MoDOT contract 260515-G05 bid tabulation
JSR0075 - ROUTE H, NN - NEWTON COUNTY. Let by Missouri DOT on May 15, 2026, Newton, Southwest. 5 bids received; low bid $362,241 by Branco Enterprises, Inc..
- Owner
- Missouri DOT
- Letting
- 15 MAY 2026
- Pay items
- 33
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Branco Enterprises, Inc. | $362,241 | Low |
| 2 | Hartman and Company, Inc. | $387,000 | +7.0% |
| 3 | Sprouls Construction, Inc. | $406,608 | +12% |
| 4 | Widel, Inc. | $494,752 | +37% |
| 5 | RL Persons Construction, Inc. | $509,995 | +41% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Branco Enterprises, Inc. | 2. Hartman and Company, Inc. | 3. Sprouls Construction, Inc. | 4. Widel, Inc. | 5. RL Persons Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (2013000) | ACRE | 1 | $24,594 | $3,060.00 | $2,500.00 | $3,250.00 | $7,500.00 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $2,737.00 | $3,730.00 | $1,200.00 | $15,000 | $7,100.00 |
| 0030 | Unclassified excavation (2035000) | CY | 1,500 | $18.00 | $3.20 | $30.00 | $8.50 | $23.50 |
| 0040 | Compacting embankment (2036000) | CY | 197 | $11.00 | $14.70 | $25.00 | $8.50 | $4.50 |
| 0050 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 49 | $15.00 | $58.50 | $20.00 | $65.00 | $20.00 |
| 0060 | Gravel (A) or crushed stone (B) (3105002) | TON | 3 | $123.00 | $452.00 | $50.00 | $55.00 | $250.00 |
| 0070 | 8 inches, bituminous pavement (4010101) | SY | 48.90 | $85.00 | $282.00 | $140.00 | $825.00 | $310.00 |
| 0080 | Furnishing type 3 rock ditch liner (6096030A) | CY | 462 | $40.00 | $55.80 | $40.00 | $90.00 | $69.50 |
| 0090 | Placing type 3 rock ditch liner (6096043) | CY | 462 | $37.00 | $30.20 | $40.00 | $14.50 | $24.00 |
| 0100 | Bedding material for rock ditch liner (6096050) | CY | 168 | $34.00 | $77.10 | $60.00 | $85.00 | $67.00 |
| 0110 | Truck mounted attenuator (TMA) (6123001) | LS | 1 | $7,000.00 | $18,700 | $6,000.00 | $18,750 | $7,250.00 |
| 0120 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 2 | $2,255.00 | $2,260.00 | $2,800.00 | $2,750.00 | $3,325.00 |
| 0130 | Work zone traffic signal system (6162000A) | EACH | 3 | $2,550.00 | $2,000.00 | $8,000.00 | $2,450.00 | $7,600.00 |
| 0140 | Temporary long-term rumble strips (6162002) | EACH | 4 | $1,600.00 | $1,600.00 | $1,400.00 | $1,850.00 | $2,015.00 |
| 0150 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $15,786 | $13,500 | $2,750.00 | $4,250.00 | $14,000 |
| 0160 | Mobilization (6181000) | LS | 1 | $48,700 | $43,963 | $47,000 | $50,000 | $130,607 |
| 0170 | Temporary removable marking tape 4 in., white (6205301B) | LF | 448 | $3.00 | $3.20 | $2.50 | $3.75 | $3.80 |
| 0180 | Temporary removable marking tape 4 in., yellow (6205303B) | LF | 2,000 | $3.00 | $3.20 | $2.60 | $3.75 | $3.80 |
| 0190 | Temporary removable marking tape, 24 in., white (6205309) | LF | 22 | $20.00 | $3.20 | $15.00 | $25.00 | $25.25 |
| 0200 | Permanent erosion control geotextile (6240103A) | SY | 755 | $5.00 | $6.60 | $6.00 | $7.00 | $5.30 |
| 0210 | Contractor furnished surveying and staking (6274000) | LS | 1 | $4,930.00 | $4,930.00 | $3,500.00 | $8,500.00 | $7,000.00 |
| 0220 | Mulching (8025006) | ACRE | 1 | $700.00 | $700.00 | $805.00 | $875.00 | $885.00 |
| 0230 | Seeding - cool season grasses (8051000A) | ACRE | 1 | $1,400.00 | $1,400.00 | $1,610.00 | $65,250 | $1,765.00 |
| 0240 | Sediment trap excavation (8061003) | CY | 17.10 | $54.00 | $77.60 | $40.00 | $35.00 | $24.50 |
| 0250 | Sediment trap rock (8061004) | CY | 17.10 | $100.00 | $248.00 | $80.00 | $160.00 | $113.00 |
| 0260 | Sediment removal (8061016) | CY | 10 | $21.00 | $183.00 | $50.00 | $35.00 | $1,250.00 |
| 0270 | Removal of bridges (2160500) | LS | 1 | $2,737.00 | $7,400.00 | $15,000 | $12,500 | $6,500.00 |
| 0280 | Class 4 excavation (2063300) | CY | 350 | $31.00 | $54.40 | $45.00 | $8.75 | $42.45 |
| 0290 | Misc.dewatering (2069901) | LS | 1 | $10,395 | $7,300.00 | $1,000.00 | $7,500.00 | $2,650.00 |
| 0300 | Removal of bridges (2160500) | LS | 1 | $2,737.00 | $9,000.00 | $7,000.00 | $18,500 | $6,500.00 |
| 0310 | Class B-1 concrete (culverts-bridge) (7034040) | CY | 89.10 | $990.00 | $1,210.00 | $1,300.00 | $975.00 | $1,135.00 |
| 0320 | Reinforcing steel (culverts-bridge) (7061020) | LB | 7,920 | $2.00 | $1.90 | $2.00 | $2.30 | $2.00 |
| 0330 | Reinforcing steel (epoxy coated) (7101000) | LB | 5,650 | $3.00 | $2.80 | $3.00 | $4.00 | $2.25 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of May 15, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way