MoDOT contract 251212-H06 bid tabulation

J9M0283 - ROUTE 77 - CAPE GIRARDEAU, SCOTT COUNTIES. Let by Missouri DOT on December 12, 2025, Scott, Southeast. 2 bids received; low bid $1,298,162 by Putz Construction, LLC.

Owner
Missouri DOT
Letting
12 DEC 2025
Pay items
17
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Putz Construction, LLC$1,298,162Low
2RL Persons Construction, Inc.$1,445,875+11%
MoDOT contract 251212-H06: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Putz Construction, LLC2. RL Persons Construction, Inc.
0010Removal of improvements (2022010)LS1$125,000$5,500.00
0020Unclassified excavation (2035000)CY187$350.00$120.00
0030Class 3 excavation (2063000)CY16$1,200.00$185.00
0040Furnishing type 1 rock blanket (6113010)CY143$75.00$58.35
0050Placing type 1 rock blanket (6113030)CY143$125.00$56.50
0060Truck mounted attenuator (TMA) (6123001)LS1$19,750$8,000.00
0070Construction signs (6161005)SF196$10.80$16.00
0080Channelizer (trim-line) (6161025)EACH40$30.00$52.60
0090Mobilization (6181000)LS1$120,000$68,648
0100Subsurface drainage geotextile (6240101A)SY216$7.50$11.75
0110Contractor furnished surveying and staking (6274000)LS1$60,000$9,750.00
012048 in. or allowed substitute group A flared end section (7320648A)EACH1$12,250$4,625.00
0130Misc.48" flap gate (7329902)EACH1$14,750$6,650.00
0140Misc.48" steel culvert - horizontal bore (7349903)LF262$3,073.38$4,905.00
0150Misc.seeding and mulching - cool season grasses (8059901)LS1$18,000$4,910.00
0160Rock ditch check (8061005)LF20$200.00$79.00
0170Sediment removal (8061016)CY1$1,000.00$1,500.00
MoDOT contract 251212-H06: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of December 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy