MoDOT contract 250815-H03 bid tabulation
JSE0150 - ROUTE Y - SCOTT COUNTY. Let by Missouri DOT on August 15, 2025, Scott, Southeast. 6 bids received; low bid $2,339,999 by RL Persons Construction, Inc..
- Owner
- Missouri DOT
- Letting
- 15 AUG 2025
- Pay items
- 74
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | RL Persons Construction, Inc. | $2,339,999 | Low |
| 2 | Fronabarger Concreters, Inc. | $2,669,490 | +14% |
| 3 | H.R. Quadri Contractors, LLC | $2,698,635 | +15% |
| 4 | Lappe Cement Finishing, Inc. | $2,765,810 | +18% |
| 5 | Young's General Contracting, Inc. | $2,801,068 | +20% |
| 6 | Putz Construction, LLC | $3,368,020 | +44% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. RL Persons Construction, Inc. | 2. Fronabarger Concreters, Inc. | 3. H.R. Quadri Contractors, LLC | 4. Lappe Cement Finishing, Inc. | 5. Young's General Contracting, Inc. | 6. Putz Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Project: JSE0150 roundabout section: 0001 roadway items - JSE0150 signet dbe reporting (1081000) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $60,500 | $108,000 | $91,102 | $110,000 | $106,469 | $110,000 |
| 0030 | Class A excavation (2031000) | CY | 5,150 | $17.50 | $22.00 | $15.00 | $22.00 | $16.26 | $30.00 |
| 0040 | Compacting embankment (2036000) | CY | 3,838 | $5.00 | $5.00 | $3.00 | $9.00 | $23.70 | $6.85 |
| 0050 | Compacting in cut (2037075) | STA | 20.30 | $1,195.00 | $1,400.00 | $300.00 | $1,490.00 | $2,587.44 | $1,400.00 |
| 0060 | Class 3 excavation (2063000) | CY | 259 | $26.00 | $30.00 | $20.00 | $42.00 | $16.17 | $38.50 |
| 0070 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 11,100 | $12.50 | $14.00 | $15.00 | $14.00 | $9.10 | $10.50 |
| 0080 | Gravel (A) or crushed stone (B) (3105002) | TON | 34 | $34.50 | $55.00 | $40.00 | $50.00 | $64.83 | $50.90 |
| 0090 | Misc. 2 inch clean rock (3109907) | CY | 171 | $73.35 | $75.00 | $75.00 | $60.00 | $80.08 | $52.00 |
| 0100 | 6 inches, bituminous pavement (4010106) | SY | 1,403 | $61.50 | $42.75 | $42.75 | $45.00 | $62.58 | $47.03 |
| 0110 | Concrete pavement (10 1/2 in. non-reinforced, 15 FT. joints) (5021334) | SY | 9,844 | $81.00 | $105.00 | $110.00 | $106.00 | $100.65 | $150.00 |
| 0120 | Misc. tinted 10.5 inch PCCP (5029905) | SY | 573 | $120.15 | $143.00 | $175.00 | $129.00 | $154.48 | $156.00 |
| 0130 | Paved approach, 8 in. (6085008) | SY | 762 | $88.65 | $112.50 | $110.00 | $94.00 | $79.27 | $114.00 |
| 0140 | Misc. tinted 6 inch concrete median (6089905) | SY | 321 | $105.00 | $140.00 | $130.00 | $125.00 | $149.17 | $125.00 |
| 0150 | Concrete gutter type A (6091041) | LF | 516 | $47.00 | $45.00 | $75.00 | $49.00 | $88.83 | $75.00 |
| 0160 | Furnishing type 1 rock ditch liner (6096010A) | CY | 338 | $57.25 | $50.00 | $30.00 | $48.00 | $51.14 | $50.15 |
| 0170 | Furnishing type 2 rock ditch liner (6096020) | CY | 30 | $68.35 | $50.00 | $35.00 | $64.00 | $53.00 | $46.00 |
| 0180 | Placing type 1 rock ditch liner (6096041) | CY | 338 | $13.25 | $50.00 | $30.00 | $44.00 | $12.43 | $41.00 |
| 0190 | Placing type 2 rock ditch liner (6096042) | CY | 30 | $25.00 | $50.00 | $35.00 | $46.00 | $46.67 | $41.00 |
| 0200 | Misc. modified concrete curb and gutter, type A (6099903) | LF | 1,188 | $45.50 | $45.00 | $75.00 | $50.00 | $94.96 | $75.00 |
| 0210 | Misc. tinted 6 inch integral curb, type M (6099903) | LF | 278 | $36.50 | $15.00 | $100.00 | $30.00 | $148.76 | $48.00 |
| 0220 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 4 | $6,000.00 | $4,250.00 | $4,500.00 | $4,800.00 | $12,500 | $4,950.00 |
| 0230 | Misc. temporary traffic control (6169901) | LS | 1 | $35,720 | $10,317 | $13,976 | $15,000 | $22,625 | $15,374 |
| 0240 | Misc. portable traffic signal system (6169902) | EACH | 1 | $49,750 | $35,953 | $45,000 | $38,000 | $37,500 | $41,250 |
| 0243 | Temporary traffic barrier, contractor furnished retained (6173600D) | LF | 1,150 | $40.35 | $36.20 | $32.00 | $45.00 | $45.25 | $39.82 |
| 0247 | Relocating temporary traffic barrier (6175010A) | LF | 1,150 | $12.50 | $14.34 | $10.00 | $14.00 | $17.93 | $15.77 |
| 0250 | Mobilization (6181000) | LS | 1 | $90,587 | $217,000 | $249,345 | $260,000 | $60,969 | $275,000 |
| 0260 | Preformed thermoplastic pavement marking, 4 in., white (6200003) | LF | 4,453 | $4.95 | $5.00 | $4.00 | $4.50 | $6.25 | $4.40 |
| 0270 | Preformed thermoplastic pavement marking, 4 in yellow (6200006) | LF | 6,583 | $4.95 | $5.00 | $4.00 | $4.60 | $6.25 | $4.40 |
| 0280 | Preformed thermoplastic pavement marking, 24 in. yellow (6200018) | LF | 367 | $29.50 | $18.00 | $24.00 | $26.00 | $22.50 | $26.40 |
| 0290 | Cold applied tape pavement marking, 24 in. X 36 in. yield line triangles (6200040A) | EACH | 32 | $92.00 | $80.00 | $75.00 | $90.00 | $100.00 | $82.50 |
| 0300 | Temporary removable marking tape 4 in., white (6205301B) | LF | 1,415 | $3.10 | $3.00 | $2.50 | $2.90 | $3.75 | $2.75 |
| 0310 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 1,500 | $1.85 | $2.00 | $1.50 | $2.00 | $2.50 | $1.65 |
| 0320 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 1,415 | $1.85 | $2.00 | $1.50 | $2.00 | $2.50 | $1.65 |
| 0330 | 24 in. white class 1 pavement marking paint (18-mil, type P beads) (6206124B) | LF | 36 | $14.75 | $10.00 | $12.00 | $18.00 | $12.50 | $13.20 |
| 0340 | Pavement marking removal (6207001) | LF | 4,366 | $2.50 | $1.50 | $2.00 | $3.20 | $1.88 | $2.20 |
| 0350 | Separation geotextile (6240104A) | SY | 2,291 | $3.15 | $4.00 | $3.00 | $6.00 | $4.54 | $5.00 |
| 0360 | Contractor furnished surveying and staking (6274000) | LS | 1 | $15,000 | $18,000 | $20,000 | $4,200.00 | $28,500 | $49,500 |
| 0370 | 15 in. pipe group B (7250315A) | LF | 182 | $93.90 | $70.00 | $40.00 | $82.00 | $266.13 | $98.00 |
| 0380 | 18 in. pipe group B (7250318A) | LF | 56 | $122.00 | $75.00 | $50.00 | $94.00 | $355.71 | $105.00 |
| 0390 | 12 in. pipe group A (7261012) | LF | 20 | $127.25 | $75.00 | $50.00 | $82.00 | $179.06 | $60.00 |
| 0400 | 18 in. pipe group A (7261018) | LF | 411 | $126.75 | $85.00 | $55.00 | $85.00 | $104.24 | $125.00 |
| 0410 | 24 in. pipe group A (7261024) | LF | 696 | $122.50 | $95.00 | $60.00 | $98.00 | $117.69 | $150.00 |
| 0420 | Precast concrete drop inlet 3 FT X 2 FT (7311032) | FT | 6 | $1,760.00 | $1,750.00 | $1,300.00 | $1,400.00 | $2,073.08 | $937.89 |
| 0430 | Precast concrete drop inlet 3 FT X 3 FT (7311033) | FT | 31 | $1,310.00 | $1,335.00 | $900.00 | $1,260.00 | $1,629.56 | $1,096.31 |
| 0440 | 12 in. or allowed substitute group A flared end section (7320612A) | EACH | 2 | $1,030.00 | $1,350.00 | $500.00 | $320.00 | $1,194.38 | $1,394.77 |
| 0450 | 18 in. or allowed substitute group A flared end section (7320618A) | EACH | 6 | $1,210.00 | $1,600.00 | $750.00 | $425.00 | $965.00 | $1,200.00 |
| 0460 | 24 in. or allowed substitute group A flared end section (7320624A) | EACH | 6 | $1,415.00 | $1,800.00 | $1,000.00 | $598.00 | $1,105.00 | $1,300.00 |
| 0470 | Mulching (8025006) | ACRE | 1.80 | $2,150.00 | $2,500.00 | $1,750.00 | $2,600.00 | $2,388.89 | $1,925.00 |
| 0480 | Seeding - cool season grasses (8051000A) | ACRE | 1.80 | $3,450.00 | $2,800.00 | $2,800.00 | $3,000.00 | $2,388.89 | $3,080.00 |
| 0490 | Rock ditch check (8061005) | LF | 220 | $17.25 | $20.00 | $14.00 | $22.00 | $36.19 | $15.40 |
| 0500 | Sediment removal (8061016) | CY | 55 | $37.50 | $35.00 | $20.00 | $36.00 | $39.66 | $28.77 |
| 0510 | Temporary seeding (8061017) | ACRE | 0.90 | $1,105.00 | $1,750.00 | $900.00 | $2,000.00 | $4,083.33 | $990.00 |
| 0520 | Silt fence (8061019) | LF | 4,400 | $3.70 | $4.15 | $3.00 | $4.25 | $1.99 | $3.30 |
| 0530 | Section: 0002 lighting items - JSE0150 lighting pole, 30 FT. or 9.0 M, type at (9011030) | EACH | 8 | $3,850.00 | $2,430.00 | $3,136.00 | $3,140.00 | $3,417.19 | $2,742.30 |
| 0540 | Bracket arm, 6 FT. or 1.8 M (9011106) | EACH | 8 | $850.00 | $595.00 | $691.00 | $691.00 | $836.72 | $672.10 |
| 0550 | Luminaire, LED-B (9011312) | EACH | 8 | $630.00 | $495.00 | $510.00 | $510.00 | $696.09 | $551.10 |
| 0560 | Base mounted control station 240 volt - 4 circuit (9012230) | EACH | 1 | $11,500 | $8,500.00 | $9,300.00 | $9,400.00 | $10,625 | $10,405 |
| 0570 | Conduit, 3 in. rigid, in trench (9013003) | LF | 1,016 | $24.55 | $0.00 | $20.00 | $21.00 | $1.25 | $17.25 |
| 0580 | Conduit, 3 in. rigid, pushed (9014003) | LF | 216 | $30.70 | $38.00 | $25.00 | $26.00 | $47.50 | $41.80 |
| 0590 | Pull box, preformed class 1 (9016110) | EACH | 6 | $1,660.00 | $2,538.00 | $1,350.00 | $1,400.00 | $3,172.50 | $3,006.30 |
| 0600 | Cable, 10 AWG 1 conductor, pole and bracket (9017110) | LF | 860 | $1.85 | $1.00 | $1.50 | $1.50 | $1.25 | $1.10 |
| 0610 | Cable-conduit, 1 in., 2 conductors and 1 bare neutral, 8 AWG (9017407) | LF | 1,320 | $6.75 | $5.50 | $5.50 | $6.00 | $6.88 | $6.05 |
| 0620 | Pole foundation (30 FT. or 9.0 M mounting height) (9018230) | EACH | 8 | $2,030.00 | $967.50 | $1,653.00 | $1,700.00 | $1,209.38 | $1,092.85 |
| 0630 | Power supply assembly, type 1, 240/120 volt service, lighting only (9018610) | EACH | 1 | $11,050 | $7,500.00 | $9,000.00 | $9,200.00 | $9,375.00 | $9,301.52 |
| 0640 | Section: 0003 signing items - JSE0150 structural steel posts (9031210) | LB | 260 | $15.75 | $24.00 | $10.00 | $14.00 | $16.01 | $14.09 |
| 0650 | Breakaway assembly (perforated square steel tube) (9031241) | EACH | 4 | $485.50 | $250.00 | $500.00 | $550.00 | $494.29 | $434.97 |
| 0660 | 2 in. PSST post - 12 GA. (9031270A) | LF | 306 | $23.25 | $15.00 | $28.00 | $24.00 | $23.55 | $20.72 |
| 0670 | Driven post anchor for 2 in. PSST - 12 GA. (9031271A) | EACH | 32 | $300.00 | $125.00 | $300.00 | $265.00 | $303.64 | $267.20 |
| 0680 | 2.25 in. PSST post insert (6 FT.) - 12 GA. (9031272A) | EACH | 4 | $480.00 | $212.00 | $175.00 | $395.00 | $487.81 | $429.28 |
| 0690 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 122 | $28.50 | $22.00 | $34.00 | $40.00 | $29.01 | $25.53 |
| 0700 | Driven post anchor for 2.5 in. PSST - 7 GA. (9031281A) | EACH | 8 | $495.00 | $125.00 | $450.00 | $500.00 | $504.18 | $443.67 |
| 0710 | SH-flat sheet (9035004A) | SF | 340 | $27.25 | $37.00 | $38.00 | $30.00 | $27.70 | $24.38 |
| 0720 | SHF-flat sheet fluorescent (9035069A) | SF | 88 | $38.25 | $50.00 | $40.00 | $35.00 | $38.96 | $34.29 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of August 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way