RL Persons Construction, Inc.: MoDOT bid record
RL Persons Construction, Inc. submitted 51 bids on Missouri DOT contracts in the data, from 19 JUN 2020 to 15 MAY 2026, and was the low bidder on 4 of them (8%). When it was not low, its total sat a median +40% above the low bid.
- Owner
- Missouri DOT
- Low bid volume
- $4,169,996
- Latest bid
- 15 MAY 2026
- Data through
- 16 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 2 | 0 | 0% |
| 2021 | 10 | 1 | 10% |
| 2022 | 4 | 0 | 0% |
| 2023 | 12 | 2 | 17% |
| 2024 | 7 | 0 | 0% |
| 2025 | 9 | 1 | 11% |
| 2026 | 7 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Southeast | 35 | 4 | 11% |
| Southwest | 12 | 0 | 0% |
| Central | 2 | 0 | 0% |
| Kansas City | 1 | 0 | 0% |
| Northeast | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Additional mobilization for seeding | 6181020 | EACH | 13 | 13 (100%) | $600.00 | $600.00 |
| Compacting embankment | 2036000 | CY | 20 | 9 (45%) | $5.12 | $7.65 |
| Placing type 2 rock ditch liner | 6096042 | CY | 12 | 7 (58%) | $31.25 | $39.01 |
| Class 3 excavation | 2063000 | CY | 20 | 6 (30%) | $54.33 | $30.00 |
| 4 in. white standard waterborne pavement marking paint, type P beads | 6206000C | LF | 23 | 5 (22%) | $0.90 | $0.20 |
| Reinforcing steel (culverts-bridge) | 7061020 | LB | 12 | 5 (42%) | $1.55 | $1.99 |
| Pipe collar, type A | 6044011 | EACH | 6 | 5 (83%) | $905.00 | $1,952.50 |
| Silt fence | 8061019 | LF | 37 | 4 (11%) | $4.50 | $3.45 |
| Class 4 excavation | 2063300 | CY | 17 | 4 (24%) | $49.20 | $45.00 |
| Sediment trap excavation | 8061003 | CY | 8 | 3 (38%) | $59.48 | $48.00 |
| Gravel (A) or crushed stone (B) | 3105002 | TON | 6 | 3 (50%) | $44.12 | $55.00 |
| Rock ditch check | 8061005 | LF | 26 | 2 (8%) | $18.00 | $20.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Putz Construction, LLC | 21 | 13 of 21 |
| Fronabarger Concreters, Inc. | 14 | 12 of 14 |
| H.R. Quadri Contractors, LLC | 13 | 7 of 13 |
| Hartman and Company, Inc. | 8 | 8 of 8 |
| Robertson Contractors, Inc. | 7 | 2 of 7 |
| Branco Enterprises, Inc. | 7 | 5 of 7 |
| Lappe Cement Finishing, Inc. | 7 | 4 of 7 |
| Hessling Construction, Inc. | 7 | 5 of 7 |
| Young's General Contracting, Inc. | 7 | 3 of 7 |
| Joe's Bridge & Grading, Inc. | 6 | 4 of 6 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 15 MAY 2026 | 260515-G05 | Southwest | JSR0075 - ROUTE H, NN - NEWTON COUNTY | 5 of 5 | $509,995 | +41% |
| 15 MAY 2026 | 260515-G06 | Southwest | JSR0110-ROUTE 7-BENTON COUNTY | 3 of 4 | $4,479,995 | +19% |
| 15 MAY 2026 | 260515-H02 | Southeast | J9P3855 - ROUTE 61 - STE GENEVIEVE COUNTY | 3 of 4 | $989,995 | +25% |
