MoDOT contract 251114-G01 bid tabulation
J7P3386 - ROUTE 60 - NEWTON, BARRY COUNTIES. Let by Missouri DOT on November 14, 2025, Newton, Southwest. 4 bids received; low bid $6,242,623 by Blevins Asphalt Construction Company, Inc..
- Owner
- Missouri DOT
- Letting
- 14 NOV 2025
- Pay items
- 62
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Blevins Asphalt Construction Company, Inc. | $6,242,623 | Low |
| 2 | APAC-Central, Inc. | $6,664,709 | +7.0% |
| 3 | Capital Paving & Construction, LLC | $7,765,000 | +24% |
| 4 | Emery Sapp & Sons, Inc. | $8,270,389 | +32% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Blevins Asphalt Construction Company, Inc. | 2. APAC-Central, Inc. | 3. Capital Paving & Construction, LLC | 4. Emery Sapp & Sons, Inc. |
|---|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $49,000 | $40,460 | $46,000 | $66,895 |
| 0020 | Linear grading class 1 (2071000) | STA | 6.20 | $877.50 | $1,450.70 | $1,000.00 | $1,700.00 |
| 0030 | Misc.shaping slope class III modified material requirement (2159910) | 100F | 59 | $1,300.00 | $1,284.00 | $1,300.00 | $1,284.00 |
| 0040 | Removal of concrete wearing surface (2161502) | SF | 14,156 | $0.67 | $0.50 | $1.00 | $1.77 |
| 0050 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 283 | $23.95 | $24.05 | $16.50 | $15.50 |
| 0060 | Asphaltic concrete mixture PG 70-22 (SP095C mix) (4030003) | TON | 56,638.10 | $64.65 | $71.90 | $83.00 | $87.30 |
| 0070 | Asphaltic concrete mixture PG 70-22 (SP095BSM mix) (4030007) | TON | 529.10 | $142.00 | $139.80 | $131.50 | $141.32 |
| 0080 | Asphaltic concrete mixture PG 70-22 (SP125C mix) (4030103) | TON | 1,923.40 | $73.00 | $69.65 | $90.00 | $90.37 |
| 0090 | Asphaltic concrete mixture PG 70-22 (SP250C mix) (4030308) | TON | 50.20 | $325.00 | $159.50 | $185.00 | $136.50 |
| 0100 | Tack coat (4071005) | GAL | 78,290 | $2.32 | $2.70 | $3.00 | $2.08 |
| 0110 | Bituminous fog seal (4134000) | GAL | 67,737 | $2.75 | $2.85 | $3.00 | $3.23 |
| 0120 | 8 in. concrete median strip (6083008) | SY | 59.30 | $151.65 | $147.31 | $150.00 | $150.00 |
| 0130 | Furnishing type 2 rock blanket (6113020) | CY | 299 | $57.75 | $52.51 | $49.65 | $88.00 |
| 0140 | Placing type 2 rock blanket (6113040) | CY | 299 | $31.95 | $40.90 | $35.00 | $88.00 |
| 0150 | Truck mounted attenuator (TMA) (6123001) | LS | 1 | $3,300.00 | $500.00 | $26,000 | $5,750.00 |
| 0160 | Construction signs (6161005) | SF | 2,111 | $7.10 | $5.55 | $7.15 | $5.50 |
| 0170 | Channelizer (trim-line) (6161025) | EACH | 200 | $12.15 | $8.10 | $12.25 | $8.00 |
| 0180 | Type 3 moveable barricade (6161030) | EACH | 6 | $171.85 | $151.50 | $175.00 | $150.00 |
| 0190 | Flashing arrow panel (6161040) | EACH | 4 | $505.35 | $757.50 | $525.00 | $750.00 |
| 0200 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 4 | $2,530.00 | $1,919.20 | $2,550.00 | $1,900.00 |
| 0210 | Work zone traffic signal system (6162000A) | EACH | 1 | $5,560.00 | $10,101 | $11,250 | $10,000 |
| 0220 | Mobilization (6181000) | LS | 1 | $282,000 | $270,517 | $515,265 | $609,721 |
| 0230 | Pavement edge treatment (6191000) | LF | 350 | $16.35 | $6.00 | $5.00 | $13.99 |
| 0240 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 1,311 | $20.00 | $20.00 | $20.25 | $19.75 |
| 0250 | Preformed thermoplastic pavement marking, 24 in. yellow (6200018) | LF | 1,851 | $18.00 | $17.95 | $18.15 | $17.75 |
| 0260 | Preformed thermoplastic pavement marking, left/right arrow (6200021) | EACH | 113 | $187.00 | $187.05 | $189.15 | $185.00 |
| 0270 | Preformed thermoplastic pavement marking, straight arrow (6200024) | EACH | 10 | $141.50 | $141.55 | $143.15 | $140.00 |
| 0280 | Preformed thermoplastic pavement marking, combination STR/LT/RT (6200027) | EACH | 3 | $424.50 | $424.65 | $429.50 | $420.00 |
| 0290 | Preformed thermoplastic pavement marking, word (only) (6200030) | EACH | 6 | $424.50 | $424.65 | $429.50 | $420.00 |
| 0300 | Preformed thermoplastic pavement marking, 24 in. X 36 in., yield line triangle (6200042A) | EACH | 41 | $30.35 | $30.35 | $30.50 | $30.00 |
| 0310 | Temporary removable marking tape 4 in., white (6205301B) | LF | 1,000 | $2.70 | $2.70 | $2.75 | $2.65 |
| 0320 | Temporary removable marking tape 4 in., yellow (6205303B) | LF | 2,000 | $2.70 | $2.70 | $2.75 | $2.65 |
| 0330 | Temporary removable marking tape, 24 in., white (6205309) | LF | 24 | $22.25 | $22.20 | $22.50 | $22.00 |
| 0340 | 4 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205901B) | LF | 292,663 | $0.17 | $0.17 | $0.17 | $0.17 |
| 0350 | 6 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B) | LF | 443,029 | $0.20 | $0.20 | $0.20 | $0.20 |
| 0360 | 12 in. white class 2 pavement marking paint (25-mil, type L beads) (6205906B) | LF | 970 | $0.91 | $0.91 | $0.95 | $0.90 |
| 0370 | Pavement marking removal (6207001) | LF | 2,601 | $1.26 | $1.26 | $1.26 | $1.25 |
| 0380 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 664,202 | $0.63 | $0.77 | $0.90 | $1.20 |
| 0390 | Modified coldmilling (depth transitions) (6224010) | SY | 2,767 | $10.95 | $2.80 | $11.20 | $6.72 |
| 0400 | Permanent erosion control geotextile (6240103A) | SY | 448 | $11.25 | $1.15 | $4.00 | $2.69 |
| 0410 | Bituminous shoulder rumble strip (6261000A) | STA | 2,360.90 | $24.90 | $21.35 | $16.15 | $21.15 |
| 0420 | Bituminous centerline rumble strip (6261001) | STA | 1,395.20 | $30.95 | $22.40 | $16.35 | $21.85 |
| 0430 | Misc.transverse rumble strips (6269903) | LF | 75 | $227.00 | $80.25 | $135.00 | $106.67 |
| 0440 | Contractor furnished surveying and staking (6274000) | LS | 1 | $9,100.00 | $500.00 | $15,500 | $5,000.00 |
| 0450 | Bridge guardrail (W-beam) (7133000) | LF | 63 | $495.00 | $490.00 | $500.00 | $487.00 |
| 0460 | Sediment removal (8061016) | CY | 4 | $64.85 | $25.45 | $80.00 | $208.22 |
| 0470 | Silt fence (8061019) | LF | 366 | $6.60 | $7.35 | $4.00 | $6.50 |
| 0480 | MGS guardrail, 8 FT. posts, 6 FT. - 3 in. spacing (6061061) | LF | 3,375 | $28.30 | $28.00 | $28.35 | $28.00 |
| 0490 | MGS guardrail, 6 FT. posts, 3 FT. - 1.5 in. spacing (6061063) | LF | 275 | $38.45 | $38.00 | $38.45 | $38.50 |
| 0500 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 16 | $3,700.00 | $3,600.00 | $3,650.00 | $3,600.00 |
| 0510 | MGS height and block transition (6061074) | EACH | 46 | $809.00 | $800.00 | $810.00 | $800.00 |
| 0520 | MGS end anchor (6061080) | EACH | 1 | $1,213.00 | $1,200.00 | $1,215.00 | $1,200.00 |
| 0530 | MGS bridge approach transition (thrie-beam bridge) (6061081) | EACH | 10 | $3,135.00 | $3,100.00 | $3,135.00 | $3,100.00 |
| 0540 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 74 | $3,140.00 | $3,106.00 | $3,145.00 | $3,106.00 |
| 0550 | Cable, loop detector, in duct (9028500) | LF | 17,390 | $5.35 | $5.25 | $5.35 | $5.25 |
| 0560 | Cable, loop detector, lead-in (9028510) | LF | 6,300 | $7.35 | $7.25 | $7.35 | $7.25 |
| 0570 | Pull box, preformed class 1 (9028810) | EACH | 2 | $2,580.00 | $2,550.00 | $2,575.00 | $2,550.00 |
| 0580 | 36 in. surface-mount delineator post (9031242) | EACH | 11 | $108.15 | $110.59 | $130.00 | $107.00 |
| 0590 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 32 | $13.80 | $14.11 | $18.25 | $13.65 |
| 0600 | Concrete post anchor for 2.5 in. PSST. - 7 GA. (9031285) | EACH | 2 | $415.00 | $423.76 | $361.00 | $410.00 |
| 0610 | Misc.relocate exist. signs to new posts (9039902) | EACH | 4 | $44.85 | $45.84 | $101.00 | $44.35 |
| 0620 | Pavement marking removal (symbols) (6207002) | EACH | 23 | $96.10 | $96.06 | $97.00 | $95.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of November 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.