Millstone Weber, LLC: MoDOT bid record
Millstone Weber, LLC submitted 17 bids on Missouri DOT contracts in the data, from 18 JUN 2021 to 18 JUN 2026, and was the low bidder on 4 of them (24%). When it was not low, its total sat a median +8.0% above the low bid.
- Owner
- Missouri DOT
- Low bid volume
- $65,177,487
- Latest bid
- 18 JUN 2026
- Data through
- 16 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 2 | 0 | 0% |
| 2022 | 1 | 0 | 0% |
| 2023 | 4 | 1 | 25% |
| 2024 | 2 | 1 | 50% |
| 2025 | 7 | 1 | 14% |
| 2026 | 1 | 1 | 100% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| St. Louis | 15 | 4 | 27% |
| Northeast | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Mulching | 8025006 | ACRE | 15 | 13 (87%) | $2,800.00 | $2,500.00 |
| Pile point reinforcement | 7027000 | EACH | 16 | 12 (75%) | $141.00 | $155.00 |
| Permanent erosion control geotextile | 6240103A | SY | 14 | 12 (86%) | $1.38 | $4.00 |
| Temporary seeding | 8061017 | ACRE | 14 | 12 (86%) | $1,000.00 | $2,100.00 |
| MGS guardrail | 6061060 | LF | 12 | 12 (100%) | $28.00 | $30.00 |
| Galvanized structural steel piles (12 in) | 7021212 | LF | 16 | 11 (69%) | $106.00 | $115.00 |
| SH-flat sheet | 9035004A | SF | 14 | 11 (79%) | $33.50 | $28.00 |
| Type A crashworthy end terminal (MASH) | 6063014 | EACH | 12 | 11 (92%) | $3,800.00 | $3,300.00 |
| Additional mobilization for seeding | 6181020 | EACH | 11 | 11 (100%) | $600.00 | $600.00 |
| 2 in. PSST post - 12 GA. | 9031270A | LF | 11 | 10 (91%) | $26.00 | $24.00 |
| Preformed thermoplastic pavement marking, 24 in. white | 6200015 | LF | 10 | 10 (100%) | $25.00 | $23.50 |
| Preformed thermoplastic pavement marking, left/right arrow | 6200021 | EACH | 10 | 10 (100%) | $325.00 | $300.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Kozeny-Wagner, Inc. | 13 | 4 of 13 |
| KCI Construction Company | 10 | 5 of 10 |
| Pace Construction Company, LLC | 6 | 4 of 6 |
| Gershenson Construction Co., Inc. | 6 | 2 of 6 |
| Plattin Creek Excavating, LLC dba PCX Construction, LLC | 4 | 1 of 4 |
| R. V. Wagner, Inc. | 2 | 0 of 2 |
| Emery Sapp & Sons, Inc. | 2 | 1 of 2 |
| Concrete Strategies, LLC | 2 | 1 of 2 |
| L.F. Krupp Construction, Inc. dba Krupp | 1 | 1 of 1 |
| Logan Excavating, LLC | 1 | 1 of 1 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 18 JUN 2026 | 260618-F01 | St. Louis | J6I3020D, J6I350B, JSL0021 - I-270 - ST. LOUIS COUNTY | 1 of 4 | $40,763,061 | Low, 8.0% under the second |
| 12 DEC 2025 | 251212-F01 | St. Louis | J6I3618-ROUTE I-270-ST LOUIS COUNTY | 3 of 5 | $848,525 | +30% |
| 17 OCT 2025 | 251017-F04 | St. Louis | J6S3289, J6S3391 - ROUTE 61/67 - JEFFERSON COUNTY | 2 of 3 | $20,655,627 | +15% |
| 15 AUG 2025 | 250815-F06 | St. Louis | JSLM0112 - ROUTE I-270 - ST LOUIS COUNTY | 2 of 3 | $609,977 | +27% |
| 16 MAY 2025 | 250516-F11 | St. Louis | JSL0112 - ROUTE I-64 NOR - ST CHARLES COUNTY | 3 of 4 | $4,746,667 | +24% |
| 14 MAR 2025 | 250314-F03 | St. Louis | J6S3626 - ROUTE D - ST. LOUIS COUNTY | 3 of 5 | $12,162,397 | +8.0% |
| 21 FEB 2025 | 250221-B02 | Northeast | J2S3438, J2S3439 - ROUTE A/B, E/Y - WAREN, MONTGOMERY COUNTIES | 2 of 4 | $14,049,484 | +2.0% |
| 17 JAN 2025 | 250117-F07 | St. Louis | J6I3624B - ROUTE I-170 - ST LOUIS COUNTY | 1 of 4 | $2,882,042 | Low, 16% under the second |
| 15 NOV 2024 | 241115-F01 | St. Louis | J6I3538 - ROUTE I-64 - ST LOUIS, ST CHARLES COUNTIES | 1 of 5 | $16,858,440 | Low, 1.0% under the second |
| 15 MAR 2024 | 240315-F04 | St. Louis | J6S3621-ROUTE 67/180-ST LOUIS COUNTY | 2 of 4 | $2,051,213 | 0.0% |
| 17 NOV 2023 | 231117-F01 | St. Louis | J6S3280 - ROUTE 67 - ST. LOUIS COUNTY | 2 of 3 | $18,529,198 | 0.0% |
| 17 NOV 2023 | 231117-F02 | St. Louis | J6S3351-ROUTE 109, CC-ST. LOUIS COUNTY | 1 of 5 | $4,673,944 | Low, 6.0% under the second |
| 20 OCT 2023 | 231020-F07 | St. Louis | J6M3422 - ROUTE 370 - ST.CHARLES COUNTY | 3 of 7 | $1,387,221 | +65% |
| 15 SEP 2023 | 230915-B01 | Northeast | J2P3357 - ROUTE 79 - MARION COUNTY | 2 of 3 | $12,762,941 | +2.0% |
| 21 JAN 2022 | 220121-F10 | St. Louis | J6S3404 - ROUTES LACKLAND ROAD, MIDLAND BLVD - ST. LOUIS COUNTY | 4 of 4 | $7,124,027 | +8.0% |
| 17 DEC 2021 | 211217-F04 | St. Louis | J6S3272, J6S3638 - ST LOUIS CITY - I-44 | 4 of 4 | $8,900,834 | +14% |
| 18 JUN 2021 | 210618-F01 | St. Louis | J6P3482 - ROUTE 364 - ST. CHARLES COUNTY | 2 of 4 | $411,570 | +8.0% |
How this record was read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Every bid counted here matched its published total to within one dollar; MoDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.