MoDOT bidders

The 98 firms with at least 10 bids on Missouri DOT contracts in the data, one of them since 2022. Each page shows the firm's bids, low bids, gap to the low bid, regions and the pay items it is most often lowest on.

Owner
Missouri DOT
Firms with a page
98
Data through
16 OCT 2026
Source
MoDOT tabulations

Firms by number of bids

BidderBidsLow bidsWin rateLatest bid
Emery Sapp & Sons, Inc.53612624%16 OCT 2026
Capital Paving & Construction, LLC38810828%16 OCT 2026
Pace Construction Company, LLC26110139%16 OCT 2026
N.B. West Contracting Company1796838%16 OCT 2026
Blevins Asphalt Construction Company, Inc.1367958%16 OCT 2026
Phillips Hardy, Inc.1262520%18 OCT 2024
Magruder Paving, LLC1234537%16 OCT 2026
Collins & Hermann, Inc.1144640%18 SEP 2026
APAC-Central, Inc.1114137%16 OCT 2026
Ideker, Inc.964446%18 SEP 2026
Louis-Company, LLC892427%16 OCT 2026
Robertson Contractors, Inc.832429%18 JUN 2026
Apex Paving Co.834352%15 MAY 2026
Radmacher Brothers Excavating Co., Inc.811519%16 OCT 2026
Lehman Construction, LLC802126%17 MAR 2023
Superior Bowen Asphalt Company, LLC771925%18 SEP 2026
E & C Bridge, LLC763141%16 OCT 2026
Concrete Strategies, LLC742432%18 SEP 2026
Missouri Petroleum Products Company, LLC741723%17 JAN 2025
Gershenson Construction Co., Inc.731419%16 OCT 2026
Vance Brothers, Inc.733244%16 OCT 2026
Gene Haile Excavating, Inc.712434%16 OCT 2026
KCI Construction Company702029%16 OCT 2026
Don Schnieders Excavating Company, Inc.651218%18 SEP 2026
Mera Excavating, LLC641219%16 OCT 2026
Above And Below Contracting, LLC63711%18 SEP 2026
Hartman and Company, Inc.633352%16 OCT 2026
Herzog Contracting Corp.624369%18 SEP 2026
Widel, Inc.582340%16 OCT 2026
Kozeny-Wagner, Inc.571425%18 SEP 2026
S & A Equipment & Builders, LLC571526%14 NOV 2025
Joe's Bridge & Grading, Inc.562341%18 JUN 2026
R. V. Wagner, Inc.541833%15 MAY 2026
Putz Construction, LLC531936%18 JUN 2026
CSD Environmental Services, Inc.531223%17 APR 2026
West Plains Bridge & Grading, LLC511224%16 OCT 2026
RL Persons Construction, Inc.5148%15 MAY 2026
Leavenworth Excavating & Equipment Company, Inc.502244%15 MAY 2026
James H. Drew Corporation491429%18 SEP 2026
Comanche Construction, Inc.441227%18 SEP 2026
H.R. Quadri Contractors, LLC442659%18 SEP 2026
Branco Enterprises, Inc.411332%18 SEP 2026
Gerstner Electric, Inc.412561%16 OCT 2026
W. L. Miller Company382155%18 SEP 2026
Realm Construction Inc.362261%18 SEP 2026
Clarkson Construction Company361644%15 MAY 2026
Hardy Construction, LLC34412%16 OCT 2026
Meyer Electric Company, Inc.33515%16 OCT 2026
Fronabarger Concreters, Inc.33927%15 MAY 2026
J M Scheidle, LLC331030%16 MAY 2025
Ti-Zack Concrete, LLC331133%18 SEP 2026
Reinhold Electric, Inc.301033%15 MAY 2026
Christensen Construction Co.301447%16 OCT 2026
Plattin Creek Excavating, LLC dba PCX Construction, LLC30310%12 DEC 2025
Mar-Jim Contracting, LLC291138%18 JUN 2026
STF, LLC dba Traffic Control Company271452%16 MAY 2025
Lamke Trenching & Excavating, Inc.26519%16 OCT 2026
D & E Plumbing and Heating, Inc.261142%16 OCT 2026
Bleigh Construction Company261142%12 DEC 2025
West Plains Bridge & Grading, LLC dba West Plains Bridge & Grading23730%19 MAY 2023
Byrne & Jones Enterprises, Inc. dba Byrne & Jones Construction23417%16 OCT 2026
Penzel Construction Company, Inc.22627%18 JUN 2026
Thomas Industrial Coatings, Inc.21210%16 OCT 2026
TraMar Contracting, Inc.21733%16 JAN 2026
BMC Enterprises, Inc. dba Missouri Petroleum Products Company20315%16 OCT 2026
Omega Coatings & Construction, LLC19632%16 OCT 2026
Amino Bros. Co., Inc.19526%18 SEP 2026
Southern Road & Bridge, LLC19211%16 OCT 2026
Olympus Painting Contractors, Inc.19211%16 OCT 2026
PCiRoads, LLC18422%16 OCT 2026
Parking Lot Maintenance, LLC171165%18 SEP 2026
Cale Seymour Construction, LLC17635%20 JUN 2025
Magruder Construction Co., Inc.17318%20 MAR 2026
Millstone Weber, LLC17424%18 JUN 2026
Sprouls Construction, Inc.1616%15 MAY 2026
Capital Electric Line Builders, Inc.16744%15 MAY 2026
AAD Contracting, Inc.161275%18 SEP 2026
K.J.U., Inc. dba K.J. Unnerstall Construction Co.16425%16 OCT 2026
Amino Brothers Co. Inc.15427%15 MAR 2024
Hunter Chase & Associates, Inc.15640%18 SEP 2026
R.A. Knapp Construction, Inc.1400%17 OCT 2025
Fahrner Asphalt Sealers, LLC1417%18 JUN 2026
Pavement Solutions, LLC14214%17 APR 2026
MegaKC Corporation1417%17 APR 2026
The Truesdell Corporation of Wisconsin, Inc.dba Truesdell Corporation14643%18 SEP 2026
Iowa Civil Contracting, Inc.13215%18 JUN 2026
Gunter Construction Company12325%17 APR 2026
Willard Asphalt Paving, Inc.121083%17 OCT 2025
North Central Bridge, LLC12433%21 JUN 2024
Young's General Contracting, Inc.12217%15 AUG 2025
Courtney Construction, LLC dba Courtney Excavating & Construction12325%18 SEP 2026
Hessling Construction, Inc.1119%17 OCT 2025
L. G. Barcus and Sons, Inc.1119%08 JUL 2024
Microsurfacing Contractors, LLC10330%18 OCT 2024
International Rigging Group, LLC10660%16 OCT 2026
Heartland Traffic Services, Inc.10330%16 JAN 2026
Aplex, Inc.10220%16 OCT 2026
America's Parking Remarking, LLC10220%17 APR 2026
MoDOT bidders with a page, by number of bids in the data

A firm's low bid is the lowest total on a contract, as ranked by MoDOT. Bids that did not match their published total are left out. Every firm, with any number of bids, is in the competitor view of the MoDOT explorer.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy