MoDOT contract 250221-D02 bid tabulation

J5S3533 - ROUTES OR I-44 - CRAWFORD COUNTY. Let by Missouri DOT on February 21, 2025, Crawford, Central. 5 bids received; low bid $579,283 by E & C Bridge, LLC.

Owner
Missouri DOT
Letting
21 FEB 2025
Pay items
35
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1E & C Bridge, LLC$579,283Low
2Kozeny-Wagner, Inc.$739,000+28%
3Concrete Strategies, LLC$883,775+53%
4Widel, Inc.$958,090+65%
5Plattin Creek Excavating, LLC dba PCX Construction, LLC$1,129,359+95%
MoDOT contract 250221-D02: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. E & C Bridge, LLC2. Kozeny-Wagner, Inc.3. Concrete Strategies, LLC4. Widel, Inc.5. Plattin Creek Excavating, LLC dba PCX Construction, LLC
0010Signet dbe reporting (1081000)LS1$1,000.00$1,000.00$1,000.00$1,000.00$1,000.00
0020Removal of improvements (2022010)LS1$15,000$12,648$2,362.90$10,500$2,100.00
0030Shaping slopes, class III (2153000)100F4$1,400.00$1,400.00$1,496.53$900.00$1,400.00
0040Bituminous pavement mixture PG64-22, (BP-1) (4011209)TON27$500.00$500.00$534.47$600.00$500.00
0050Tack coat (4071005)GAL24$78.00$3.25$3.47$4.00$3.25
0060Furnishing type 2 rock blanket (6113020)CY303$50.00$69.00$75.19$105.00$63.00
0070Placing type 2 rock blanket (6113040)CY303$30.00$25.00$23.66$20.00$100.00
0080Construction signs (6161005)SF109$10.00$10.00$10.69$11.00$10.00
0090Advanced warning rail system (6161008)EACH2$60.00$60.00$64.14$69.00$60.00
0100Type III moveable barricade (6161030)EACH10$125.00$125.00$133.62$144.00$125.00
0110Changeable message sign without communication interface, contractor furnished, contractor retained (6161098A)EACH2$2,500.00$2,500.00$2,672.37$2,800.00$2,500.00
0120Mobilization (6181000)LS1$85,000$73,000$190,600$115,000$111,000
01304 in. white standard waterborne pavement marking paint, type P beads (6206000C)LF575$0.50$0.50$0.53$0.60$0.50
01404 in. yellow standard waterborne pavement marking paint, type P beads (6206001C)LF72$0.50$0.50$0.53$0.60$0.50
0150Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001)SY244$8.00$8.00$8.55$9.00$8.00
0160Permanent erosion control geotextile (6240103A)SY624$3.00$2.50$5.46$3.00$3.00
0170Mulching (8025006)ACRE0.30$3,000.00$3,200.00$3,420.64$26,000$3,000.00
0180Seeding - cool season grasses (8051000A)ACRE0.30$3,450.00$6,900.00$7,375.75$11,000$3,450.00
0190Rock ditch check (8061005)LF80$16.00$27.00$28.86$7.50$16.00
0200Sediment removal (8061016)CY11$15.00$25.00$333.66$80.00$100.00
0210Silt fence (8061019)LF262$4.00$6.50$6.95$7.00$4.00
0220MGS bridge approach transition section (regular/no curb) (6061069)EACH4$4,000.00$4,000.00$4,275.80$4,500.00$4,000.00
0230Type A crashworthy end terminal (MASH) (6063014)EACH4$3,800.00$3,800.00$4,062.01$4,300.00$3,800.00
0240Removal of miscellaneous acm (non-friable) (2024043)SF13$375.00$375.00$400.86$500.00$375.00
0250Removal of existing bridge deck (2162500)SF4,242$10.00$32.00$18.37$15.00$28.00
0260Bridge approach slab (minor road) (5031011A)SY118$250.00$200.00$205.24$225.00$400.00
0270Slab on steel (7034212)SY470$400.00$482.00$647.03$450.00$1,150.00
0280Type D barrier (7034219A)LF294$120.00$180.00$165.58$210.00$305.00
0290Protective coating - concrete bents and piers (epoxy) (7110200)LS1$6,000.00$6,000.00$6,413.70$12,000$6,000.00
0300Slab drain (7123610)EACH22$300.00$575.00$563.22$420.00$330.00
0310Surface preparation for overcoating structural steel (system G) (7125201)SF3,600$15.50$15.50$16.57$26.00$15.50
0320Intermediate field coat (system G) (7125365A)SF3,600$3.00$3.00$3.21$43.00$3.00
0330Finish field coat (system G) (7125370A)SF1,000$2.00$2.00$2.14$62.00$2.00
0340Non-destructive testing (7126000)LF52$30.00$25.00$108.31$31.00$25.00
0350Vertical drain at end bents (7151001)EACH2$1,500.00$11,400$11,618$4,100.00$7,170.00
MoDOT contract 250221-D02: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of February 21, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy