MoDOT contract 251017-H04 bid tabulation
JSE0141 - VARIOUS ROUTES - VARIOUS COUNTIES. Let by Missouri DOT on October 17, 2025, Various, Southeast. 5 bids received; low bid $962,808 by Putz Construction, LLC.
- Owner
- Missouri DOT
- Letting
- 17 OCT 2025
- Pay items
- 34
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Putz Construction, LLC | $962,808 | Low |
| 2 | Fronabarger Concreters, Inc. | $1,299,403 | +35% |
| 3 | Lappe Cement Finishing, Inc. | $1,350,000 | +40% |
| 4 | Hessling Construction, Inc. | $1,394,793 | +45% |
| 5 | RL Persons Construction, Inc. | $2,945,995 | +206% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Putz Construction, LLC | 2. Fronabarger Concreters, Inc. | 3. Lappe Cement Finishing, Inc. | 4. Hessling Construction, Inc. | 5. RL Persons Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0010 | Signet dbe reporting (1081000) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $75,000 | $125,000 | $136,938 | $118,521 | $430,000 |
| 0030 | Linear grading class 1 (2071000) | STA | 42 | $1,000.00 | $1,500.00 | $2,450.00 | $1,429.43 | $5,050.00 |
| 0040 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 2,251.30 | $13.75 | $12.00 | $15.00 | $20.84 | $21.00 |
| 0050 | Modified concrete gutter type A (6071101) | LF | 992 | $90.00 | $75.00 | $64.00 | $106.94 | $210.00 |
| 0060 | Concrete curb ramp (6081010) | SY | 544.50 | $160.00 | $195.00 | $150.00 | $174.74 | $425.00 |
| 0070 | Truncated domes (6081012) | SF | 323.10 | $32.00 | $25.00 | $42.00 | $64.25 | $60.65 |
| 0080 | Sidewalk hand-railing with balusters (6084024) | LF | 40 | $175.00 | $225.00 | $162.00 | $293.59 | $435.00 |
| 0090 | Paved approach, 7 in. (6085007) | SY | 308.30 | $94.00 | $145.00 | $150.00 | $235.82 | $285.00 |
| 0100 | Paved approach, 8 in. (6085008) | SY | 1,502.10 | $96.00 | $150.00 | $156.00 | $203.25 | $260.00 |
| 0110 | Concrete sidewalk, 4 in. (6086004) | SY | 1,264.30 | $66.00 | $115.00 | $116.00 | $109.33 | $185.00 |
| 0120 | Concrete sidewalk, 7 in. (6086007) | SY | 46 | $94.00 | $135.00 | $152.00 | $264.57 | $320.00 |
| 0130 | Concrete sidewalk, 8 in. (6086008) | SY | 907.30 | $96.00 | $140.00 | $159.00 | $149.56 | $220.00 |
| 0140 | Integral curb (6 in. height and under) type A (6092011) | LF | 1,307 | $38.00 | $30.00 | $16.00 | $42.67 | $85.00 |
| 0150 | Misc.drainage cover plate (6149902) | EACH | 1 | $3,500.00 | $5,000.00 | $2,482.90 | $6,743.76 | $15,000 |
| 0160 | Construction signs (6161005) | SF | 385 | $7.00 | $9.00 | $10.00 | $21.21 | $18.65 |
| 0170 | Channelizer (trim-line) (6161025) | EACH | 100 | $14.00 | $20.00 | $20.00 | $64.07 | $55.10 |
| 0180 | Flashing arrow panel (6161040) | EACH | 2 | $1,200.00 | $1,200.00 | $1,280.00 | $2,170.19 | $3,845.00 |
| 0190 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 2 | $4,500.00 | $2,800.00 | $4,600.00 | $4,090.19 | $9,025.00 |
| 0200 | Misc.ADA compliant moveable barricade (6169902) | EACH | 20 | $165.00 | $125.00 | $175.00 | $265.46 | $185.00 |
| 0210 | Mobilization (6181000) | LS | 1 | $50,000 | $125,000 | $126,900 | $8,413.76 | $242,141 |
| 0220 | Preformed thermoplastic pavement marking, 6 in. white (6200009) | LF | 1,369 | $6.50 | $6.00 | $6.50 | $7.56 | $8.95 |
| 0230 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 824 | $28.00 | $20.00 | $30.00 | $24.74 | $35.80 |
| 0240 | Pavement marking removal (6207001) | LF | 963 | $3.00 | $3.00 | $3.60 | $4.11 | $11.95 |
| 0250 | Pavement marking removal (symbols) (6207002) | EACH | 64 | $350.00 | $100.00 | $375.00 | $127.72 | $300.00 |
| 0260 | Contractor furnished surveying and staking (6274000) | LS | 1 | $13,500 | $15,000 | $1,200.00 | $35,294 | $32,500 |
| 0270 | 18 in. pipe group B (7250318A) | LF | 25 | $75.00 | $125.00 | $155.00 | $123.78 | $245.00 |
| 0280 | Mulching (8025006) | ACRE | 1.40 | $2,500.00 | $10,000 | $3,500.00 | $5,152.69 | $14,500 |
| 0290 | Turf type tall fescue soddingsodding (8031000A) | SY | 1,867 | $15.84 | $15.00 | $20.00 | $20.18 | $125.00 |
| 0300 | Seeding - cool season grasses (8051000A) | ACRE | 1.40 | $2,850.00 | $10,000 | $7,200.00 | $6,856.86 | $13,500 |
| 0310 | Curb inlet check (8061007A) | EACH | 42 | $200.00 | $150.00 | $210.00 | $82.18 | $275.00 |
| 0320 | Sediment removal (8061016) | CY | 42 | $12.00 | $25.00 | $20.00 | $342.81 | $40.00 |
| 0330 | Silt fence (8061019) | LF | 1,000 | $4.00 | $3.50 | $5.00 | $1.07 | $8.75 |
| 0340 | Misc.rectangular rapid flashing beacon (9029902) | EACH | 1 | $27,500 | $32,950 | $27,150 | $12,494 | $36,250 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of October 17, 2025. Compiled by Mirage Metrics.