| 17 APR 2026 | 260417-H11 | Southeast | Rank vendor id vendor name total bid percent of low bid | 4 of 4 | $81,795 | +69% |
| 20 MAR 2026 | 260320-H02 | Southeast | JSE0069 - ROUTE 67 - MADISON COUNTY | 3 of 3 | $2,963,995 | +8.0% |
| 20 MAR 2026 | 260320-H04 | Southeast | JSE0332 - ROUTE I-57 - MISSISSIPPI COUNTY | 6 of 6 | $3,135,995 | +62% |
| 16 JAN 2026 | 260116-D06 | Central | JCD0129 - ROUTE 19, 32, 72 - DENT COUNTY | 4 of 4 | $2,899,995 | +94% |
| 12 DEC 2025 | 251212-H06 | Southeast | J9M0283 - ROUTE 77 - CAPE GIRARDEAU, SCOTT COUNTIES | 2 of 2 | $1,445,875 | +11% |
| 17 OCT 2025 | 251017-H02 | Southeast | J9S3798 - VARIOUS ROUTES - VARIOUS COUNTIES | 4 of 4 | $894,995 | +201% |
| 17 OCT 2025 | 251017-H04 | Southeast | JSE0141 - VARIOUS ROUTES - VARIOUS COUNTIES | 5 of 5 | $2,945,995 | +206% |
| 15 AUG 2025 | 250815-H03 | Southeast | JSE0150 - ROUTE Y - SCOTT COUNTY | 1 of 6 | $2,339,999 | Low, 14% under the second |
| 15 AUG 2025 | 250815-H05 | Southeast | JSEM0106-ROUTE KK-WAYNE COUNTY | 3 of 7 | $207,999 | +40% |
| 20 JUN 2025 | 250620-B01 | Northeast | JNE0147 - ROUTE 156, J, 149, C - MACON COUNTY | 4 of 4 | $1,923,999 | +96% |
| 18 APR 2025 | 250418-H04 | Southeast | J9S3609-ROUTE A-CARTER COUNTY | 3 of 4 | $934,999 | +7.0% |
| 21 FEB 2025 | 250221-H02 | Southwest | J9S3744 - ROUTE HH - SCOTT COUNTY | 3 of 3 | $1,118,999 | +52% |
| 17 JAN 2025 | 250117-H03 | Southeast | J9P3842-ROUTES 72/51-BOLLINGER COUNTY | 2 of 4 | $3,499,999 | +29% |
| 18 OCT 2024 | 241018-H07 | Southeast | JSEM0061 - ROUTE I-55 - CAPE GIRARDEAU COUNTY | 4 of 5 | $2,714,999 | +32% |
| 21 JUN 2024 | 240621-H02 | Southeast | JSEM0059 - ROUTE 67 - BUTLER COUNTY | 3 of 8 | $249,999 | +31% |
| 17 MAY 2024 | 240517-H10 | Southeast | JSEM0048-ROUTE HH-NEW MADRID COUNTY | 5 of 7 | $87,777 | +49% |
| 19 APR 2024 | 240419-H11 | Southeast | JSE0089 - ROUTE 62 - NEW MADRID COUNTY | 2 of 3 | $1,399,777 | +26% |
| 16 FEB 2024 | 240216-H03 | Southeast | J9P3756 - I-57 - Mississippi County | 3 of 5 | $447,777 | +6.0% |
| 19 JAN 2024 | 240119-G02 | Southwest | J7P3386B - ROUTE 60 - NEWTON COUNTY | 4 of 4 | $1,009,777 | +22% |
| 19 JAN 2024 | 240119-H06 | Southeast | J9S3611 - ROUTE M - WRIGHT COUNTY | 6 of 6 | $1,399,777 | +53% |
| 15 DEC 2023 | 231215-C02 | Kansas City | J3S3156 - ROUTE 2 - JOHNSON COUNTY | 8 of 8 | $1,229,888 | +98% |
| 15 DEC 2023 | 231215-H04 | Southeast | J9S3449B - ROUTE M - STE. GENEVIEVE COUNTY | 3 of 6 | $744,888 | +19% |
How this record was read
MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
- Every bid counted here matched its published total to within one dollar; MoDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.