Blevins Asphalt Construction Company, Inc.: MoDOT bid record
Blevins Asphalt Construction Company, Inc. submitted 136 bids on Missouri DOT contracts in the data, from 17 JAN 2020 to 16 OCT 2026, and was the low bidder on 79 of them (58%). When it was not low, its total sat a median +9.0% above the low bid.
- Owner
- Missouri DOT
- Low bid volume
- $125,166,854
- Latest bid
- 16 OCT 2026
- Data through
- 16 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 23 | 14 | 61% |
| 2021 | 17 | 10 | 59% |
| 2022 | 23 | 16 | 70% |
| 2023 | 14 | 6 | 43% |
| 2024 | 29 | 17 | 59% |
| 2025 | 18 | 10 | 56% |
| 2026 | 12 | 6 | 50% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Southwest | 79 | 47 | 59% |
| Central | 35 | 24 | 69% |
| St. Louis | 13 | 5 | 38% |
| Northeast | 6 | 0 | 0% |
| Southeast | 3 | 3 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Tack coat | 4071005 | GAL | 87 | 73 (84%) | $2.45 | $2.90 |
| 4 in. white standard waterborne pavement marking paint, type P beads | 6206000C | LF | 128 | 52 (41%) | $0.13 | $0.20 |
| Emulsified asphalt, seal coat | 4091048 | GAL | 118 | 52 (44%) | $2.50 | $2.75 |
| Seal coat aggregate, grade B2 | 4094012 | SY | 60 | 52 (87%) | $0.81 | $1.00 |
| Bituminous pavement mixture PG64-22 (surface leveling) | 4020520 | TON | 72 | 44 (61%) | $74.30 | $88.05 |
| Construction signs | 6161005 | SF | 128 | 39 (30%) | $6.33 | $7.00 |
| 4 in. yellow standard waterborne pavement marking paint, type P beads | 6206001C | LF | 85 | 28 (33%) | $0.13 | $0.25 |
| Preformed thermoplastic pavement marking, 24 in. white | 6200015 | LF | 103 | 27 (26%) | $25.03 | $23.50 |
| Channelizer (trim line) | 6161025 | EACH | 111 | 23 (21%) | $12.15 | $18.00 |
| Seal coat aggregate, grade B1 | 4094011 | SY | 23 | 23 (100%) | $0.84 | $6.85 |
| Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) | 6221001 | SY | 72 | 22 (31%) | $2.80 | $4.00 |
| Temporary short-term rumble strips | 6162004 | EACH | 45 | 19 (42%) | $816.50 | $1,213.35 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| APAC-Central, Inc. | 64 | 25 of 64 |
| Vance Brothers, Inc. | 45 | 9 of 45 |
| Missouri Petroleum Products Company, LLC | 43 | 9 of 43 |
| Emery Sapp & Sons, Inc. | 37 | 7 of 37 |
| N.B. West Contracting Company | 25 | 11 of 25 |
| Capital Paving & Construction, LLC | 24 | 5 of 24 |
| BMC Enterprises, Inc. dba Missouri Petroleum Products Company | 11 | 4 of 11 |
| W. L. Miller Company | 7 | 3 of 7 |
| Hutchens Construction Company, LLC | 5 | 2 of 5 |
| Leo Journagan Construction Co., Inc. | 5 | 0 of 5 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 16 OCT 2026 | 261016-B06 | Northeast | JNE0259 - ROUTE 94 - MONTGOMERY COUNTY | 2 of 4 | $355,895 | +9.0% |
| 16 OCT 2026 | 261016-D05 | Central | JCD0205 - ROUTE CC, M - MONITEAU, MILLER COUNTIES | 2 of 3 | $695,000 | +3.0% |
| 18 SEP 2026 | 260918-B01 | Northeast | JNE0112 - ROUTE J - AUDRAIN COUNTY | 3 of 5 | $686,105 | +15% |
