Penzel Construction Company, Inc.: MoDOT bid record

Penzel Construction Company, Inc. submitted 22 bids on Missouri DOT contracts in the data, from 15 MAY 2020 to 18 JUN 2026, and was the low bidder on 6 of them (27%). When it was not low, its total sat a median +8.0% above the low bid.

Owner
Missouri DOT
Low bid volume
$20,985,761
Latest bid
18 JUN 2026
Data through
16 OCT 2026
22Bids
6Low bids
27Win rate, percent
+8.0%Median gap to the low bid when not low, 16 bids

By year

YearBidsLow bidsWin rate
2020100%
2021100%
2022200%
202311100%
20245120%
20257229%
20265240%
Penzel Construction Company, Inc., MoDOT: bids and low bids by year of letting

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Construction signs6161005SF3327 (82%)$7.00$7.00
4 in. white standard waterborne pavement marking paint, type P beads6206000CLF2623 (88%)$0.50$0.20
Changeable message sign without communication interface, contractor furnished, contractor retained6161098AEACH2320 (87%)$3,000.00$3,078.23
4 in. yellow standard waterborne pavement marking paint, type P beads6206001CLF2419 (79%)$0.50$0.25
Class B concrete (substructure)7032003CY3215 (47%)$1,290.00$1,300.00
Bridge approach slab (minor road)5031011ASY3015 (50%)$152.78$195.00
Type A crashworthy end terminal (MASH)6063014EACH2015 (75%)$3,800.00$3,300.00
Type III moveable barricade6161030EACH1915 (79%)$145.00$156.69
Advanced warning rail system6161008EACH1815 (83%)$45.00$51.40
MGS bridge approach transition section (regular/no curb)6061069EACH1713 (76%)$4,000.00$3,800.00
Type D barrier7034219ALF1513 (87%)$115.96$135.80
Silt fence8061019LF3912 (31%)$3.50$3.45
Penzel Construction Company, Inc., MoDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Robertson Contractors, Inc.2013 of 20
Joe's Bridge & Grading, Inc.147 of 14
Putz Construction, LLC60 of 6
Louis-Company, LLC50 of 5
Plattin Creek Excavating, LLC dba PCX Construction, LLC40 of 4
PCX Construction, LLC41 of 4
N.B. West Contracting Company40 of 4
Pace Construction Company, LLC31 of 3
Keith Simpson Contracting, LLC20 of 2
Lehman Construction, LLC10 of 1
Penzel Construction Company, Inc., MoDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
18 JUN 2026260618-H03SoutheastJ9S3738 - ROUTE Z - CAPE GIRARDEAU ROUTE2 of 6$3,554,898+5.0%
15 MAY 2026260515-H03SoutheastJ9S3671, JSE0056-ROUTES K, C-PERRY, CAPE GIRARDEAU COUNTIES1 of 4$3,366,393Low, 0.0% under the second
17 APR 2026260417-H03SoutheastJSE0030-ROUTE OO- CAPE GIRARDEAU COUNTY1 of 4$2,834,749Low, 0.0% under the second
16 JAN 2026260116-H02SoutheastJ9P3772, J9S3810 - ROUTE 25, 61 - CAPE GIRARDEAU COUNTY2 of 5$1,375,308+1.0%
16 JAN 2026260116-H03SoutheastJ9S3670, J9S3771 - ROUTE T, NN - PERRY COUNTY4 of 6$3,361,004+6.0%
12 DEC 2025251212-H03SoutheastJ9S3727, J9S3776-ROUTES C, BB-SCOTT, CAPE GIRARDEAU COUNTIES3 of 5$1,789,355+9.0%
19 SEP 2025250919-H01SoutheastJ9S3677 - ROUTE AA - BUTLER COUNTY3 of 3$2,157,777+15%
19 SEP 2025250919-H02SoutheastJSE0083 - ROUTE 67 - WAYNE COUNTY3 of 3$3,238,196+14%
15 AUG 2025250815-H04SoutheastJSE0155 - ROUTE 62 - DUNKLIN COUNTY2 of 4$12,487,177+8.0%
16 MAY 2025250516-H10SoutheastJSE0248 - ROUTE AA - SCOTT COUNTY1 of 5$4,428,373Low, 1.0% under the second
18 APR 2025250418-H05SoutheastJ9S3679, JSE0076, JSE0078 - ROUTE DD, D - MISSISSIPPI COUNTY2 of 5$2,949,988+4.0%
14 MAR 2025250314-H02SoutheastJ9S3680, JSE0116, JSE0127 - ROUTE 102, O, E - MISSISSIPPI, NEW MADRID COUNTIESSTODDARD,1 of 6$2,288,286Low, 9.0% under the second
17 MAY 2024240517-H03SoutheastJ9S3593, J9S3595, J9S3669, J9S3676 - ROUTE HH, K, O, A - PEMISCOT, DUNKLIN COUNTIES3 of 3$4,992,633+19%
19 APR 2024240419-H08SoutheastJ9S3589 - ROUTE Y - CAPE GIRARDEAU COUNTY1 of 5$981,021Low, 2.0% under the second
15 MAR 2024240315-H03SoutheastJ9P3768, J9S3608, JSE0086, JSE0088 - ROUTE 53, U, J, H - DUNKLIN, BUTLER COUNTIES2 of 3$4,663,238+7.0%
19 JAN 2024240119-H07SoutheastJ9S3640, J9S3642, J9S3645, J9S3646 - ROUTES Z, P , D, ZZ - SCOTT, STODDARD, CAPE GIRARDEAU,3 of 4$3,542,181+1.0%
19 JAN 2024240119-H08SoutheastJ9S3641, J9S3723, J9S3724, J9S3769 - ROUTE D, E, 75- MISSISSIPPI, NEW MADRID COUNTIES3 of 3$3,910,781+1.0%
19 MAY 2023230519-H01SoutheastJ9P3735 - ROUTE 61 - CAPE GIRARDEAU1 of 1$7,086,940Low
18 FEB 2022220218-H05SoutheastJ9P3218 - ROUTE 34 - WAYNE COUNTY2 of 2$6,692,985+15%
21 JAN 2022220121-H01SoutheastJ9I3643 - I-55 - SCOTT COUNTY2 of 2$3,757,680+3.0%
21 MAY 2021210521-H07SoutheastJ9M0282- ROUTE 72- CAPE GIRARDEAU COUNTY3 of 10$45,420+8.0%
15 MAY 2020200515-H06SoutheastJ9S3063 - ROUTE BUS 61 - SCOTT COUNTY2 of 5$2,516,040+13%
Penzel Construction Company, Inc.: latest MoDOT bids in the data

How this record was read

MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

  • Every bid counted here matched its published total to within one dollar; MoDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy