MoDOT contract 250117-H03 bid tabulation
J9P3842-ROUTES 72/51-BOLLINGER COUNTY. Let by Missouri DOT on January 17, 2025, Bollinger, Southeast. 4 bids received; low bid $2,720,536 by Fronabarger Concreters, Inc..
- Owner
- Missouri DOT
- Letting
- 17 JAN 2025
- Pay items
- 78
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Fronabarger Concreters, Inc. | $2,720,536 | Low |
| 2 | RL Persons Construction, Inc. | $3,499,999 | +29% |
| 3 | Robertson Contractors, Inc. | $3,909,661 | +44% |
| 4 | Lappe Cement Finishing, Inc. | $3,952,098 | +45% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fronabarger Concreters, Inc. | 2. RL Persons Construction, Inc. | 3. Robertson Contractors, Inc. | 4. Lappe Cement Finishing, Inc. |
|---|---|---|---|---|---|---|---|
| 0010 | Temporary surfacing (1041000) | CY | 662 | $55.00 | $97.75 | $60.00 | $41.00 |
| 0020 | Signet dbe reporting (1081000) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0030 | Removal of improvements (2022010) | LS | 1 | $85,000 | $83,500 | $115,000 | $379,000 |
| 0040 | Class A excavation (2031000) | CY | 3,252 | $23.00 | $23.75 | $24.50 | $40.00 |
| 0050 | Embankment in place (2035500) | CY | 1,551 | $20.00 | $60.10 | $35.00 | $46.00 |
| 0060 | Compacting embankment (2036000) | CY | 2,828 | $7.00 | $6.85 | $10.00 | $28.00 |
| 0070 | Compacting in cut (2037075) | STA | 21.30 | $1,400.00 | $1,595.00 | $850.00 | $2,550.00 |
| 0080 | Class 3 excavation (2063000) | CY | 75 | $40.00 | $38.50 | $45.00 | $64.00 |
| 0090 | Misc.modified linear grading class 2 (2079909) | STA | 24.10 | $3,300.00 | $1,850.00 | $2,650.00 | $3,800.00 |
| 0100 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 11,162 | $9.00 | $15.00 | $18.00 | $9.30 |
| 0110 | Misc.2 inch clean rock (3109907) | CY | 177 | $52.00 | $83.65 | $95.00 | $29.00 |
| 0120 | Type A2 shoulder (4010150) | SY | 839.40 | $50.00 | $82.25 | $65.00 | $49.00 |
| 0130 | Bituminous pavement mixture PG64-22, (BP-1) (4011209) | TON | 1,530.60 | $116.11 | $168.50 | $116.11 | $120.00 |
| 0140 | Misc.optional pavement (4019905) | SY | 1,522.60 | $58.58 | $85.00 | $58.58 | $64.00 |
| 0150 | Misc.optional base (4029905) | SY | 929.30 | $27.91 | $40.50 | $27.91 | $30.00 |
| 0160 | Tack coat (4071005) | GAL | 412 | $3.99 | $5.80 | $3.99 | $4.00 |
| 0170 | Concrete pavement ( 9 in. non-reinf) (5021109) | SY | 8,945.80 | $95.00 | $100.00 | $155.00 | $126.00 |
| 0180 | Misc.tinted 9 inch PCCP (5029905) | SY | 595.20 | $126.00 | $148.50 | $185.00 | $154.00 |
| 0190 | Paved approach, 7 in. (6085007) | SY | 380 | $82.00 | $110.00 | $130.00 | $106.00 |
| 0200 | Paved approach, 8 in. (6085008) | SY | 1,796 | $87.00 | $110.00 | $135.00 | $114.00 |
| 0210 | Misc.tinted 6 inch concrete median (6089905) | SY | 829.50 | $120.00 | $125.00 | $130.00 | $125.00 |
| 0220 | Concrete gutter type A (6091041) | LF | 93 | $55.00 | $120.00 | $92.00 | $75.00 |
| 0230 | Furnishing type 2 rock ditch liner (6096020) | CY | 41 | $46.00 | $64.50 | $70.00 | $70.00 |
| 0240 | Placing type 2 rock ditch liner (6096042) | CY | 41 | $41.00 | $23.65 | $65.00 | $64.00 |
| 0250 | Misc.modified concrete curb and gutter, type A (6099903) | LF | 1,744 | $43.00 | $67.75 | $80.00 | $57.00 |
| 0260 | Misc.tinted 6 inch integral curb, type A (6099903) | LF | 503 | $15.00 | $50.00 | $48.00 | $24.00 |
| 0270 | Construction signs (6161005) | SF | 1,081 | $9.00 | $13.60 | $9.00 | $10.00 |
| 0280 | Changeable message sign without communication interface, contractor furnished, contractor retained (6161098A) | EACH | 4 | $3,200.00 | $6,500.00 | $3,200.00 | $3,600.00 |
| 0290 | Misc.temporary traffic control (6169901) | LS | 1 | $7,625.00 | $49,500 | $85,000 | $9,455.00 |
| 0300 | Misc.portable traffic signal system (6169902) | EACH | 1 | $25,500 | $70,300 | $25,500 | $58,600 |
| 0310 | Temporary traffic barrier, contractor furnished retained (6173600D) | LF | 1,300 | $36.44 | $54.50 | $55.00 | $52.00 |
| 0320 | Temporary traffic barrier height transition (6174000A) | EACH | 2 | $1,194.00 | $2,900.00 | $1,050.00 | $2,000.00 |
| 0330 | Mobilization (6181000) | LS | 1 | $205,000 | $226,876 | $335,000 | $369,400 |
| 0340 | Preformed thermoplastic pavement marking, 4 in yellow (6200006) | LF | 4,918 | $5.00 | $5.80 | $5.00 | $6.00 |
| 0350 | Preformed thermoplastic pavement marking, 6 in. white (6200009) | LF | 4,782 | $6.00 | $8.70 | $6.00 | $7.00 |
| 0360 | Preformed thermoplastic pavement marking, 24 in. yellow (6200018) | LF | 77 | $25.00 | $36.25 | $25.00 | $34.00 |
| 0370 | Temporary removable marking tape 4 in., white (6205301B) | LF | 200 | $3.00 | $2.90 | $3.00 | $4.00 |
| 0380 | Temporary removable marking tape 4 in., yellow (6205303B) | LF | 1,000 | $3.00 | $2.90 | $3.00 | $4.00 |
| 0390 | Temporary removable marking tape, 24 in., white (6205309) | LF | 36 | $10.00 | $17.50 | $10.00 | $14.00 |
| 0400 | 4 in. white standard waterborne pavement marking paint, type P beads (6206000C) | LF | 375 | $5.00 | $0.90 | $5.00 | $6.50 |
| 0410 | 4 in. yellow standard waterborne pavement marking paint, type P beads (6206001C) | LF | 12,172 | $0.80 | $0.90 | $0.80 | $1.23 |
| 0420 | 24 in. white standard waterborne pavement marking paint, type P beads (6206124A) | LF | 36 | $10.00 | $17.40 | $10.00 | $15.00 |
| 0430 | Pavement marking removal (6207001) | LF | 1,236 | $4.00 | $4.35 | $4.00 | $5.30 |
| 0440 | Misc.preformed thermoplastic marking, 24 inch, yield line (6209902) | EACH | 32 | $75.00 | $72.50 | $75.00 | $93.00 |
| 0450 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 775 | $8.50 | $12.35 | $8.50 | $9.00 |
| 0460 | Modified coldmilling (depth transitions) (6224010) | SY | 444 | $14.83 | $21.50 | $14.83 | $15.00 |
| 0470 | Separation geotextile (6240104A) | SY | 872 | $5.00 | $3.35 | $5.00 | $8.00 |
| 0480 | Contractor furnished surveying and staking (6274000) | LS | 1 | $15,000 | $23,500 | $25,000 | $38,400 |
| 0490 | 18 in. pipe group B (7250318A) | LF | 177 | $85.00 | $180.00 | $95.00 | $159.00 |
| 0500 | 21 in. pipe group B (7250321A) | LF | 71 | $90.00 | $185.00 | $105.00 | $162.00 |
| 0510 | 18 in. pipe group A (7261018) | LF | 100 | $85.00 | $215.00 | $115.00 | $153.00 |
| 0520 | 24 in. pipe group A (7261024) | LF | 62 | $95.00 | $215.00 | $150.00 | $164.00 |
| 0530 | 18 in. or allowed substitute group A flared end section (7320618A) | EACH | 2 | $650.00 | $2,100.00 | $1,200.00 | $3,200.00 |
| 0540 | 24 in. or allowed substitute group A flared end section (7320624A) | EACH | 2 | $750.00 | $2,325.00 | $1,300.00 | $3,990.00 |
| 0550 | Mulching (8025006) | ACRE | 1.10 | $1,250.00 | $1,815.00 | $1,250.00 | $6,400.00 |
| 0560 | Seeding - cool season grasses (8051000A) | ACRE | 1.10 | $2,900.00 | $4,200.00 | $2,900.00 | $8,000.00 |
| 0570 | Rock ditch check (8061005) | LF | 180 | $15.00 | $21.75 | $15.00 | $38.00 |
| 0580 | Temporary seeding (8061017) | ACRE | 0.70 | $2,150.00 | $3,120.00 | $2,150.00 | $6,200.00 |
| 0590 | Silt fence (8061019) | LF | 3,540 | $2.90 | $4.20 | $2.90 | $5.20 |
| 0600 | Lighting pole, 45 FT. or 13.5 M, type at design 2 (9011062) | EACH | 8 | $2,990.00 | $4,775.00 | $3,050.00 | $3,450.00 |
| 0610 | Bracket arm, 6 FT. or 1.8 M (9011106) | EACH | 8 | $562.00 | $805.00 | $637.00 | $600.00 |
| 0620 | Luminaire, LED-B (9011312) | EACH | 8 | $359.00 | $670.00 | $359.00 | $500.00 |
| 0630 | Conduit, 3 in. rigid, pushed (9014003) | LF | 186 | $40.00 | $51.00 | $40.00 | $40.00 |
| 0640 | Trenching type I (9015010) | LF | 1,363 | $8.61 | $8.00 | $8.61 | $6.00 |
| 0650 | Pull box, preformed class 1 (9016110) | EACH | 6 | $1,232.00 | $1,815.00 | $1,232.00 | $1,324.00 |
| 0660 | Cable, 10 AWG 1 conductor, pole and bracket (9017110) | LF | 860 | $1.00 | $1.45 | $1.00 | $1.40 |
| 0670 | Cable-conduit, 1 in., 2 conductors and 1 bare neutral, 8 AWG (9017407) | LF | 1,940 | $3.90 | $8.70 | $3.90 | $7.00 |
| 0680 | Pole foundation (45 FT. or 13.5 M mounting height) (9018245) | EACH | 8 | $1,853.00 | $2,625.00 | $2,038.00 | $1,900.00 |
| 0690 | Structural steel posts (9031210) | LB | 260 | $8.00 | $12.00 | $8.00 | $12.40 |
| 0700 | Breakaway assembly (perforated square steel tube) (9031241) | EACH | 14 | $350.00 | $510.00 | $350.00 | $395.00 |
| 0710 | 2 in. PSST post - 12 GA. (9031270A) | LF | 342 | $26.00 | $38.00 | $25.00 | $26.00 |
| 0720 | Driven post anchor for 2 in. PSST - 12 GA. (9031271A) | EACH | 34 | $175.00 | $250.00 | $150.00 | $175.00 |
| 0730 | 2.25 in. PSST post insert (6 FT.) - 12 GA. (9031272A) | EACH | 9 | $200.00 | $290.00 | $300.00 | $200.00 |
| 0740 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 221 | $28.00 | $40.65 | $25.00 | $32.00 |
| 0750 | Driven post anchor for 2.5 in. PSST - 7 GA. (9031281A) | EACH | 16 | $225.00 | $325.00 | $175.00 | $240.00 |
| 0760 | SH-flat sheet (9035004A) | SF | 340 | $26.00 | $38.00 | $25.00 | $29.00 |
| 0770 | ST-structural (9035011A) | SF | 160 | $36.00 | $52.25 | $45.00 | $36.00 |
| 0780 | SHF-flat sheet fluorescent (9035069A) | SF | 88 | $32.00 | $46.50 | $30.00 | $34.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of January 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.