MoDOT contract 260618-H03 bid tabulation
J9S3738 - ROUTE Z - CAPE GIRARDEAU ROUTE. Let by Missouri DOT on June 18, 2026, Cape Girardeau, Southeast. 6 bids received; low bid $3,381,857 by Robertson Contractors, Inc..
- Owner
- Missouri DOT
- Letting
- 18 JUN 2026
- Pay items
- 59
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Robertson Contractors, Inc. | $3,381,857 | Low |
| 2 | Penzel Construction Company, Inc. | $3,554,898 | +5.0% |
| 3 | PCX Construction, LLC | $3,798,108 | +12% |
| 4 | N.B. West Contracting Company | $3,802,164 | +12% |
| 5 | Louis-Company, LLC | $3,839,217 | +14% |
| 6 | Putz Construction, LLC | $3,893,755 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Robertson Contractors, Inc. | 2. Penzel Construction Company, Inc. | 3. PCX Construction, LLC | 4. N.B. West Contracting Company | 5. Louis-Company, LLC | 6. Putz Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Temporary surfacing (1041000) | CY | 1,590 | $39.10 | $11.50 | $9.00 | $30.00 | $73.08 | $38.00 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $12,500 | $41,000 | $50,000 | $61,300 | $31,413 | $75,000 |
| 0030 | Class A excavation (2031000) | CY | 837 | $6.80 | $16.00 | $17.00 | $13.00 | $20.10 | $13.00 |
| 0040 | Embankment in place (2035500) | CY | 11,104 | $12.00 | $19.00 | $23.50 | $23.00 | $28.58 | $19.50 |
| 0050 | Compacting embankment (2036000) | CY | 670 | $2.95 | $6.20 | $10.80 | $5.00 | $12.55 | $4.50 |
| 0060 | Compacting in cut (2037075) | STA | 5.20 | $345.00 | $1,100.00 | $1,460.00 | $1,470.00 | $1,021.98 | $650.00 |
| 0070 | Class 3 excavation (2063000) | CY | 32 | $18.20 | $51.00 | $7.00 | $9.00 | $89.94 | $22.00 |
| 0080 | Porous backfill (2064000) | CY | 68 | $115.00 | $76.00 | $102.00 | $91.00 | $116.65 | $95.00 |
| 0090 | Linear grading class 1 (2071000) | STA | 5 | $650.00 | $1,132.00 | $907.00 | $3,370.00 | $1,771.43 | $2,250.00 |
| 0100 | Misc.modified linear grading class 2 (2079909) | STA | 2.30 | $1,800.00 | $5,700.00 | $7,060.00 | $5,830.00 | $2,395.67 | $2,000.00 |
| 0110 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 4,326 | $13.70 | $14.25 | $14.50 | $14.00 | $18.20 | $17.00 |
| 0120 | Gravel (A) or crushed stone (B) (3105002) | TON | 237 | $28.00 | $48.00 | $20.00 | $60.00 | $56.16 | $39.00 |
| 0130 | Misc.optional pavement (4019905) | SY | 4,325.60 | $62.00 | $62.00 | $62.00 | $62.00 | $76.23 | $71.50 |
| 0140 | Furnishing type 1 rock ditch liner (6096010A) | CY | 94 | $41.00 | $52.00 | $65.00 | $53.00 | $86.68 | $39.00 |
| 0150 | Placing type 1 rock ditch liner (6096041) | CY | 94 | $25.00 | $22.00 | $85.00 | $39.00 | $23.56 | $28.00 |
| 0160 | Furnishing type 2 rock blanket (6113020) | CY | 1,342 | $49.00 | $53.00 | $65.00 | $65.00 | $86.68 | $40.00 |
| 0170 | Placing type 2 rock blanket (6113040) | CY | 1,342 | $15.00 | $24.00 | $36.00 | $27.00 | $13.20 | $26.00 |
| 0180 | Grate and bearing plate (3 FT. X 2 FT. or 914 MM X 610 MM) (6141021) | EACH | 1 | $2,800.00 | $603.00 | $1,040.00 | $2,540.00 | $1,327.86 | $1,650.00 |
| 0190 | Construction signs (6161005) | SF | 995 | $7.00 | $6.50 | $7.00 | $7.00 | $8.61 | $7.00 |
| 0200 | Type 3 moveable barricade (6161030) | EACH | 16 | $150.00 | $185.00 | $150.00 | $185.00 | $184.42 | $150.00 |
| 0210 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 2 | $4,100.00 | $3,500.00 | $4,100.00 | $3,500.00 | $5,040.92 | $4,100.00 |
| 0220 | Mobilization (6181000) | LS | 1 | $155,000 | $216,000 | $180,000 | $234,000 | $57,680 | $125,000 |
| 0230 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 3,765 | $0.50 | $0.45 | $0.50 | $0.45 | $0.61 | $0.56 |
| 0240 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 3,952 | $0.50 | $0.45 | $0.50 | $0.45 | $0.61 | $0.56 |
| 0250 | Permanent erosion control geotextile (6240103A) | SY | 2,013 | $2.85 | $3.00 | $3.00 | $4.00 | $3.07 | $3.00 |
| 0260 | Contractor furnished surveying and staking (6274000) | LS | 1 | $22,500 | $12,900 | $28,500 | $19,000 | $22,131 | $45,000 |
| 0270 | 15 in. pipe group C (7250415) | LF | 67 | $48.00 | $64.00 | $92.00 | $128.00 | $109.30 | $95.00 |
| 0280 | Precast concrete drop inlet 3 FT X 2 FT (7311032) | FT | 2 | $1,150.00 | $795.00 | $1,150.00 | $1,130.00 | $1,844.24 | $1,600.00 |
| 0290 | 15 in. or allowed substitute group C flared end section (7320815A) | EACH | 2 | $1,700.00 | $515.00 | $2,060.00 | $2,100.00 | $1,108.26 | $285.00 |
| 0300 | Mulching (8025006) | ACRE | 2.40 | $1,850.00 | $3,500.00 | $3,500.00 | $3,500.00 | $2,213.08 | $1,500.00 |
| 0310 | Seeding - cool season grasses (8051000A) | ACRE | 1.60 | $2,700.00 | $4,500.00 | $4,500.00 | $4,500.00 | $3,565.53 | $2,800.00 |
| 0320 | Rock ditch check (8061005) | LF | 300 | $14.00 | $20.00 | $18.00 | $18.00 | $22.13 | $20.00 |
| 0330 | Sediment removal (8061016) | CY | 25 | $0.01 | $11.00 | $60.00 | $67.00 | $70.86 | $1.00 |
| 0340 | Temporary seeding (8061017) | ACRE | 0.80 | $825.00 | $2,500.00 | $2,500.00 | $2,500.00 | $3,442.56 | $750.00 |
| 0350 | Silt fence (8061019) | LF | 2,312 | $2.05 | $3.50 | $4.00 | $4.00 | $3.69 | $3.00 |
| 0360 | Type C berm (8061050) | LF | 200 | $9.70 | $20.00 | $30.00 | $30.00 | $36.88 | $18.00 |
| 0370 | MGS guardrail (6061060) | LF | 75 | $73.11 | $73.11 | $32.00 | $32.00 | $89.89 | $32.00 |
| 0380 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 4 | $3,730.57 | $3,730.57 | $4,000.00 | $4,000.00 | $4,586.70 | $4,000.00 |
| 0390 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 4 | $3,148.48 | $3,148.48 | $3,800.00 | $3,800.00 | $3,871.03 | $3,800.00 |
| 0400 | Class 1 excavation (2061000) | CY | 35 | $45.00 | $40.00 | $36.00 | $171.00 | $35.84 | $34.00 |
| 0410 | Removal of bridges (2160500) | LS | 1 | $40,000 | $43,000 | $69,400 | $44,600 | $40,716 | $60,000 |
| 0420 | Bridge approach slab (minor road) (5031011A) | SY | 117 | $170.00 | $111.00 | $90.75 | $310.00 | $289.95 | $104.36 |
| 0430 | Galvanized structural steel piles (14 in) (7021214) | LF | 2,766 | $160.00 | $172.00 | $170.00 | $168.00 | $188.02 | $215.28 |
| 0440 | Pile point reinforcement (7027000) | EACH | 44 | $210.00 | $195.00 | $171.00 | $209.00 | $196.72 | $218.00 |
| 0450 | Class B concrete (substructure) (7032003) | CY | 76.80 | $1,180.00 | $1,425.00 | $1,840.00 | $1,410.00 | $2,631.44 | $1,200.00 |
| 0460 | Type D barrier (7034219A) | LF | 644 | $130.00 | $102.00 | $96.00 | $97.00 | $142.24 | $109.00 |
| 0470 | Slab on concrete beam (7034222) | SY | 965 | $455.00 | $460.00 | $425.00 | $426.00 | $405.76 | $480.00 |
| 0480 | 27 in., prestressed concrete spread box beam (7056050A) | LF | 1,193 | $440.00 | $435.00 | $484.00 | $496.00 | $506.90 | $502.58 |
| 0490 | Reinforcing steel (bridges) (7061060) | LB | 6,900 | $2.25 | $2.00 | $1.50 | $2.00 | $1.01 | $1.75 |
| 0495 | Fabricated structural carbon steel (misc) (7121000) | LB | 1,910 | $12.40 | $11.55 | $10.00 | $6.00 | $13.15 | $7.50 |
| 0500 | Slab drain (7123610) | EACH | 32 | $550.00 | $604.00 | $611.00 | $579.00 | $547.18 | $530.00 |
| 0510 | Vertical drain at end bents (7151001) | EACH | 2 | $2,450.00 | $2,160.00 | $7,310.00 | $5,250.00 | $5,364.37 | $2,700.00 |
| 0520 | Plain neoprene bearing pad (7161000) | EACH | 8 | $240.00 | $291.00 | $488.00 | $186.00 | $301.23 | $295.00 |
| 0530 | Laminated neoprene bearing pad (7161002) | EACH | 32 | $285.00 | $330.00 | $374.00 | $276.00 | $153.69 | $480.00 |
| 0540 | Class 4 excavation (2063300) | CY | 1,435 | $14.80 | $28.00 | $64.00 | $23.00 | $17.59 | $32.00 |
| 0550 | Misc.dewatering (2069901) | LS | 1 | $10,000 | $11,800 | $20,600 | $24,600 | $21,936 | $10,000 |
| 0560 | Removal of bridges (2160500) | LS | 1 | $25,000 | $21,240 | $47,400 | $26,500 | $12,183 | $25,000 |
| 0570 | Class B-1 concrete (culverts-bridge) (7034040) | CY | 554.80 | $930.00 | $919.00 | $920.00 | $880.00 | $805.12 | $999.99 |
| 0580 | Reinforcing steel (culverts-bridge) (7061020) | LB | 80,140 | $1.95 | $1.47 | $1.35 | $2.00 | $0.98 | $1.75 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of June 18, 2026. Compiled by Mirage Metrics.