.19 | $4,000.00 | $4,009.52 | $4,000.00 | $4,400.00 | $4,000.00 |
| 0090 | Misc.temporary traffic control (6169901) | LS | 1 | $12,210 | $7,608.00 | $7,626.11 | $7,608.00 | $8,250.00 | $7,608.00 |
| 0100 | Mobilization (6181000) | LS | 1 | $60,000 | $193,500 | $132,953 | $166,878 | $300,000 | $237,334 |
| 0110 | 4 in. white standard waterborne pavement marking paint, type P beads (6206000C) | LF | 2,300 | $1.21 | $1.00 | $1.00 | $1.00 | $2.00 | $1.00 |
| 0120 | 4 in. yellow standard waterborne pavement marking paint, type P beads (6206001C) | LF | 146 | $1.21 | $1.00 | $1.00 | $1.00 | $2.00 | $1.00 |
| 0130 | Temporary raised pavement marker (6208064A) | EACH | 80 | $7.27 | $6.00 | $6.01 | $6.00 | $8.00 | $6.00 |
| 0140 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 490 | $23.62 | $19.50 | $22.05 | $19.50 | $25.00 | $19.50 |
| 0150 | Bituminous shoulder rumble strip (6261000A) | STA | 15.50 | $146.57 | $121.00 | $783.11 | $121.00 | $260.00 | $395.00 |
| 0160 | Bituminous centerline rumble strip (6261001) | STA | 2.10 | $2,005.46 | $358.00 | $783.11 | $358.00 | $550.00 | $663.00 |
| 0170 | Contractor furnished surveying and staking (6274000) | LS | 1 | $9,690.47 | $2,500.00 | $8,019.05 | $12,500 | $4,000.00 | $7,134.00 |
| 0180 | Mulching (8025006) | ACRE | 1 | $2,180.35 | $3,300.00 | $1,804.29 | $1,800.00 | $2,000.00 | $3,300.00 |
| 0190 | Seeding - cool season grasses (8051000A) | ACRE | 1 | $3,936.75 | $3,600.00 | $3,257.74 | $3,250.00 | $3,750.00 | $3,600.00 |
| 0200 | Sediment removal (8061016) | CY | 18 | $237.49 | $10.00 | $28.77 | $6.00 | $20.00 | $25.00 |
| 0210 | Silt fence (8061019) | LF | 1,740 | $3.63 | $2.90 | $3.01 | $3.00 | $3.50 | $2.90 |
| 0220 | MGS guardrail (6061060) | LF | 825 | $35.13 | $28.00 | $30.51 | $30.44 | $34.00 | $30.44 |
| 0230 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 8 | $5,087.50 | $4,200.00 | $3,708.81 | $3,700.08 | $4,100.00 | $3,700.08 |
| 0240 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 8 | $4,602.97 | $3,800.00 | $3,297.63 | $3,289.80 | $3,600.00 | $3,289.80 |
| 0250 | Misc.dewatering (2069901) | LS | 1 | $14,340 | $5,000.00 | $3,342.42 | $9,700.00 | $15,000 | $23,442 |
| 0260 | Removal of existing bridge deck (2162500) | SF | 6,439 | $9.00 | $8.00 | $7.17 | $18.00 | $8.00 | $24.00 |
| 0270 | Class B-1 concrete (substructure) (7034003) | CY | 27.70 | $865.00 | $1,400.00 | $1,497.18 | $1,065.00 | $1,250.00 | $1,415.00 |
| 0280 | Slab on steel (7034212) | SY | 744 | $290.57 | $400.00 | $357.17 | $489.00 | $425.00 | $469.00 |
| 0290 | Type D barrier (7034219A) | LF | 467 | $137.76 | $110.00 | $92.22 | $135.00 | $86.00 | $135.00 |
| 0300 | Reinforcing steel (bridges) (7061060) | LB | 2,250 | $0.79 | $1.75 | $11.94 | $5.00 | $5.00 | $3.00 |
| 0310 | Slab drain (7123610) | EACH | 24 | $371.85 | $400.00 | $483.13 | $600.00 | $550.00 | $415.00 |
| 0320 | Surface preparation for applying epoxy-mastic primer (7125102) | LS | 1 | $12,113 | $3,007.54 | $7,217.14 | $3,007.54 | $8,000.00 | $7,152.25 |
| 0330 | Gray epoxy-mastic primer (7125961) | LS | 1 | $9,690.47 | $1,288.95 | $3,307.14 | $1,288.95 | $8,000.00 | $7,152.25 |
| 0340 | Non-destructive testing (7126000) | LF | 60 | $115.07 | $25.00 | $95.23 | $95.00 | $50.00 | $95.00 |
| 0350 | Misc.dewatering (2069901) | LS | 1 | $12,000 | $5,000.00 | $2,488.78 | $4,750.00 | $15,000 | $23,441 |
| 0360 | Removal of existing bridge deck (2162500) | SF | 3,920 | $8.86 | $8.00 | $10.60 | $21.00 | $12.00 | $32.00 |
| 0370 | Class B-1 concrete (substructure) (7034003) | CY | 27.60 | $863.36 | $1,400.00 | $1,630.80 | $1,060.00 | $1,250.00 | $1,297.00 |
| 0380 | Slab on steel (7034212) | SY | 470 | $336.36 | $425.00 | $506.74 | $545.00 | $485.00 | $574.00 |
| 0390 | Type D barrier (7034219A) | LF | 295 | $154.89 | $115.00 | $109.26 | $155.00 | $96.00 | $150.00 |
| 0400 | Reinforcing steel (bridges) (7061060) | LB | 2,250 | $0.82 | $1.75 | $14.38 | $5.00 | $5.00 | $3.00 |
| 0410 | Shear connectors (7121159) | EACH | 2,192 | $6.47 | $8.75 | $14.96 | $9.00 | $12.00 | $5.50 |
| 0420 | Slab drain (7123610) | EACH | 26 | $345.20 | $390.00 | $442.07 | $550.00 | $475.00 | $387.00 |
| 0430 | Surface preparation for applying epoxy-mastic primer (7125102) | LS | 1 | $12,113 | $3,289.50 | $6,014.29 | $3,289.50 | $6,000.00 | $5,117.94 |
| 0440 | Gray epoxy-mastic primer (7125961) | LS | 1 | $9,690.47 | $1,409.78 | $2,004.76 | $1,409.78 | $6,000.00 | $5,117.94 |
| 0450 | Non-destructive testing (7126000) | LF | 19 | $187.75 | $35.00 | $155.37 | $155.00 | $100.00 | $155.00 |
| 0460 | Removal of improvements (2022010) | LS | 1 | $15,888 | $25,000 | $17,680 | $11,000 | $25,000 | $17,314 |
| 0470 | Bituminous pavement mixture PG64-22, (BP-1) (4011209) | TON | 53 | $328.26 | $271.00 | $491.17 | $271.00 | $540.00 | $271.00 |
| 0480 | Tack coat (4071005) | GAL | 49 | $4.54 | $3.75 | $5.01 | $3.75 | $6.00 | $3.75 |
| 0490 | Furnishing type 2 rock blanket (6113020) | CY | 405 | $81.35 | $55.00 | $84.88 | $65.00 | $68.00 | $63.00 |
| 0500 | Placing type 2 rock blanket (6113040) | CY | 405 | $35.06 | $25.00 | $30.31 | $33.00 | $20.00 | $19.00 |
| 0510 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 6 | $3,876.19 | $4,000.00 | $4,009.52 | $4,000.00 | $4,500.00 | $4,000.00 |
| 0520 | Misc.temporary traffic control (6169901) | LS | 1 | $9,514.83 | $7,031.00 | $7,047.74 | $7,031.00 | $8,000.00 | $7,031.00 |
| 0530 | Mobilization (6181000) | LS | 1 | $68,000 | $193,500 | $130,748 | $122,500 | $300,000 | $179,922 |
| 0540 | 4 in. white standard waterborne pavement marking paint, type P beads (6206000C) | LF | 2,186 | $1.21 | $1.00 | $1.00 | $1.00 | $2.00 | $1.00 |
| 0550 | 4 in. yellow standard waterborne pavement marking paint, type P beads (6206001C) | LF | 273 | $1.21 | $1.00 | $1.00 | $1.00 | $2.00 | $1.00 |
| 0560 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 489 | $23.62 | $19.50 | $25.06 | $19.50 | $27.50 | $19.50 |
| 0570 | Permanent erosion control geotextile (6240103A) | SY | 813 | $1.62 | $3.00 | $13.17 | $3.50 | $4.00 | $3.00 |
| 0580 | Contractor furnished surveying and staking (6274000) | LS | 1 | $9,690.47 | $1,500.00 | $8,019.05 | $10,000 | $5,000.00 | $7,133.00 |
| 0590 | Mulching (8025006) | ACRE | 1 | $2,180.35 | $3,300.00 | $1,804.29 | $1,800.00 | $2,000.00 | $3,300.00 |
| 0600 | Seeding - cool season grasses (8051000A) | ACRE | 1 | $3,936.75 | $3,600.00 | $3,257.74 | $3,250.00 | $3,750.00 | $3,600.00 |
| 0610 | Sediment removal (8061016) | CY | 10 | $190.15 | $10.00 | $51.78 | $6.00 | $20.00 | $25.00 |
| 0620 | Silt fence (8061019) | LF | 700 | $3.63 | $2.90 | $3.51 | $3.50 | $3.75 | $2.90 |
| 0630 | Type C berm (8061050) | LF | 620 | $60.57 | $15.00 | $6.87 | $40.50 | $15.00 | $35.00 |
| 0640 | U-channel post, 3 LB (9031250A) | LF | 336 | $31.49 | $32.00 | $23.78 | $20.00 | $27.00 | $23.72 |
| 0650 | SHF-flat sheet fluorescent (9035069A) | SF | 72 | $42.40 | $28.00 | $84.33 | $25.00 | $93.00 | $84.13 |
| 0660 | Removal of miscellaneous acm (non-friable) (2024043) | SF | 16 | $423.96 | $350.00 | $350.83 | $350.00 | $450.00 | $491.00 |
| 0670 | Removal of existing bridge deck (2162500) | SF | 5,226 | $9.00 | $8.00 | $8.25 | $15.05 | $12.00 | $26.00 |
| 0680 | Bridge approach slab (minor road) (5031011A) | SY | 118 | $312.42 | $200.00 | $250.60 | $275.00 | $275.00 | $254.00 |
| 0690 | Slab on steel (7034212) | SY | 579 | $310.10 | $425.00 | $447.72 | $525.00 | $450.00 | $511.00 |
| 0700 | Type D barrier (7034219A) | LF | 363 | $147.81 | $115.00 | $100.24 | $140.00 | $92.00 | $144.00 |
| 0710 | Protective coating - concrete bents and piers (epoxy) (7110200) | LS | 1 | $8,479.16 | $4,236.96 | $6,014.29 | $4,236.96 | $9,000.00 | $7,950.00 |
| 0720 | Slab drain (7123610) | EACH | 32 | $345.20 | $400.00 | $486.20 | $560.00 | $475.00 | $388.00 |
| 0730 | Surface preparation for applying epoxy-mastic primer (7125102) | LS | 1 | $12,113 | $7,832.14 | $32,076 | $7,832.14 | $4,000.00 | $3,518.00 |
| 0740 | Gray epoxy-mastic primer (7125961) | LS | 1 | $9,690.47 | $3,356.63 | $11,026 | $3,356.63 | $4,000.00 | $3,518.00 |
| 0750 | Non-destructive testing (7126000) | LF | 50 | $84.79 | $30.00 | $70.17 | $70.00 | $50.00 | $70.00 |
| 0760 | Removal of miscellaneous acm (non-friable) (2024043) | SF | 21 | $423.96 | $350.00 | $350.83 | $350.00 | $450.00 | $469.00 |
| 0770 | Misc.dewatering (2069901) | LS | 1 | $20,000 | $5,000.00 | $2,488.78 | $4,750.00 | $15,000 | $19,523 |
| 0780 | Removal of existing bridge deck (2162500) | SF | 6,723 | $5.38 | $8.00 | $7.74 | $13.65 | $12.00 | $21.50 |
| 0790 | Bridge approach slab (minor road) (5031011A) | SY | 118 | $281.60 | $200.00 | $250.60 | $275.00 | $275.00 | $254.00 |
| 0800 | Class B-1 concrete (substructure) (7034003) | CY | 14.40 | $1,300.00 | $1,400.00 | $1,923.03 | $1,100.00 | $2,000.00 | $1,525.00 |
| 0810 | Slab on steel (7034212) | SY | 745 | $277.21 | $400.00 | $278.17 | $495.00 | $425.00 | $472.00 |
| 0820 | Type D barrier (7034219A) | LF | 467 | $137.09 | $110.00 | $92.22 | $130.00 | $86.00 | $135.00 |
| 0830 | Reinforcing steel (bridges) (7061060) | LB | 1,220 | $0.79 | $2.00 | $11.13 | $5.00 | $8.00 | $4.00 |
| 0840 | Protective coating - concrete bents and piers (epoxy) (7110200) | LS | 1 | $8,479.16 | $4,236.96 | $6,014.29 | $4,236.96 | $9,500.00 | $8,310.00 |
| 0850 | Slab drain (7123610) | EACH | 44 | $371.85 | $400.00 | $419.14 | $610.00 | $550.00 | $517.00 |
| 0860 | Surface preparation for applying epoxy-mastic primer (7125102) | LS | 1 | $12,113 | $7,832.14 | $46,611 | $7,832.14 | $4,500.00 | $3,795.00 |
| 0870 | Gray epoxy-mastic primer (7125961) | LS | 1 | $9,690.47 | $3,356.63 | $15,537 | $3,356.63 | $4,500.00 | $3,795.00 |
| 0880 | Non-destructive testing (7126000) | LF | 56 | $78.74 | $25.00 | $65.15 | $65.00 | $45.00 | $65.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of May 16, 2025. Compiled by Mirage Metrics.