MoDOT contract 250314-D01 bid tabulation

J5P3537 - ROUTE 63 - PHELPS COUNTY. Let by Missouri DOT on March 14, 2025, Phelps, Central. 3 bids received; low bid $1,560,000 by Kozeny-Wagner, Inc..

Owner
Missouri DOT
Letting
14 MAR 2025
Pay items
42
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Kozeny-Wagner, Inc.$1,560,000Low
2Louis-Company, LLC$1,622,194+4.0%
3West Plains Bridge & Grading, LLC$1,635,000+5.0%
MoDOT contract 250314-D01: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Kozeny-Wagner, Inc.2. Louis-Company, LLC3. West Plains Bridge & Grading, LLC
0010Signet dbe reporting (1081000)LS1$1,000.00$1,000.00$1,000.00
0020Clearing and grubbing (2013000)ACRE1$2,500.00$4,399.19$5,500.00
0030Removal of improvements (2022010)LS1$9,805.06$19,035$20,000
0040Bituminous pavement mixture PG64-22, (BP-1) (4011209)TON59.10$182.00$409.97$182.00
0050Tack coat (4071005)GAL55$15.00$20.50$15.00
0060Furnishing type 2 rock blanket (6113020)CY348$65.00$109.95$70.00
0070Placing type 2 rock blanket (6113040)CY348$25.00$15.78$35.00
0080Impact attenuator 55 MPH (sand barrel array) (6122012)EACH2$2,400.00$3,211.45$2,350.00
0090Replacement sand barrel (6122020)EACH2$200.00$580.79$425.00
0100Impact attenuator (relocation) (6122030)EACH2$1,000.00$2,664.82$1,950.00
0110Truck mounted attenuator (TMA) (6123001)LS1$1,000.00$54,663$4,500.00
0120Construction signs (6161005)SF392$7.50$10.25$7.50
0130Advanced warning rail system (6161008)EACH2$45.00$45.10$45.00
0140Changeable message sign without communication interface, contractor furnished retained (6161098A)EACH8$2,500.00$4,236.38$2,500.00
0150Work zone traffic signal system (6162000A)EACH1$12,500$54,663$12,500
0160Temporary long-term rumble strips (6162002)EACH12$1,000.00$1,639.89$1,000.00
0170Temporary traffic barrier, contractor furnished retained (6173600D)LF1,200$41.00$38.26$28.00
0180Relocating temporary traffic barrier (6175010A)LF1,200$19.00$18.45$13.50
0190Mobilization (6181000)LS1$161,432$48,781$111,746
02004 in. yellow high build waterborne pavement marking paint, type L beads (6205901A)LF3,144$1.50$2.73$1.50
02106 in. white high build waterborne pavement marking paint, type L beads (6205902A)LF1,323$1.50$3.07$1.50
0220Pavement marking removal (6207001)LF1,345$4.00$4.10$7.50
02304 in temporary pavement marking paint (6208076)LF3,095$2.00$1.37$1.80
0240Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001)SY545$20.00$41.00$25.00
0250Contractor furnished surveying and staking (6274000)LS1$5,000.00$10,933$20,000
0260Mulching (8025006)ACRE1$2,800.00$3,826.40$1,500.00
0270Seeding - warm season grasses (8052000A)ACRE1$2,500.00$3,416.43$3,400.00
0280Sediment removal (8061016)CY22$25.00$62.41$10.00
0290Silt fence (8061019)LF2,178$4.00$5.47$2.90
0300Type C berm (8061050)LF296$35.00$47.83$30.00
0310MGS guardrail, 8 FT. posts, 6 FT. - 3 in. spacing (6061061)LF2,050$28.97$43.73$28.97
0320MGS bridge approach transition section (regular/no curb) (6061069)EACH4$3,639.44$5,466.29$3,639.44
0330MGS end anchor (6061080)EACH4$1,584.32$3,826.41$1,584.32
0340Removal of miscellaneous acm (non-friable) (2024043)SF29$300.00$403.28$300.00
0350Removal of existing bridge deck (2162500)SF11,843$20.00$22.49$16.00
0360Slab on steel (7034212)SY1,322$484.00$355.00$560.00
0370Type D barrier (7034219A)LF735$127.00$159.41$170.00
0380Substructure repair (unformed) (7040102)SF10$325.00$478.24$145.00
0390Mechanical bar splice (7061070)EACH1,081$53.00$50.27$60.00
0400Slab drain (7123610)EACH64$390.00$783.17$625.00
0410Surface preparation for applying epoxy-mastic primer (7125102)LS1$5,500.00$28,698$5,500.30
0420Gray epoxy-mastic primer (7125961)LS1$5,500.00$12,251$5,500.30
MoDOT contract 250314-D01: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of March 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy