Aplex, Inc.: MoDOT bid record
Aplex, Inc. submitted 10 bids on Missouri DOT contracts in the data, from 17 MAR 2023 to 16 OCT 2026, and was the low bidder on 2 of them (20%). When it was not low, its total sat a median +16% above the low bid.
- Owner
- Missouri DOT
- Low bid volume
- $2,197,359
- Latest bid
- 16 OCT 2026
- Data through
- 16 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2023 | 3 | 1 | 33% |
| 2025 | 5 | 1 | 20% |
| 2026 | 2 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Central | 8 | 2 | 25% |
| St. Louis | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Silt fence | 8061019 | LF | 8 | 5 (63%) | $3.50 | $3.45 |
| Pavement marking removal (symbols) | 6207002 | EACH | 5 | 5 (100%) | $125.00 | $100.00 |
| Pavement marking removal | 6207001 | LF | 6 | 4 (67%) | $2.00 | $1.04 |
| Preformed thermoplastic pavement marking, 24 in. white | 6200015 | LF | 5 | 4 (80%) | $22.50 | $23.50 |
| Curb inlet check | 8061007A | EACH | 7 | 3 (43%) | $190.00 | $145.38 |
| Concrete sidewalk, 4 in. | 6086004 | SY | 6 | 3 (50%) | $67.50 | $79.31 |
| Paved approach, 8 in. | 6085008 | SY | 6 | 3 (50%) | $105.00 | $115.20 |
| Base, concrete | 9029100 | CY | 5 | 3 (60%) | $3,000.00 | $2,100.00 |
| Driven post anchor for 2.5 in. PSST - 7 GA. | 9031281A | EACH | 5 | 3 (60%) | $250.00 | $280.00 |
| Truncated domes | 6081012 | SF | 6 | 2 (33%) | $30.00 | $35.00 |
| Concrete curb ramp | 6081010 | SY | 6 | 2 (33%) | $135.00 | $172.00 |
| 2.5 in. PSST post - 12 GA. | 9031280 | LF | 5 | 2 (40%) | $25.00 | $23.48 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| S & A Equipment & Builders, LLC | 5 | 1 of 5 |
| Don Schnieders Excavating Company, Inc. | 3 | 1 of 3 |
| K.J.U., Inc. dba K.J. Unnerstall Construction Co. | 3 | 2 of 3 |
| Sam Gaines Construction, Inc. | 2 | 2 of 2 |
| Emery Sapp & Sons, Inc. | 2 | 1 of 2 |
| Concrete Solution LLC | 2 | 1 of 2 |
| N.B. West Contracting Company | 2 | 1 of 2 |
| Ti-Zack Concrete, LLC | 2 | 1 of 2 |
| Pace Construction Company, LLC | 2 | 0 of 2 |
| Geromini Concrete Paving, LLC dba GC Paving | 1 | 1 of 1 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 16 OCT 2026 | 261016-F06 | St. Louis | JSLM0104-ROUTE 50-FRANKLIN COUNTY | 2 of 5 | $282,382 | +10% |
| 16 JAN 2026 | 260116-D06 | Central | JCD0129 - ROUTE 19, 32, 72 - DENT COUNTY | 3 of 4 | $1,637,029 | +10% |
| 12 DEC 2025 | 251212-D02 | Central | J5S3418 - ROUTE OR 50 - COLE COUNTY | 3 of 3 | $2,046,338 | +32% |
| 14 NOV 2025 | 251114-D02 | Central | JCD0127 - ROUTE SP 44 - PULASKI COUNTY | 2 of 4 | $2,137,595 | +13% |
| 14 NOV 2025 | 251114-F06 | St. Louis | JSLM0079 - ROUTE 100 - FRANKLIN COUNTY | 3 of 10 | $129,376 | +13% |
| 14 MAR 2025 | 250314-D06 | Central | JCD0008 - ROUTE I-70 - COOPER, BOONE, CALLAWAY COUNTIES | 2 of 3 | $709,429 | +41% |
| 14 MAR 2025 | 250314-D07 | Central | JCD0076 - VARIOUS ROUTES - BOONE, CALLAWAY, OSAGE, PHELS COUNTIES | 1 of 4 | $967,082 | Low, 13% under the second |
| 19 MAY 2023 | 230519-D03 | Central | J5P3490- ROUTE BUS 50 - VARIOUS COUNTIES | 1 of 3 | $1,230,277 | Low, 19% under the second |
| 19 MAY 2023 | 230519-D05 | Central | J5S3369 - VARIOUS ROUTES - VARIOUS COUNTIES | 3 of 5 | $897,987 | +19% |
| 17 MAR 2023 | 230317-D01 | Central | J5P3576 - ROUTE 54 - CALLAWAY COUNTY | 4 of 5 | $1,597,189 | +42% |
How this record was read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Every bid counted here matched its published total to within one dollar; MoDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.