| 18 JUN 2026 | 260618-G01 | Southwest | JSRM0124 - VARIOUS ROUTES - BATES, BENTON, DALLAS COUNTIES | 1 of 2 | $2,555,978 | Low, 35% under the second |
| 15 MAY 2026 | 260515-H6A | Southeast | J9S3803, J9S3804, J9S3805 - ROUTE B, V, A - TEXAS, WRIGHT, SHANON COUNTIES | 1 of 3 | $4,460,000 | Low, 21% under the second |
| 15 MAY 2026 | 260515-H6B | Southeast | JSE0005 - ROUTE PP - WRIGHT COUNTY | 1 of 3 | $284,500 | Low, 10% under the second |
| 16 JAN 2026 | 260116-G05 | Southwest | JSR0177-I-44-NEWTON, LAWRENCE, JASPER, GREENE COUNTIES | 1 of 2 | $2 | Low, 6.0% under the second |
| 16 JAN 2026 | 260116-G06 | Southwest | JSR0178 - I-44 - WEBSTER COUNTY | 2 of 2 | $2 | +7.0% |
| 16 JAN 2026 | 260116-G07 | Southwest | JSR0179 - I-49 - BATES, VERNON COUNTIES | 2 of 2 | $2 | +4.0% |
| 16 JAN 2026 | 260116-G08 | Southwest | JSR0180 - I-49 - VARIOUS COUNTIES | 1 of 2 | $2 | Low, 3.0% under the second |
| 16 JAN 2026 | 260116-G09 | Southwest | JSR0181 - I-49 - MCDONALD COUNTY | 1 of 2 | $2 | Low, 14% under the second |
| 16 JAN 2026 | 260116-G13 | Southwest | JSU0197 - ROUTE I-44, 60, 65 - GREENE COUNTY | 2 of 2 | $2 | +3.0% |
| 14 NOV 2025 | 251114-G01 | Southwest | J7P3386 - ROUTE 60 - NEWTON, BARRY COUNTIES | 1 of 4 | $6,242,623 | Low, 7.0% under the second |
| 14 NOV 2025 | 251114-G04 | Southwest | JSR0324 - VARIOUS ROUTES - VARIOUS COUNTIES | 1 of 2 | $3,143,055 | Low, 43% under the second |
| 14 NOV 2025 | 251114-G05 | Southwest | JSR0324B - ROUTE HH - VARIOUS | 1 of 2 | $1,711,050 | Low, 10% under the second |
| 14 NOV 2025 | 251114-G9A | Southwest | JSR0312-ROUTE H-LAWRENCE COUNTY | 2 of 3 | $2,566,144 | +2.0% |
| 14 NOV 2025 | 251114-G9B | Southwest | JST0166-ROUTE O, V-LAWRENCE COUNTY | 2 of 3 | $839,450 | -3.0% |
| 17 OCT 2025 | 251017-D05 | Central | JCD0208 - VARIOUS ROUTES , VARIOUS COUNTIES | 1 of 3 | $1,412,405 | Low, 1.0% under the second |
| 17 OCT 2025 | 251017-G03 | Southwest | JSR0269, JSR0344 - ROUTE I-44 - JASPER, LAWRENCE COUNTIES | 3 of 4 | $15,141,829 | +5.0% |
| 17 OCT 2025 | 251017-G05 | Southwest | JST0165 - ROUTE CC, JJ, Y - GREEN AND POLK COUNTIES | 2 of 4 | $1,561,163 | 0.0% |
| 19 SEP 2025 | 250919-D06 | Central | JCD0147-ROUTE U-PULASKI, MILLER COUNTIES | 2 of 3 | $574,150 | +1.0% |
| 19 SEP 2025 | 250919-D08 | Central | JCD0153 - ROUTE B - GASCONADE, PHELPS COUNTIES | 1 of 3 | $744,975 | Low, 4.0% under the second |
| 19 SEP 2025 | 250919-D09 | Central | JCD0179-ROUTE J-MORGAN COUNTY | 1 of 3 | $271,040 | Low, 4.0% under the second |
| 19 SEP 2025 | 250919-D2A | Central | JCD0143, JCD0144-ROUTES O, UU- CALLAWAY COUNTY | 3 of 3 | $820,660 | +9.0% |
| 19 SEP 2025 | 250919-D2B | Central | JCD0145, JCD0146-ROUTES JJ, OR70-CALLAWAY | 3 of 3 | $501,475 | +9.0% |
How this record was read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Every bid counted here matched its published total to within one dollar; MoDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.